Electrification Plan for Northern Shan State Prioritizing Villages and Infrastructure

Slide Note
Embed
Share

The Republic of the Union of Myanmar's Ministry of Electric Power has outlined a comprehensive electrification plan for Northern Shan State. The plan prioritizes villages without electricity, focusing on those along main roads and near existing grid lines. It emphasizes building quality infrastructure, engaging local communities, and coordinating with government authorities. The plan includes detailed project lists, estimated costs, and specific tasks for electrifying villages within a 2-mile radius of existing 11 kV distribution lines in Lashio, Kyaukme, and Muse districts.


Uploaded on Sep 15, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. The Republic of the Union of Myanmar Ministry of Electric Power Electricity Supply Enterprise Northern Shan State Office Priorities and Detailed Description of Electrification Plan For Northern Shan State Dated -21.Oct.2015

  2. Priority Electrification Project List for Northern Shan State The following facts are agreement after discussion with Chief Minister (Shan State) To be performed priority the villages still without Electricity, which have along the main road. To meet the electrical safety and voltage to establish priorities. To Build quality products with proper power distribution Line. The villages within 2 miles from National Grid Line.(11 kV Line) To be performed priority villages having households more than 100 and above. To be explain the public of villages to construct the low voltage line by local fund. In areas with difficult transportation to go to all the relevant authorities spicy leaves. And then, the remain villages will be implemented continuously by National Electrification Plan. ESE (Northern Shan State) will implement the work done under management MOEP coordination 2 especially with local Government.

  3. Priority Electrification Plan for Northern Shan State (Within 2 miles from Existing 11 kV Distribution Line) To be constructed Task regional No; of Village To be Electrif- ied Estimat e cost (Mil Kyats) No of Hous e Cost for 11 kV Line 11/0.4 kV Transformer Hous e hold N o Popu lation 400 V Lines (Miles ) Estimate Cost (Mil Kyats) Distric Constr u ction Cost Transp- ort Cost Materia l Cost Trans port Cost Constru ction Cost mileMaterial Total kVA No Total Cost 3511 35111678 64.421540.15 83.746246.72 1870.6 3 4650 78 786.33483.52 34.485904.34 2774.9 74 53.572404.70 1 Lashio 77 1 3 9 7 6 4 5023 49712197 50.521207.83 65.676193.49 1467.0 0 5220 69 731.339129.3 49.400910.08 2377.0 83 46.852103.05 2 Kyaukme 61 7 2 2 4 3 0 4356 43702262 36.68 876.945 47.684140.48 1065.1 1 4950 74 770.37259.20 25.900855.47 1920.5 86 62.722815.43 3 Muse 49 4 4 0 2 8 1289 0 1285 2 6138 2 151.63624.93 197.106580.70 4402.7 4 1482 0 2212288.0 272.0 7 109.78 5 2669.9 01 7072.6 43 163.17323.19 Total 187 1 5 5 1 3

  4. Electrification Plan for Villages of Northern Shan State (Within 2 miles from Existing 11 kV Distribution Line) To be Constructed 11 kV Distribution Line 151.62 miles 400 V Distribution Line 163.14 miles 11/0.4 kV Distribution Transformer Muse District No. of Villages - 49 Nos Household - 4370 Estimated Cost - 1920.586 (mil kyats) Kyaukme District 221 Nos No. of Villages - 61 Nos Household - 4971 Estimated Cost - 2377.083 (mil kyats) Lashio District No. of Villages - 77 Nos Household - 3511 Estimated Cost - 2774.974 (mil kyats) 4

  5. Priority Electrification Plan for Lashio District (Within 2 miles from Existing 11 kV Distribution Line) To be constructed Task regional No; of Village To be Electrifie d Estimat e cost (Mil Kyats) No of Hous e Hous e hold Popu latio n Cost for 11 kV Line 11/0.4 kV Transformer Estimat e Cost (Mil Kyats) NoTownshi 400 V Lines (Mile s) p Constr u ction Cost Constr u ction Cost Materia l Cost Transpor t Cost Materia l Cost Trans port Cost mile Total kVA No Total 1723 1723 809729.6 113.44 5 860.106220 39390.06 52.32 7 20.835463.22 1323.33 4 1 Lashio 38 708.155 38.506 18.32 822.366 2 0 7 9 608 2871 9.50 227.126 12.350 36.385 275.861 850 15150.14 12.00 0 5.250167.39 2 Hsenwi 15 608 443.256 15.50 695.780 5 5 739 401013.1 313.195 17.030 50.173 380.398 950 14144.99 11.20 0 4.900161.09 3 Tantyan 14 739 541.490 13.25 594.779 0 2 2 441 180312.2 291.678 15.860 46.726 354.264 650 10101.13 8.000 3.500112.63 4 Mongyal 10 441 466.894 6.50 291.779 0 0 0 3511 35111678 64.4 2 1540.15 3 83.746246.72 1870.62 8 465 0 78786.33 83.52 7 34.485904.34 2774.97 4 53.572404.70 Total 77 1 9 4 6 4 5

