North Mason Regional Fire Authority Headquarters Fire Station Project Review

 
North Mason Regional Fire Authority
Headquarters Fire Station
Project Review Committee | Project Approval
Process
March 26, 2020
ATTACHMENT A – NORTH MASON REGIONAL FIRE AUTHORITY HQ FIRE STATION
PROJECT ORGANIZATIONAL CHART
D-B 
RFQ/RFP -
 
10%
Design 
-
 
10%
Construction 
-
 
15%
Aron Aston
Estimator
Hill 
International,
 
Inc.
D-B 
RFQ/RFP -
 
10%
Design 
-
 
10%
Construction 
-
 
15%
Mamie Kamada
Document Controls Specialist
Hill 
International,
 
Inc.
D-B 
RFQ/RFP -
 
10%
Design 
-
 
10%
Construction 
-
 
15%
D-B 
RFQ/RFP -
 
50
%
Design 
-
 
80
%
Construction 
-
 
60
%
Construction
Manager
Merry Anna Valdez
Project  Scheduler
Hill 
International,
 
Inc.
Project Committee
Scott Cooper, Assistant Fire Chief, Design Advisor
Renee Wassenaar, Contract and Procurement
Advisor
Charles Westover
Project Manager
Hill International, Inc.
D-B RFQ/RFP - 30%
Design - 100%
Construction - 10%
Gregory Heinz
Principal-in-Charge
Hill International, Inc.
D-B RFQ/RFP - 10%
Design - 5%
Construction - 5%
D-B RFQ/RFP - 10%
Design - 10%
Construction - 10%
Construction
Manager
Beau Bakken
Project Director
Fire Chief
North Mason Regional Fire Authority
Board of Commissioners
D-B RFQ/RFP - 10%
Design - On-call
Construction - On-call
Robynne Thaxton (Parkinson)
JD, DBIA DB Legal Counsel
Thaxton Parkinson, PLLC
Becky Blankenship
Construction Manager
Hill International, Inc.
D-B RFQ/RFP - 100%
Design - 20%
Construction - 100%
Progressive
Design-Builder
Design 
-
 
10
0
%
Construction 
-
 
1
00
HQ Fire Station Facility Overview
Replace existing facility that no longer meets our
needs
New facility - approximately 20,200 SF
Office and living space, including:
Kitchen/dining area;
Fitness room;
Day room;
Sleeping quarters;
Indoor classes and training; and
Apparatus bay for fire, ambulance and command
vehicles
Proposed HQ Fire Station Site
HQ Fire Station Project Budget
Professional Services
  
$       700,000
Construction Cost 
  
$    7,100,000
Off-site Costs
   
$       360,000
Contract Admin/Other
  
$       200,000
NMRFA Contingency 
  
$       700,000
Other Related Project Expenses
 
$       150,000 
WSST
    
$       790,000
Total Project Cost
   
$  10,000,000
Schedule
D-B RFQ Advertisement
  
Apr 02, 2020
D-B SOQ Due
   
Apr 29, 2020
Shortlist Finalists
   
May 06, 2020
Issue RFP
    
May 12, 2020
DB Team/Owner Interactive Mtg
 
May 18, 2020
Proposal Due
   
May 26, 2020
DB Team Interviews
   
Jun 10, 2020
Selection of DB Team
  
June 22, 2020
NTP
     
Jul 2020
Set GMP
    
Jan 2020
Construction Phase
  
Jan 2021 thru Mar 2022
Procurement Approach
Request for Qualifications
Successful Experience with Projects of Similar Scope and Complexity – Fire
Stations or other Municipal facilities with unique equipment or functions
Team Organization
Experience developing GMP collaboratively with Owner
Shortlist no more than three finalists
History in soliciting and/or utilizing OMWBE subcontractors
Request for Proposal
Management approach specific to the project
Innovation and Problem Solving
Interactive Proprietary Meetings
Statutorily required evaluation factors
Price related factor:  Fee
$5,000 honorarium
Limited required proposal submittals
Consistent with other projects
Design-Build Agreement
1.
Phase 1 - Validation and GMP Development Period
Validate information from the Owner
Examine options to identify innovation
Commercially reasonable examination of site
Develop Basis of Design Documents, Project
Schedule, GMP
Contract Amendment
2
.
 
