Detailed Status and Plans of MEBT BPM Stripline Project

Slide Note
Embed
Share

This document outlines the detailed status and plans for the MEBT BPM Stripline project, including the 3D electromagnetic and mechanical design status, prototype fabrication process, RF measurements, magnetic checks, and production plan for required pieces. It also covers verifications and tests such as metrology, magnetic properties, and acceptance tests, along with identified risks and their current status.


Uploaded on May 14, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. MEBT BPM Stripline Plans S. Varnasseri On behalf of BPM team 12-13 July 2017, Bilbao MEBT BPM Plans

  2. MEBT BPM Stripline Status 3D Electromagnetic and mechanical Design: Finished February 2016 Prototype fabrication process started: April 2016 Finished first prototype: April 2017 RF measurements of prototype finished: April 2017 Magnetic checks finished: May 2017 BPM CDR: May 2017 Long lead items are ordered: June-July 2017 Mechanical improvements (in the Arturo presentation): June 2017 Manufacturing readiness review: July 2017 MEBT BPM Plans

  3. Pieces production plan Before welding process BPM required pieces to fabricate/order Absolute Quantity Ordering Quantity BPM n Start order 2017 Piece Lead time Receive Priority ~2.5 Months 1 Feedthrough SMA, W-NM 64 75 1-8 High (Aug-17) June 2 MEBT-BP-0102-ESS.00-MEC 64 75 1-8 ~ 2 Months High(Aug-17) June 3 MEBT BP 0101 ESS.03 MEC 32 40 1-8 ~ 3 Months High(Sep-17) July 4 MEBT BP 0103 ESS.02 MEC 32 50 1-8 ~ 3 months High(Sep-17) July 5 MEBT BP 0201 ESS.03 MEC 5 Types 5 Types 1-8 ~ 3 Months High(Sep-17) July 6 Rotating CF Flange 16 20 1-8 ~ 2 Months Medium(Oct-17) Sep. 7 Bellow type1 (short) 1 5 ~ 2 Months Medium(Nov-17) Sep. 8 Bellow type2 (long) 5 1,2,3,6,8 ~2 Months Medium(Nov-17) Sep. MEBT BPM Plans

  4. Verifications and Tests I. I. Pieces verifications Pieces verifications Metrology Metrology Magnetic properties Magnetic properties Fabrication/Welding process verifications Fabrication/Welding process verifications Metrology Metrology Vacuum leakage tests Vacuum leakage tests RF measurements RF measurements III. Acceptance tests and verifications Acceptance tests and verifications RF measurements RF measurements Magnetic permeability Magnetic permeability Metrology Metrology Vacuum leakage tests Vacuum leakage tests II. II. III. MEBT BPM Plans

  5. Risks Risks involved involved Expected Risk Expected Risk Status Status Closed (Prototype measurements April 2017) Do not fulfill RF Do not fulfill RF specifications specifications Closed (Prototype measurements April 2017) Do not fulfill Magnetic Do not fulfill Magnetic properties properties Partially (Prototype April 2017) Improved fabrication/welding June 2017 BPM#3 September 2017) Partially (Prototype April 2017) Improved fabrication/welding June 2017 BPM#3 September 2017) Acceptance test plan DOCUMENTED (MEBT-BI-BP93-01) Fulfill tight Metrology Fulfill tight Metrology specifications specifications Fulfill Fulfill Vacuum Vacuum requirements requirements MEBT BPM Plans

  6. BPM provisional schedule BPM provisional schedule April April- - 2016 April April- - 2017 minor but important fabrication modifications. June June- - 2017 2017: Long lead components production started Sep Sep- -2017 2017: First BPM production ready to start (BPM#P3) Nov Nov- -2017 2017: RF and mechanical checks for BPM#P3 Dec Dec- -2017 2017: Series production BPM#1-8 May May- -2018 2018: BPM#1-8 production finished July July- - 2018 2018: BPM#1-8 measurements and verifications finished 2016: Finish design (electromagnetic and mechanical) 2017: First prototype ready, results show the need for some MEBT BPM Plans

Related


More Related Content