  6. Electrification Plan for Villages of Lashio District (Within 2 miles from Existing 11 kV Distribution Line) HsenwiTownship No. of Villages - 15 Nos Household - 608 Estimated Cost - 443.26 (mil kyats) Lashio Township No. of Villages - 39 Nos Household - 1723 Estimated Cost - 1323.33 (mil kyats) Estimated Cost - 541.49 (mil kyats) Mongyal Township No. of Villages - 10 Nos Household - 441 Estimated Cost - 466.89 (mil kyats) To be Constructed 11 kV Distribution Line 64.42 miles 400 V Distribution Line 53.57 miles 11/0.4 kV Distribution Transformer 78 Nos TantyanTownship No. of Villages - 14 Nos Household - 739 6

  7. Priority Electrification Plan for Kyaukme District (Within 2 miles from Existing 11 kV Distribution Line) To be constructed Task regional No; of Village To be Electrifie d Estimat e cost (Mil Kyats) No of Hous e Hous e hold Popu latio n Cost for 11 kV Line 11/0.4 kV Transformer Estimat e Cost (Mil Kyats) 400 V Lines (Miles ) No Township Constr u ction Cost Constr u ction Cost Materia l Cost Transpor t Cost Materi al Cost Trans port Cost mile Total kVA No Total 886 405415.6 372.965 20.280 59.748 452.993 950 12128.48 9.600 4.200142.28 1 Kyaukme 12 886 595.279 10.80 484.801 0 6 6 481 2242 7.35 175.724 9.555 28.151 213.429 650 10102.68 82.144 28.750213.57 2 Hispaw 10 484 427.004 5.98 268.436 0 4 682 341611.0 262.988 14.300 42.130 319.418 800 12123.83 9.600 4.200137.63 3 Naungcho 12 731 457.054 10.10 453.379 0 6 6 927 4317 9.50 227.126 12.350 36.385 275.861115 19192.45 15.200 6.650214.30 4 Namtu 17 927 490.168 12.90 579.068 0 7 7 1995 1995 7948 7.07 169.030 9.191 27.078 205.299167 16183.88 12.800 5.600202.28 5 Moemate 10 407.579 7.07 317.365 0 0 0 5023 49712197 50.5 2 1207.8 32 65.676193.49 1467.0 0 522 0 69731.33 129.34 4 49.400 910.082377.0 46.852103.0 Total 61 7 2 9 83 50 7

  8. The additional electrification statement due to replacement 66/11 kV substation for Northern Shan State The effective area (within 2 mile) Total House hold Estimate Cost (millon kyats) To be Constructed Town ship No 66kV Line (mile) 33kV Line (mile) Total Villages Total Substation populationMaterial Installation Total 33/11 kV 5 MVA to 66/11 kV 10 MVA with (2) bay 1Hispaw 10 484 2242 1588.49 125.3 1713.79 Total 10 484 2242 1588.49 125.3 1713.79 8

  9. Electrification Plan for Villages of Kyaukme District (Within 2 miles from Existing 11 kV Distribution Line) Moemate Township No. of Villages - 16 Nos Household - 1995 Estimated Cost - 407.58 (mil kyats) No. of Villages - 19 Nos Household - 927 Estimated Cost - 490.17 (mil kyats) No. of Villages - 10 Nos Household - 481 Estimated Cost - 427.00 (mil kyats) Kyaukme Township No. of Villages - 12 Nos Household - 886 Estimated Cost - 595.28 (mil kyats) To be Constructed 11 kV Distribution Line 50.52 miles 400 V Distribution Line 46.85 miles 11/0.4 kV Distribution Transformer 69 Nos Namatu Township Hsipaw Township Naungcho Township No. of Villages - 12 Nos Household - 682 Estimated Cost - 457.05 (mil kyats) 9

