The Ministry of Electric Power in Myanmar has outlined an electrification plan for Southern Shan State, focusing on prioritizing villages without electricity along main roads and near the national grid. The plan includes constructing distribution lines, transformers, and encouraging local participation in funding. The detailed plan breaks down villages in Taungyyi, Loi Lem, and Lin Kae districts, estimating costs and infrastructure needs. The goal is to provide electricity to households in these areas and ensure efficient power distribution for improved living conditions.


Uploaded on Sep 16, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. The Republic of the Union of Myanmar Ministry of Electric Power Electricity Supply Enterprise Southern Shan State Priorities and Detailed Description of Electrication Plan For Southern Shan State Dated -21.Oct.2015

  2. Priority Electrification Project List for Southern Shan State The following facts are agreement after discussion with Chief Minister (Shan State) To be performed priority the villages still without Electricity, which have along the main road. To meet the electrical safety and voltage to establish priorities. To Build quality products with proper power distribution Line. The villages within 2 miles from National Grid Line.(11 kV Line) To be performed priority villages having householes more than 100 and above. To be explain the public of villages to construct the low voltage line by local fund. In areas with difficult transportation to go to all the relevant authorities spicy leaves. And then, the remain villages will be implemented containuously by National Electrification Plan. ESE (Southern Shan State) will implement the work done under management MOEP coordination especially with local Government. 2

  3. Electrification Plan for Villages of Southern Shan State (Within 2 miles from Existing 11 kV Distribution Line) To be Constructed o 11 kV Distribution Line ( 279 ) miles o 400 V Distribution Line (345.81 ) miles o 11/0.4 kV Distribution Transformer ( 236 ) Nos Loi Lem District No. of Village )Nos Household Estimated Cost (mil kyats) - ( 39 - ( 3031 ) - ( 2707.32 ) Taungyyi District No. of Village 236)Nos Household Estimated Cost (mil kyats) - ( - (21033) (18782.33 ) Lin Kae District No. of Village 14 )Nos Household Estimated Cost (mil kyats) - ( - ( 824 ) - ( 892.23 ) 3

  4. Electrification Plan for Villages of Southern Shan State (Within 2 miles from Existing 11 kV Distribution Line) Task by Regional To be construted Estimatedcost(MilKyats) 33/11 kV Tr; 11/0.4 kV TR; Nos of House hole No Township VillagesPopula- House hole 11 kV Line (Mile) 400 V Line (Mile) Estimated Cost (MilKyats) tion Store Installation Total MVA No KVA No 3177 0 271 16,357.01 2,425.32 18,782. 1 Taunggyi 234 100839 21033 21888 281 296.15 13293.88 33 2,707.3 2 2 Loi Lem 39 15350 3031 3027 39 4710 41 2,361.40 345.92 39.16 1757.853 3 Lin Kae 14 3357 824 815 10 1800 14 785.19 107.04 892.23 10.5 471.3345 3828 0 326 19,503.60 2,878.28 22,381. Total 287 119546 24888 25730 330 345.81 15523.1 88 4

  5. Detailed Electrification Plan for Taunggyi District (Within 2 miles from Existing 11kV Distribution Line) Taunggyi District No. of Village - ( 234 )Nos Household - (21888) Estimated Cost - (10370.11)(mil kyats) Yask Sout No. of Village - ( 36 )Nos Household Estimated Cost (3,420.59)(mil kyats) Shwe Naung No. of Village - ( 7 )Nos Household Estimated Cost (337.88)(mil kyats) Ayetharyar No. of Village - ( 6 )Nos Household Estimated Cost (470.75)(mil kyats) - (3498) Ywar Ngan - No. of Village - ( 26 )Nos Household Estimated Cost (2,138.19)(mil kyats) - (3956) - - (434) Yask Sout Pin Ta Ya - No. of Village - (30)Nos Household Estimated Cost (2,010.77)(mil kyats) - (2693) - Ywar Ngan - (514) Aung Ban - No. of Village - (4)Nos Household Estimated Cost (312.37)(mil kyats) Ho Pone - (379) Taunggyi Pin Ta Ya - No. of Village - ( 8 )Nos Household Estimated Cost (1,188.76)(mil kyats) Kyaut Ta Lone No. of Village - ( 19 )Nos Household Estimated Cost (1,880.91)(mil kyats) Shw e Nau ng - (691) Ayethar yar Taungg yi Ti Gyit Kalaw - No. of Village - (8)Nos Household Estimated Cost (510.88)(mil kyats) Naung Ta Yar No. of Village - (26)Nos Household Estimated Cost (1,842.56)(mil kyats) Pin Laung No. of Village - (33)Nos Household Estimated Cost (2,491.92)(mil kyats) Naung Shwe No. of Village - (20)Nos Household Estimated Cost (1,123.66)(mil kyats) Aung Ban - (675) Kyaut Ta Lone Naung Kae - Ti Gyit Naung Shwe - (2188) Naung Ta Yar Pin Laung - See Sai - (1898) Naung Kae - No. of Village - ( 5 )Nos Household Estimated Cost (490.82)(mil kyats) - (507) - - (12862) See Sai Pae Kone - No. of Village - ( 6 )Nos Household Estimated Cost (68.91)(mil kyats) - (566) - 5 - (1027) -

