The Market System Release Update for SEM Project includes modifications approved during committee meetings. The deployment was successful, and project milestones were met promptly. Key features such as Intra-Day Trading enhancements and project milestones completion status are highlighted. Additionally, the scope for future releases and approved Modification Proposals are outlined. The update provides a comprehensive overview of the progress and upcoming developments in the SEM project.


Uploaded on Dec 10, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. MARKET SYSTEM RELEASE UPDATE Modifications Committee Meeting 31 July 2012

  2. SEM R2.0.0 Intra-Day Trading Deployment The following approved Modification Proposals were included in the release Mod_18_10: Intra-Day Trading Mod 43_10: Variable Price-Taker Generator Units and Firm Access. The release was successfully implemented on schedule overnight on Fri 20th / Sat 21st July. Central Market Systems were available for Trading as scheduled at 8am on July 21st. All project milestones were completed to quality and schedule (see next slide for more detail). New capability embedded successfully: All Ex-Ante schedules (EA1, EA2 & WD1) published to schedule post deployment.

  3. SEM R2.0.0 Intra-Day Trading Project milestones Activity Schedule Status Detailed Requirements Dec 1st , 2010 Apr 30th, 2011 Complete Vendor Detailed Design May 1st, 2011 Jul 29th, 2011 Complete Design Deliverables Issued to Participants (MPUD etc.) Aug 29th, 2011 Complete Participant Engagement Plan published Sep 9th 2011 Complete Participant Systems Design Workshops Sep 28th, Oct 5th 2011 Complete Vendor Implementation Jun 20th, 2011 Nov 11th, 2011 Complete Factory Testing Nov14th, 2011 - Dec 23rd, 2011 Complete System Integration Testing Jan 3rd, 2012 - Apr 27th, 2012 Complete Market Trial Apr 30th, 2012 Jul 6th, 2012 Complete Deployment Jul 20th, 2012* Complete

  4. SEM R2.1.0 Oct. 2012 Scope Reminder The Approved scope for SEM R2.1.0 is as follows: Mod Ref CR Ref Description Mod_40_10 SEM_PC_CR254 Differentiation between Dwell Times and Dwell Trigger Points While Ramping Up and Ramping Down Mod_42_10 SEM_PC_CR255 Changes to the Single Ramp-Up Rate and the Single Ramp-Down Rate calculation. Mod_01_11 SEM_PC_CR258 UI Payments for Generator Units. Mod_06_11 SEM_PC_CR259 Increasing maximum daily submission number and automating cancellation of Settlement Reallocation Agreements. Mod_10_11 SEM_PC_CR274 Interconnector Under Test. Mod_12_11 SEM_PC_CR275 Interconnector Unit Loss Adjustment when Exporting Mod_21_11 SEM_PC_CR280 UI Payments for Generator Units Constrained On SDS SEM_PC_CR207 Automation of FMOC Calculation SDS SEM_PC_CR260 Additional MI-AMP Feed SDS SEM_PC_CR261 Removal of orphan Trading Site Settlement Points SDS SEM_PC_CR266 Change of Effective Date in the MPI SDS SEM_PC_CR267 Wind and Load Forecast Data SDS SEM_PC_CR286 Publication of Zero MIUNs when no PQ Pairs available

  5. SEM R2.2.0 Apr. 2013 Scope to Date The following Modification Proposals are approved for the SEM R2.2.0 release: Mod Ref CR Ref Description Mod_17_11 SEM_PC_CR281 Addition of a D+3 DI report Mod_03_12 SEM_PC_CR290 Alignment of T&SC with Revised VAT arrangements The release cut-off date for the April 2013 release to the Central Market Systems was Friday, June 22nd, 2012. Regarding non-T&SC scope (i.e. SDS), impact assessments are with our vendors. Once received: A meeting of the CCF will be scheduled to prioritise these for inclusion in scope; Scope Proposal will be issued to the Regulatory Authorities for approval; and Once approved, the complete release scope will be published to the Industry.

  6. SEM R2.3.0 Oct. 2013 Release Cut-Off Date The release cut-off date for the October 2013 release to the Central Market Systems is: Friday February 22nd, 2013. All approved Modifications Proposals will be allocated to this release (subject to available capacity).