  10. Priority Electrification Plan for Muse District (Within 2 miles from Existing 11 kV Distribution Line) To be constructed Task regional No; of Village To be Electrifi ed Estimat e cost (Mil Kyats) No of Hous e Hous e hold Popu latio n Cost for 11 kV Line 11/0.4 kV Transformer Estimat e Cost (Mil Kyats) 400 V Lines (Mile s) No Township Constr u ction Cost Constr u ction Cost Materi al Cost Transpo rt Cost Materi al Cost Trans port Cost mile Total kVA No Total 1040 1040 5394 8.20196.04 10.660 31.406 238.112 1150 13142.93 10.40 0 4.550157.88 1 Muse 12 396.001 9.90 444.401 6 9 9 Namtkha m 1234 1234 635411.3 270.16 0 14.690 43.279 328.129 1450 16176.99 12.80 0 5.600195.39 2 11 523.52714.37645.055 0 8 8 1655 1655 882616.4 392.09 1 21.320 62.812 476.223 2050 39385.41 31.20 0 13.65 0 430.26 7 906.49029.701333.20 3 Kukhine 22 0 7 3 4 Kyukoke 4 427 441 2050 0.78 18.648 1.014 2.987 22.650 300 6 65.018 4.800 2.100 71.918 94.568 8.75 392.779 4356 43702262 36.6 8 876.94 5 47.684140.48 1065.11 4 4950 74770.37 59.20 0 25.90 0 855.47 2 1920.58 6 62.722815.43 Total 49 4 4 2 8 10

  11. Electrification Plan for Villages of Muse District (Within 2 miles from Existing 11 kV Distribution Line) Muse Township Pansai(Kyukoke) Township No. of Villages - 6 Nos Household - 441 Estimated Cost - 94.57 (mil kyats) To be Constructed 11 kV Distribution Line 36.68 miles 400 V Distribution Line 62.72 miles 11/0.4 kV Distribution Transformer 74 Nos No. of Villages - 13 Nos Household - 1040 Estimated Cost - 396.00 (mil kyats) Namkham Township No. of Villages - 16 Nos Household - 1234 Estimated Cost - 523.53 (mil kyats) KukhineTownship No. of Villages - 39 Nos Household - 1655 Estimated Cost - 906.49 11

  12. The Statement of Fiscal Yearly Budget and Electrified Connection for Northern Shan State State/Region Electrified Connection State/Region Capital Budget Capital Budget for for DRD (mil On Grid Off Grid ESE (mil Kyats) kyats) Sr. Fiscal Year No Total Cost Total Cost Consume Consume for 11 kV Village Village for 400 V Total Off Grid r r Line (Nos) (Nos) Line (Nos) (Nos) & 11/0.4 TR 2014--2015 Estimate 1 655.245 445.777 1101.022 3614.540 26 1820 260 16457 (BE+RE) 2 2015-2016 Estimate (BE+RE) 2416.780 2548.000 4964.780 2841.856 77 4625 242 13537 2016-2017 Budget Estimate 3 3661.230 3786.400 7447.630 6452.400 48 3120 508 27617 (BE) 12 13513.4 Grand Total 6733.255 6780.177 12908.796 151 9565 1020 57611

  13. Main Materials List Transported to Lashio District Office Sr No Description Quantities Transported Site 1 11/0.4 kV Distribution Transformer 78 Lashio District, PMO Office 2 10 m Concrete Pole 3506 Lashio District, PMO Office 3 ACSR 95 mm2 134 Lashio District, PMO Office 4 11 kV, Disc Insulator with Fitting 8865 Lashio District, PMO Office 5 11 kV, Pin Insulator with Spindle 1747 Lashio District, PMO Office 6 Surge Arrestors, Disconnectors, Fuse 78 Lashio District, PMO Office 7 Other materials 1 Lot Lashio District, PMO Office 13

  14. Main Materials List Transported to Kyaukme District Office Sr No Description Quantities Transported Site 1 11/0.4 kV Distribution Transformer 69 Kyaukme District, PMO Office 2 10 m Concrete Pole 2766 Kyaukme District, PMO Office ACSR 95 mm2 3 105 Kyaukme District, PMO Office 4 11 kV, Disc Insulator with Fitting 1420 Kyaukme District, PMO Office 5 11 kV, Pin Insulator with Spindle 7083 Kyaukme District, PMO Office 6 Surge Arrestors, Disconnectors, Fuse 69 Kyaukme District, PMO Office 7 Other materials 1 Lot Kyaukme District, PMO Office 14

  15. Main Materials List Transported to Muse District Office Sr No Description Quantities Transported Site 1 11/0.4 kV Distribution Transformer 74 Muse District, PMO Office 2 10 m Concrete Pole 2056 Muse District, PMO Office 3 ACSR 95 mm2 76.26 Muse District, PMO Office 4 11 kV, Disc Insulator with Fitting 1102 Muse District, PMO Office 5 11 kV, Pin Insulator with Spindle 5118 Muse District, PMO Office 6 Surge Arrestors, Disconnectors, Fuse 74 Muse District, PMO Office 7 Other materials 1 Lot Muse District, PMO Office 15

  16. THANK YOU