Analysis and Decision-Making for MEBT Kicker Technology in PIP-II Project

Slide Note
Embed
Share

The final design and procurement readiness review for the PIP-II MEBT kickers involved evaluating alternatives, costs, and schedules, with a focus on 200-Ohm kicker technology. Developments in kicker design, testing, and decision-making points, such as choosing the 200-Ohm system over the 50-Ohm concept, were highlighted for efficient injection into the Booster. Various partnerships and technical considerations were crucial in guiding the project direction.


Uploaded on Aug 14, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. MEBT kicker FDR/PRR Alternatives Analysis, Cost & Schedule Lionel PROST Final Design/Procurement Readiness Review for the PIP-II MEBT kickers 2 August 2018 In partnership with: India/DAE Italy/INFN UK/STFC France/CEA/Irfu, CNRS/IN2P3

  2. Outline Alternatives Analysis 200-Ohm kicker as the baseline for the PIP-II chopping system Cost Schedule 2 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  3. Reminder In 2010 RFQ frequency dropped from 325 MHz to 162.5 MHz Concept with multiple (2) kickers 3 envelopes of the transmitted (a) and chopped- out (b) bunches simulated with TraceWin. Appears doable but still challenging (assumes CW operation) Two proposals: 50-Ohm and 200-Ohm structures 3 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  4. Kickers development Two versions developed in parallel 1 of each prototype installed at PIP2IT 50-Ohm 24 electrodes per plate connected in vacuum by 50 Ohm cables Driver: commercially available linear amplifier Concept tested with similar lower-power amplifier 200-Ohm Helix as a travelling-wave structure Driver developed at Fermilab Broadband, DC-coupled switches in push-pull configuration A. Chen G. Saewert D. Sun A. Chen 4 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  5. Decision point (~September 2017) Before the CD-1 review, it was decided that the Project should not continue to carry the cost of having 2 kicker designs in development Needed to set a baseline plan 200-Ohm kicker technology of choice At that time 200-Ohm system tests had demonstrated that it could provide the appropriate kicking pattern for bucket-to-bucket injection into the Booster The same proof-of-principle would have required the purchase of expensive power amplifiers not compatible with the project s budget profile 5 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  6. 50-Ohm concept concerns not addressed Did not identify a linear power amplifier with proper characteristics readily available off-the-shelf Pre-distortion of the driving signal to correct for non-linearities only at the proof-of-principle level with low-power amplifier, matched dummy load and short sequence of bunches Unlike the 200-Ohm system case, the scheme with 50-Ohm kickers requires deflecting both the passing and to- be-removed bunches variations of the pulse voltage amplitude cause additional motion of the passing bunches stability issues Simulation made in MathCAD by V. Lebedev 6 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  7. 50-Ohm concept concerns not addressed (cont) Pre-distortion implies that the LLRF system needs to generate a driving signal of exact shape and amplitude 200-Ohm design uses switches that only need binary signals 7 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  8. 1.1% duty factor vs. CW Originally, the 50-Ohm system offered a clearer path to CW operation 50-Ohm kicker development ahead of 200-Ohm s Elimination of the CW requirement dramatically reduces difficulties for the design of the 200-Ohm kicker driver Requirements for 50-Ohm s PAs kicker likely unchanged 0.55 ms @ 20 Hz CW-compatible 8 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  9. Bottom line 200-Ohm kicker as the baseline technology for the MEBT chopping system Relatively low up-front cost Most expensive single part is the vacuum vessel (~$20k) Cost of PAs for 50-Ohm system: $500k-$1M (estimate) Flexibility: design and fabrication at FNAL 50-Ohm kicker design as back-up Appears in the Risk Registry 9 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  10. Cost (for 2 production kickers) M&S Mechanical structure Feedthroughs (for 2): $40k (already in procurement) Tooling: $5k Cost for 1 unit, k$ Parts Machinable Nitride Ceramics (Photoveel II) Electro- and laser welding Ground tube & brazing Ceramic stands Vacuum box Other misc. 7 5 5 4 8 6 35 Total for 2 kickers: $115,000 Total 10 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  11. Cost (for 2 production kickers) M&S Item Qty Cost, $ Totals, $ Driver electronics ~$50k for two kicker drivers Photonic components Laser SOA Amplifier/switch Fiber optic, cable, connectors 2 2 1,300 3,900 2,500 Misc. PCBs, parts, chassis 1,000 Photonics subtotal 8,700 FET Drivers & Loads Ceramic substrates FETs, misc. parts, PCBs Loads 10 1,800 1,200 2,200 8 Drivers subtotal 5,200 Misc. cable & Hardware 1-1/4 Heliax Connectors, adapters 280 2,400 1,000 Misc. subtotal 3,400 Equipment Scope, 4-Chan., 1 GHz 600V dc, 2.6 A PS Computer Relay rack Misc. PSs, instrumentation 20,000 3,600 1,000 2,000 1,200 2 1 Equip. subtotal Machine shop 27,800 5,000 50,100 TOTAL 11 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  12. Cost (for 2 production kickers) FTE Mechanical structure 25% FTE Principal Engineer for 8 months 30% FTE Designer for 2 months 5% FTE Designer for 5 months 50% FTE Mechanical Tech. for 3 months 75% FTE Senior Electronics Engineer for 1 month Driver electronics 60% FTE Senior Electronics Engineer for 11 months 55% FTE Electronics Technician for 10 months 5% FTE Software Developer for 2 months 12 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

  13. Schedule Driven by fabrication of driver electronics ~1 year once the approval to proceed is received Mechanical structure 8-9 months once the approval to proceed is received Drawings already complete (~1 month worth) Ready for offline tests and tuning: July/August 2019 Ready for installation on the beam line at PIP2IT ~2 weeks later 13 8/2/2018 L. Prost | MEBT kicker FDR/PRR | Alt. Analysis, Cost & Schedule

Related


More Related Content