Phase 2 - GMP Execution Period
Complete Design
Construction
Close out
Benefits of Design-Build Delivery
RCW 39.10.300(1)(b) “Greater Innovation or efficiencies between the
designer and the builder”
Maximum possibility for coordination of design and construction phasing to
provide greatest project value, cost efficiency and design for specialized fire
equipment and processes.
RCW 39.10.300 (1)(c) “significant savings in project delivery time”
Progressive Design-Build is the fastest delivery method. Starting construction
work prior to completion of design results in a significantly reduced schedule.
An earlier completion date for the NMRFA HQ Fire Station will allow greater
efficiency in emergency response services at an earlier date. This is critical for
serving a broader portion of the community as soon as possible.
RCW 39.10.280(2)(a) “Substantial Fiscal Benefit”
The budget is limited to fit within the Fire Authority’s project budget.  The
Design-Builder will be required to design within that budget.
The Design-Builder’s involvement in the development of the scope shifts more
risk of the performance of the project to the design-build team.
With one team managing the coordination of the various aspects of the
project, the Fire Authority’s risk of claims by various contractors performing
adjacent projects are reduced.
Additional Questions
 
Q
U
E
S
T
I
O
N
The relationship of the Design-Builder to those listed in the organization
chart is unclear.
R
E
S
P
O
N
S
E
Organization chart has been updated to clarify the relationship of the
Design-Builder to the rest of the project team.
Additional Questions
 
Q
U
E
S
T
I
O
N
Was an Independent Cost Estimator considered for this project?
R
E
S
P
O
N
S
E
During our early programming phase, we engaged an Independent Cost
Estimator to validate our initial target budget.  For the next project
phase, we’ve included a cost estimator on our team, as shown on our
Organizational Chart. Aaron Aston is an employee of our 3rd party
consultant, Hill International. He has recent experience with fire stations
and with many other projects in the greater Seattle area, and is highly
familiar with construction cost trends as they pertain to the proposed
project.
Additional Questions
 
Q
U
E
S
T
I
O
N
W
h
a
t
 
l
e
v
e
l
 
o
f
 
c
o
n
s
t
r
u
c
t
i
o
n
 
c
o
n
t
i
n
g
e
n
c
i
e
s
 
i
s
 
i
n
c
l
u
d
e
d
 
i
n
 
t
h
e
 
P
r
o
j
e
c
t
B
u
d
g
e
t
 
o
n
 
P
a
g
e
 
1
 
o
f
 
8
?
R
E
S
P
O
N
S
E
We are at a very conceptual phase in planning for this project, so the
breakdown shown on Page 1 is only an estimate. At this time we have
assumed a construction contingency of 5% to 6%, and we expect the
allocations of cost will change as we align the design with the GMP.
 
Thank you!
Slide Note
Embed
Share

The North Mason Regional Fire Authority is undergoing a project to build a new headquarters fire station that better meets their needs. The project involves various stakeholders and includes constructing a facility with office and living spaces, a kitchen, fitness room, sleeping quarters, and apparatus bay. The project budget, schedule, and organizational chart provide insights into the approval process and key milestones.


Uploaded on Sep 09, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. North Mason Regional Fire Authority Headquarters Fire Station Project Review Committee | Project Approval Process March 26, 2020

  2. ATTACHMENT A NORTH MASON REGIONAL FIRE AUTHORITY HQ FIRE STATION PROJECT ORGANIZATIONAL CHART Beau Bakken Project Director Fire Chief Robynne Thaxton (Parkinson) JD, DBIA DB Legal Counsel Thaxton Parkinson, PLLC North Mason Regional Fire Authority Board of Commissioners Construction Manager D-B RFQ/RFP - 10% Design - On-call Construction - On-call D-B RFQ/RFP - 10% Design - 10% Construction - 10% Project Committee Gregory Heinz Principal-in-Charge Hill International, Inc. Scott Cooper, Assistant Fire Chief, Design Advisor Renee Wassenaar, Contract and Procurement Advisor Construction Manager D-B RFQ/RFP - 10% Design - 5% Construction - 5% D-B RFQ/RFP -50% Design -80% Construction -60% Charles Westover Project Manager Hill International, Inc. Becky Blankenship Construction Manager Hill International, Inc. Progressive Design-Builder D-B RFQ/RFP - 100% Design - 20% Construction - 100% D-B RFQ/RFP - 30% Design - 100% Construction - 10% Design -100% Construction -100 Aron Aston Estimator Hill International, Inc. Merry Anna Valdez Project Scheduler Hill International, Inc. Mamie Kamada Document Controls Specialist Hill International, Inc. D-B RFQ/RFP -10% Design -10% Construction -15% D-B RFQ/RFP -10% Design -10% Construction -15% D-B RFQ/RFP -10% Design -10% Construction -15%

