Implementor's Perspective on Project Development and Issues
In-depth analysis of projects under the PSDP by NLC, covering completed and ongoing initiatives along with associated costs. Highlights key challenges faced, including non-cohesive development plans, unrealistic goals, and delayed decisions. Suggested improvements focus on due diligence at the planning stage and the use of PPP mode.
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
PSDP PROJS BY NLC Projs No of Projs Cost (Rs Mn) Completed 16 37,891 Ongoing 11 36,358 TOTAL 27 74,249 2
COMPLETED PROJS Cost Rs Million 8,979 1,899 2,405 24,609 Punjab Sindh KPK Balochistan 3
ONGOING PROJS COST RS MILLION 3,198 3,710 16,797 12,142 510 Punjab Sindh KPK Balochistan AJK&GB 4
ISSUES 5
Non Cohesive Dev Plans Unrealistic Goals / Timelines Cash Flow Issues Budget Cuts Scope / Design changes VOs / Revisions Delayed Decisions Lengthy Approval Channels Hasty Surveys Design Inaccuracies Plan, Feasibility Handover, Fin close Survey, Design PROJECT LIFECYCLE Delayed TOCs Delayed Final Bills Execution, Monitoring Funding, Approval 6
SUGGESTED IMPROVEMENTS Due Diligence at Planning Stage Time spent on detailed feasibility / ground surveys ensures:- Economical / Accurate Design Minimum Variations / Revisions Smooth Execution Timely Completion No cost overruns Curtail approval / decision making process (E-Processing) PPP mode to be encouraged Funds visibility during proj lifecycle GST Exemption for Public Sector Projects 8
THANKS 9