Litchfield Elementary School District Bond Update June 30, 2021

Bond Update as of June 30, 2021
2014 Bond Authorization
Presenter
Wendy D. Qualls, Executive Director of Finance
Strategic Plan Alignment
Finances/Resources
Increase stakeholder knowledge and understanding of
school funding.
Timeline for Completion
Arizona Revised Statute § 15-491.K
Each school district that issues bonds under this section is
required to hold a public meeting each year between
September 1 and October 31, until the bond proceeds are
spent, at which an update of the progress of capital
improvements financed through bonding is discussed.
2014 Bond Authorization and Bonds Issued
Bond Authorization
  
  $35,000,000
Bonds Issued
 
2015                                     $   6,000,000
           2016                                     $   6,000,000
           2018                                     $ 16,000,000
           2021                                     
$   7,000,000
Total Bonds Issued 
  
$ 35,000,000
Expenditures to Date
  
$(
26,681,352)
Available Cash
   
$   8,318,648
2014 Bond Expenditures through June 30, 2021
Remodel Existing Schools Budget 
   
$2,100,000
 
Corte Sierra Elementary School (2016)
    
$       28,280
 
L. Thomas Heck Middle School (2019)
    
$       58,221
Litchfield Elementary School (2020)
    
$     294,443
Scott L. Libby Elementary School (2020)
    
$     149,677
Western Sky Middle School (2020)
    
$     204,000
Wigwam Creek Middle School
 
(2020)
    
$       65,022
 
Remaining Balance 
       
$  1,300,357
New School Construction Budget
 
 
  
$25,200,000
Verrado Heritage Elementary School (opened August 2015)
 
$  4,001,898
Belen Soto Elementary School
 
(opened August 2019)
  
$16,298,573
White Tanks Learning Center (started 2021)
   
$        34,074
 
Remaining Balance
       
$ 4,865,455
Remodel Administrative Facilities
   
$     200,000
Data Center (2017)
      
$       40,504
Food Services (2018)
      
$     127,367
 
Remaining Balance
       
$        32,129
2014 Bond Expenditures through June 30, 2021
Operational & Administrative Construction
  
$ 3,500,000
Support Facility (opened fall 2017)
    
$  2,392,473
Fuel Storage Tanks (2020)
     
$      493,063
 
Remaining Balance
       
$    614,464
Pupil Transportation Vehicles Budget
  
$ 4,000,000
Buses (2016, 2018, 2019)
     
$  2,404,153
 
Remaining Balance
       
$  1,595,847
Legal Costs for Bond Issuance
Expenditures
      
$       89,604
 
Future Construction Plans
   White Tanks Learning Center
Other Funds Used for Construction
    
Verrado Heritage Elementary School (opened August 2015)
Community Education
   
$    361,785
Donations
     
$    129,704
2009 Bond 
    
$ 8,151,159
Adjacent Ways
    
$    860,906
Belen Soto Elementary School (opened August 2019):
Adjacent Ways
    
$    795,482
Scott L Libby Elementary School Remodel (2020):
Capital Outlay (DAA)
   
$      77,932
Other Funds Used for Construction
Wigwam Creek Middle School Bus Loop (2020):
Adjacent Ways
    
$    349,024
Fuel Storage Tanks (2020):
ADEQ Grant
    
$      64,674
Palm Valley Elementary School Roof Replacement (2019):
School Facilities Board
   
$    833,555
     
Western Sky Middle School Roof School Replacement (2019):
School Facilities Board 
   
$1,126,908
Wendy D. Qualls
Executive Director of Finance
qualls@lesd.k12.az.us
(623)535-6017
www.lesd.org
Slide Note
Embed
Share

Litchfield Elementary School District provides an update on the 2014 Bond Authorization as of June 30, 2021. The District has issued bonds totaling $35 million with expenditures and available cash detailed. Expenditures include school remodeling, new construction projects, operational expenses, and more in alignment with their strategic finance plan.

  • School District
  • Bond Update
  • Finance
  • Strategic Planning
  • Expenditures

Uploaded on Sep 17, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Litchfield Elementary School District Bond Update as of June 30, 2021 2014 Bond Authorization

  2. Presenter Wendy D. Qualls, Executive Director of Finance

  3. Strategic Plan Alignment Finances/Resources Increase stakeholder knowledge and understanding of school funding.

  4. Timeline for Completion Arizona Revised Statute 15-491.K Each school district that issues bonds under this section is required to hold a public meeting each year between September 1 and October 31, until the bond proceeds are spent, at which an update of the progress of capital improvements financed through bonding is discussed.

  5. 2014 Bond Authorization and Bonds Issued Bond Authorization $35,000,000 Bonds Issued 2015 $ 6,000,000 2016 $ 6,000,000 2018 $ 16,000,000 2021 $ 7,000,000 Total Bonds Issued Expenditures to Date Available Cash $ 35,000,000 $(26,681,352) $ 8,318,648

  6. 2014 Bond Expenditures through June 30, 2021 Remodel Existing Schools Budget Corte Sierra Elementary School (2016) L. Thomas Heck Middle School (2019) Litchfield Elementary School (2020) Scott L. Libby Elementary School (2020) Western Sky Middle School (2020) Wigwam Creek Middle School(2020) Remaining Balance New School Construction Budget Verrado Heritage Elementary School (opened August 2015) Belen Soto Elementary School(opened August 2019) White Tanks Learning Center (started 2021) Remaining Balance Remodel Administrative Facilities Data Center (2017) Food Services (2018) Remaining Balance $2,100,000 $ 28,280 $ 58,221 $ 294,443 $ 149,677 $ 204,000 $ 65,022 $ 1,300,357 $25,200,000 $ 4,001,898 $16,298,573 $ 34,074 $ 4,865,455 $ 200,000 $ 40,504 $ 127,367 $ 32,129

  7. 2014 Bond Expenditures through June 30, 2021 Operational & Administrative Construction Support Facility (opened fall 2017) Fuel Storage Tanks (2020) Remaining Balance Pupil Transportation Vehicles Budget Buses (2016, 2018, 2019) Remaining Balance Legal Costs for Bond Issuance Expenditures $ 3,500,000 $ 2,392,473 $ 493,063 $ 614,464 $ 4,000,000 $ 2,404,153 $ 1,595,847 $ 89,604

  8. Future Construction Plans White Tanks Learning Center

  9. Other Funds Used for Construction Verrado Heritage Elementary School (opened August 2015) Community Education Donations 2009 Bond Adjacent Ways $ 361,785 $ 129,704 $ 8,151,159 $ 860,906 Belen Soto Elementary School (opened August 2019): Adjacent Ways $ 795,482 Scott L Libby Elementary School Remodel (2020): Capital Outlay (DAA) $ 77,932

  10. Other Funds Used for Construction Wigwam Creek Middle School Bus Loop (2020): Adjacent Ways $ 349,024 Fuel Storage Tanks (2020): ADEQ Grant $ 64,674 Palm Valley Elementary School Roof Replacement (2019): School Facilities Board $ 833,555 Western Sky Middle School Roof School Replacement (2019): School Facilities Board $1,126,908

  11. Litchfield Elementary School District Wendy D. Qualls Executive Director of Finance qualls@lesd.k12.az.us (623)535-6017 www.lesd.org

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#