Industry Symposium Highlights and Project Specifics for 2022
The Partnering with Industry Symposium in February 2022 presented valuable insights into major capital projects like the Interdisciplinary Science and Innovation Centre (ISIC), Capital Maintenance, Utility Reduction Programs, and Minor Institutional Projects. Specifics of projects such as ISIC's 9,500 m² building area, the CMR Program's deferred maintenance projects, URPr Grant's utility reduction program, and Capital/Minor Projects under $3 million were discussed. The symposium also outlined prequalification scopes and renewal dates for contractors and architects involved in the projects.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
Partnering with Industry Symposium February, 2022 Boris Dragicevic AVP Facilities Development
Agenda 1. 2. Budget Categories Major Capital Projects: I. Interdisciplinary Science and Innovation Centre (ISIC) Programs: I. Capital Maintenance and Renwal (CMR) II. Utility Reduction Program (URPr Grant) Capital Projects (under 3 million) & Minor Institutional Projects Prequalification Scopes & Renewal Dates 3. 4. 5. 2
Project Categories Major Capital Projects: Interdisciplinary Science and Innovation Centre (ISIC) Programs: Capital Maintenance and Renewal Program (CMR) Utility Reduction Program (URPr Grant) Capital Projects (under 3 million) & Minor Institutional Projects 3
Interdisciplinary Science and Innovation Centre Specifics: 9,500 m2 Gross Building Area Schedule: Spring 2024 $130M Total Project Budget Construction Management Delivery Phase: Schematic Design and RFP for CM Service 4
Capital Maintenance & Renewal Program (CMR) Specifics: Deferred maintenance projects Schedule: Through out the year Design Bid Build predominantly Phase: Various Stages $31.05M for 21/22 (confirmed), $19.00M for 22/23 (pending) 5
Utility Reduction Program (URPr Grant) Specifics: Multi-year program Schedule: To April, 2024 Construction Management Delivery Phase: Design & Construction $19.3M Total Project Budget for 2021/22 6
Capital & Minor Projects (under $3M) Specifics: School/Department and Institution funding Schedule: Through out the year Design Bid Build predominantly Phase: Various Stages $20.0M in Total Projects Estimated for 2022/23 7
Prequalification Scopes & Renewal Dates Tier 1 General Contractors: March, 2024 Those that do labs Tier 2 General Contractors: March, 2024 Those that do not do labs Mechanical Contractors: April, 2026 Electrical Contractors: March, 2022 Architects: December, 2026 Labs, assembly spaces and commercial Interior Design: February, 2022 Functional Space Programming: February, 2022 Engineers: September, 2026 8