Building Project Updates Presentation - July 28, 2015

Slide Note
Embed
Share

Providing detailed progress updates on major building projects including L'Ouverture, Wyman, Pruitt, and Madison. Updates on completion status, ongoing work, and scheduled turnovers to SLPS. Key activities, such as furniture moves, facility repairs, and program relocations, are highlighted for each project.


Uploaded on Oct 01, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Building Project Updates Presentation to the Special Administrative Board Yvonne Green July 28, 2015

  2. Overview Update on major building projects: L Ouverture (AESM Middle relocation) Wyman (CSMB relocation) Pruitt (KIPP new building) Madison (new Therapeutic School)

  3. LOuverture Project has been substantially completed as of July 1, 2015 Working on punch-list items In process of coordinating furniture move into classrooms week of July 20th Currently working on repairing water main and preparing for resurfacing playground/ parking lot L Ouverture is scheduled to be turned over to SLPS on or before July 31st Closed Chouteau and Spring leased building on schedule (June 25, 2015) - awaiting deposit

  4. LOuverture

  5. Wyman Modular classrooms are arriving and being installed Hallway floor refinishing work is 70% complete Student lockers on back order but should be received and installed by late August Construction of the ADA hallway and ramp have begun Wyman is scheduled to be turned over to SLPS on or before July 31st

  6. Wyman

  7. Wyman Modular Science Labs

  8. Pruitt Building is substantially complete Working on punch list items and heating unit repairs KIPP has moved into the building and have been issued 3 sets of keys Payments have been made promptly when billed

  9. Pruitt

  10. Madison Moved Special Education functions from McKinley Moving the Epworth program from Fanning the week of July 27th Hazmat remediation for lower grades will be completed by July 31st

  11. Questions?

Related