  6. Detailed Electrification Plan for Taunggyi District (Within 2 miles from Existing 11kV Distribution Line) To be construted 33/11 kV Tr; Estimated cost(MilKyats) Task by Regional Nos of Househol e 11/0.4 kV TR; Village s Populatio n Hous ehole 11 kV Line (Mile) 400 V Line (Mile) Estimated Cost (MilKyats) No Township Store Installation Total MVA No KVA No 1 Taunggyi 8 3168 660 691 11 2600 13 136.94 1,188.76 12 1,051.81 538.67 2 Ayetharyar 6 1833 514 514 7 800 8 410.07 60.68 470.75 6.3 282.80 3 Shwe Naung 7 2151 421 434 3 750 7 299.27 38.61 337.88 5.2 233.42 4 Kyaut Ta Lone 19 7269 2230 2188 30 3020 21 247.42 1,880.91 32.51,458.89 1,633.49 5 Naung Kae 5 2141 507 507 7 860 6 428.28 62.54 490.82 9.5 426.45 6 See Sai 6 2452 552 566 8 900 6 464.32 68.91 533.23 7.5 336.67 7 Naung Shwe 20 5256 989 1027 22 1450 20 965.90 157.76 1,123.66 21.6969.60 8 Aung Ban 4 1578 364 379 5 500 4 271.24 41.13 312.37 4.5 202.00 9 Pin Ta Ya 30 13844 2675 2643 21 4190 32 237.48 2,010.77 39.21,759.65 1,773.29 10 Ywar Ngan 26 17353 3956 3956 27 4050 37 263.92 2,138.19 39 1,874.27 1,750.67 11 Yosk Sout 36 18390 3116 3498 57 5280 46 455.91 3,420.59 53.22,388.09 2,964.68 12 Pin Laung 33 14250 2643 2862 34 4500 36 313.77 2,491.92 31.91,431.96 6 2,178.15 13 Naung Ta Yar 26 8223 1754 1898 41 1950 27 270.71 1,842.56 25.151,128.96 1,571.85

  7. Detailed Electrification Plan for Loi Lem District (Within 2 miles from Existing 11kV Distribution Line) Loi Lem District No. of Village Household Estimated Cost (mil kyats) - ( 39 )Nos - (3072) -(2,707.32 ) Mine Kaing Mine Shu Mine Naung + Wan Sin Mine Naung + Wan Sin No. of Village (3)Nos Household Estimated Cost (mil kyats) Mine Kaing - No. of Village ( 12 )Nos Household Estimated Cost (mil kyats) - Lae Char - (757) - (108.23 ) - (788) - (615.94 ) Kum Hein Loi Lem Kho Lem Mine PonNan Sam Mine Pon Khoe Lom No. of Village 3 )Nos Household Estimated Cost - (241.10 )(mil kyats) - ( No. of Village (10)Nos Household Estimated Cost (mil kyats) - - (171) - (1331) - (934.46 ) Nan Sam No. of Village 11 )Nos Household Estimated Cost (mil kyats) - ( - (654) - (836.62 ) 7

  8. Detailed Electrification Plan for Loilem District (Within 2 miles from Existing 11kV Distribution Line) Task by regional Estimate To be construted Estimated cost (MilKyats) Hous e hole Nos of House hole 33/11 kV Tr; 11/0.4 kV TR; Town ship Village s Popu - lation 11 kV Line (Mile ) No 400 V Line (Mile) d Installatio n Store Total cost (MilKyats ) MVA No KVA No 1 Mine Pon 3 794 168 171 6 200 3 241.10 4 179.56 204.13 36.97 2 Nan Sam 11 3129 628 654 12 1460 11 836.62 14.5 650.89 729.85 106.77 3 Kho Lem 10 7028 1319 1331 8 2100 12 934.46 13.25 594.78 828.39 106.07 4 Mine Kaing 12 3642 788 788 12 800 12 615.94 5.91 265.29 529.61 86.33 Mine Naung + Wan Sin 5 3 757 128 128 2 150 3 108.23 1.5 67.33 93.33 14.90 Total 39 15350 3031 3027 39 4710 41 2,361.40 345.92 2,707.32 39.16 1,757.85 8

