This presentation showcases the proposed construction sequence for the mainline pavement section of the project in Shelby County. It includes detailed images and descriptions of various construction stages, such as the segments from W. McLemore Avenue to South of Crump Boulevard, the Crump/Roundabout area, different pavement section alternatives, traffic control procedures, and construction sequence planning.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
CNW055 Shelby County Mandatory Pre-bid Meeting March 8, 2022 Jamie Fitzpatrick
Presentation Order: Proposed Construction Mainline Pavement Section Construction Sequence
Construction Sequence Local Street Detours Riverside Drive to South Parkway
Construction Sequence Local Street Detours S. Third Street to South Parkway
Construction Sequence Local Street Detours McLemore Ave. to S. Third Street
Construction Sequence Local Street Detours Riverside Boulevard to South Parkway
Construction Sequence Local Street Detours Presidents Island Detour: Riverside Boulevard to Trigg Avenue to Jack Carley Causeway
Construction Sequence Local Street Detours Crump Blvd. to Metal Museum
Construction Sequence Stage 4C Crossover C Mod TWO-WEEK SHUTDOWN Memphis-Arkansas Bridge