Operational Updates and Activities for the Week Ahead

Slide Note
Embed
Share

This report outlines the operational activities scheduled for the upcoming week, including machine sign-offs, safety system tests, weekend activities, power outages, and ICW flushing. Key tasks include obtaining permissions, conducting safety tests, completing maintenance activities, and scheduling controlled access for equipment checks. The report also mentions upcoming activities such as vacuum system rebuilds and power outages in Wilson Hall.


Uploaded on Sep 24, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Shut Down Managers Report Cons Gattuso

  2. Machine Sign off We have permission to run Linac and NTF (Oct 16th) We should be completing obtaining permission for Booster Today MI Sign offs are scheduled for early next week (Monday) 2 9/24/2024

  3. Weekend activities Friday, Oct 17th ~16:00 hrs. MI keys returned and removed locks from 13.8 Kv Evening shift Search and Secure for Saturday Safety System tests Interlock and CDC testing MI checkout list will need to be completed Saturday, Oct18th MI Safety System Test. Starting at 06:00-~12:00 If successful We can Hi-pot and clear faults Other wise we will low pot and clear what ever faults we can find Sunday Clear faults Monday Controlled access Complete final Leak check Remove Equipment from 40 Complete signoffs Possibly run beam Monday afternoon 3 9/24/2024

  4. Safety System Test What still needs to be completed Booster CDC MI ESS Transport ESS Tev F sector Rad monitors MI65 ESS Minos ESS NuMI Rad monitors NuMI CDC Meson MT6 sec1 & 2 Enclosure Meson Rad monitors Meson Test Logic Module Meson Test Primary CDC Meson MC6 ESS Meson MC7 MB7 ESS Meson Center Rad Monitor Meson Center CDC Neutrino G2 ESS Neutrino NM3-4 RMSS Neutrino Rad Monitors Neutrino CDC 4 9/24/2024

  5. Next Week Activities NuMI Continue with Be Window Assembly Replacement Mike Andrews will provide more details in the NuMI report F-Sector Vacuum Recovery for F1, F2 and F3 house due to Feeder 46B work ( done next week some time) ~2 hour access over 2 days to pump down and leak check Switchyard Rebuild vacuum system around the MuLam replacement magnet (EPB) in G1 stub Magnet replacement at MC-6 5 9/24/2024

  6. Week End Power outages Saturday, Oct. 18th 07:00 - Sunday, Oct. 19th 16:00 0700-16:00 hrs Wilson Hall Power outage Phase 1- Electrical Switch gear in Wilson will be removed. Two more to come in the future (November) 6 9/24/2024

  7. ICW Flushing Monday 10-20-2014 CMTF, Labs A thru G, NML, NS1, NS2, NS4, NWA, MDB, MS1, 2 & 3, Training Center Tuesday 10-21-2014 Fire Dept., Fuel Service Center, GCC, HIL, KTEV, LLRW, MAB, MCRB, MC8, MDB, MP9, MW9, NE8, NS4, PAB, PB7, PS2, PS3, PS4, PS5, PS6, PW2, Rad Cal, Site 37, Site 38, Site 39, Vehicle Maint., WHI, WHII, Well 4 Wednesday 10-22-2014 CDF Office, CDF PK, CHL, D0, D0 Corridor, FCCF, IB1, IB1A, IB2, IB3, IB4, Main Sanitary Lift Station, Master Sub, PS1, Switch Yard, Well 4, Wilson Hall (north east) Thursday 10-23-2014 AP10, AP30, AP50, APOTH, BTW, BTE, Cross Gallery, CUB, Linac, SWA, SEA, Tev ring, Transfer Gallery, Wilson Hall back horse shoe (0600 start) Note: Weather and adverse conditions may alter this schedule 7 9/24/2024

  8. Next week 09:00 meeting schedule Phasing back to the our standard M/W/F 09:00 meeting Monday No Meeting Wednesday Huddle Friday- One West (Operations will be running 09:00) 8 9/24/2024

  9. Schedules and Links Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.html We have added the following links to Operation s Schedule Web page MS project schedule for the entire shutdown Week by week Schedule for Each machine 9 9/24/2024