  9. Detailed Electrification Plan for Lin Kae District (Within 2 miles from Existing 11kV Distribution Line) Moe Nal Lin Kae District No. of Village )Nos Household Estimated Cost (mil kyats) - ( 14 No. of Village )Nos Household Estimated Cost (mil kyats) - ( 14 - (851) - (892.23 ) - (851) - (892.23 ) Moe Nal Lin Kae Moke Mal Mine Pan 9

  10. Detailed Electrification Plan for Lin Kae District (Within 2 miles from Existing 11kV Distribution Line) Task by regional To be construted Estimated cost (MilKyats) Nos of House hole Town ship Popu- lation House hole No Villages Estimated Cost (MilKyats ) 33/11 kV Tr; 11/0.4 kV TR; 11 kV Line (Mile) 400 V Line (Mile) Installatio n Store Total MVA No KVA No 1 Moe Nal 14 3357 824 851 10 1800 14 785.19 107.04 10.5 471.33 892.23 Total 14 3357 824 815 10 1800 14 785.19 107.04 892.23 10.5 471.33 10

  11. The Statement of fiscal Yealy Budget Electrified Connection for Southern Shan State State Capital Budget for DRD (Mik kyat) State Capital Budget for ESE(Mil Kyat) Electrified Connection Total Cost for 11kV Line & 11/0.4 kV TR No Fiacial Year ON Grid Off Grid Total Cost for 400V Line Total Off Grid Village (Nos) Consumer (Nos) Village (Nos) Consumer (Nos) 1 2014-2015 Estimate (BE+RE) 1629.85 2444.78 4074.63 7437.96 10 3230 573 5630 2 2015-2016 Estimate (BE+RE) 3650.94 5476.39 9127.34 5520.42 115 35600 516 4950 3 2016-2017 Budget Estimate (BE) 4780.54 6354.57 11135.1 6520.55 70 22400 540 5230 Grand Total 10061.33 14275.75 24337.1 19478.95 195 61230 1629 15810 11

  12. Main Material List Transported to Taunggyi Dristract Office No Description Quantities Transported Site 1 11/0.4 kV Distribution Transformer 271 Nos Taunggyi Sub-Station -1,2,3 2 10 Mconcrete Pole 13749 Nos Taunggyi Sub-Station -1,2,3 3 ACSR 95 mm2 584 Ton Taunggyi Sub-Station -1,2,3 4 11 kV Disc Insulator with Fitting 5871 Set Taunggyi Sub-Station -1,2,3 5 11 kV Pin Insulator with Spindle 37002 Nos Taunggyi Sub-Station -1,2,3 6 Surge arresters, Disconnectors, Fuses 813 Set Taunggyi Sub-Station -1,2,3 7 Other Materials 1Lot Taunggyi Sub-Station -1,2,3 12

  13. Main Material List Transported to Loi Lem Office No Description Quantities Transported Site 1 11/0.4 kV Distribution Transformer 41 Nos Loi Lem District Office 2 10 Mconcrete Pole 1903 Nos Loi Lem District Office 3 ACSR 95 mm 85Ton Loi Lem District Office 4 11 kV Disc Insulator with Fitting 820 Set Loi Lem District Office 5 11 kV Pin Insulator with Spindle 5134 Nos Loi Lem District Office 6 Surge arresters, Disconnectors, Fuses 123 Set Loi Lem District Office 7 Other Materials 1 Lot Loi Lem District Office 13

  14. Main Material List Transported to Lin Kae Office No Description Quantities Transported Site 1 11/0.4 kV Distribution Transformer 14 Nos Moe Nal Sub-Station 2 10 Mconcrete Pole 511 Nos Moe Nal Sub-Station 3 ACSR 95 mm2 21Ton Moe Nal Sub-Station 4 11 kV Disc Insulator with Fitting 227 Set Moe Nal Sub-Station 5 11 kV Pin Insulator with Spindle 1389 Nos Moe Nal Sub-Station 6 Surge arresters, Disconnectors, Fuses 42 Set Moe Nal Sub-Station 7 Other Materials 1 Lot Moe Nal Sub-Station 14