  3. HQ Fire Station Facility Overview Replace existing facility that no longer meets our needs New facility - approximately 20,200 SF Office and living space, including: Kitchen/dining area; Fitness room; Day room; Sleeping quarters; Indoor classes and training; and Apparatus bay for fire, ambulance and command vehicles

  4. Proposed HQ Fire Station Site

  5. HQ Fire Station Project Budget Professional Services $ 700,000 Construction Cost $ 7,100,000 Off-site Costs $ 360,000 Contract Admin/Other $ 200,000 NMRFA Contingency $ 700,000 Other Related Project Expenses $ 150,000 WSST $ 790,000 Total Project Cost $ 10,000,000

  6. Schedule D-B RFQ Advertisement Apr 02, 2020 D-B SOQ Due Apr 29, 2020 Shortlist Finalists May 06, 2020 Issue RFP May 12, 2020 DB Team/Owner Interactive Mtg May 18, 2020 Proposal Due May 26, 2020 DB Team Interviews Jun 10, 2020 Selection of DB Team June 22, 2020 NTP Jul 2020 Set GMP Jan 2020 Construction Phase Jan 2021 thru Mar 2022

  7. Procurement Approach Request for Qualifications Successful Experience with Projects of Similar Scope and Complexity Fire Stations or other Municipal facilities with unique equipment or functions Team Organization Experience developing GMP collaboratively with Owner Shortlist no more than three finalists History in soliciting and/or utilizing OMWBE subcontractors Request for Proposal Management approach specific to the project Innovation and Problem Solving Interactive Proprietary Meetings Statutorily required evaluation factors Price related factor: Fee $5,000 honorarium Limited required proposal submittals Consistent with other projects

  8. Design-Build Agreement 1. Phase 1 - Validation and GMP Development Period Validate information from the Owner Examine options to identify innovation Commercially reasonable examination of site Develop Basis of Design Documents, Project Schedule, GMP Contract Amendment 2. Phase 2 - GMP Execution Period Complete Design Construction Close out

  9. Benefits of Design-Build Delivery RCW 39.10.300(1)(b) Greater Innovation or efficiencies between the designer and the builder Maximum possibility for coordination of design and construction phasing to provide greatest project value, cost efficiency and design for specialized fire equipment and processes. RCW 39.10.300 (1)(c) significant savings in project delivery time Progressive Design-Build is the fastest delivery method. Starting construction work prior to completion of design results in a significantly reduced schedule. An earlier completion date for the NMRFA HQ Fire Station will allow greater efficiency in emergency response services at an earlier date. This is critical for serving a broader portion of the community as soon as possible. RCW 39.10.280(2)(a) Substantial Fiscal Benefit The budget is limited to fit within the Fire Authority s project budget. The Design-Builder will be required to design within that budget. The Design-Builder s involvement in the development of the scope shifts more risk of the performance of the project to the design-build team. With one team managing the coordination of the various aspects of the project, the Fire Authority s risk of claims by various contractors performing adjacent projects are reduced.

  10. Additional Questions QUESTION The relationship of the Design-Builder to those listed in the organization chart is unclear. RESPONSE Organization chart has been updated to clarify the relationship of the Design-Builder to the rest of the project team.

  11. Additional Questions QUESTION Was an Independent Cost Estimator considered for this project? RESPONSE During our early programming phase, we engaged an Independent Cost Estimator to validate our initial target budget. For the next project phase, we ve included a cost estimator on our team, as shown on our Organizational Chart. Aaron Aston is an employee of our 3rd party consultant, Hill International. He has recent experience with fire stations and with many other projects in the greater Seattle area, and is highly familiar with construction cost trends as they pertain to the proposed project.

  12. Additional Questions QUESTION What level of construction contingencies is included in the Project Budget on Page 1 of 8? RESPONSE We are at a very conceptual phase in planning for this project, so the breakdown shown on Page 1 is only an estimate. At this time we have assumed a construction contingency of 5% to 6%, and we expect the allocations of cost will change as we align the design with the GMP.

  13. Thank you!