Alabama Department of Transportation Local Master Calendar Planning Schedule 2022

Slide Note
Embed
Share

The schedule outlines various tasks to be completed by the Alabama Department of Transportation for the year 2022, including urban funds reporting, performance measures tracking, certification reviews, archival tasks, cube voyager invoicing, reporting to MPOs, and work program calculations. The detailed plan covers a range of activities essential for transportation planning and execution.


Uploaded on Sep 15, 2024 | 1 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. ALABAMA DEPARTMENT OF TRANSPORTATION LOCAL Master Calendar Planning Schedule TRANSPORTATION- PLANNING SECTION 2022 SCHEDULE W/ 2023, 2024 2025 & 2026

  2. January 4th,2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months See if MPOs agree with contract estimates-on January and February Lettings

  3. January 2022 PERFORMANCE MEASURES Remind MPOs about PM1 deadline Receive information on Transit Performance Measures from LTB Transit Provide information on Transit Performance Measures to MPOs

  4. January 2022 Certification Review and approve FL-AL Self-Certification Questionnaire Route signed Self-Certification Form to FL-AL; verify it is included in the TIP Route FL-AL Self-Certification Forms to Director for signature

  5. January 2022 CONTINUOUS ARCHIVE Archive invoices, UPWPs, and Work Programs more than 3 years old Archive expired LRTPs, TIPs, and various plans Support archival efforts

  6. January 2022 CUBE Give Cube Voyager invoice to Administrative Assistant for payment* * Both Design Bureau and Local Transportation Bureau have contracts with Bentley, Inc. Consultant Management Section will often receive the invoice for both and forward ours to us for payment.

  7. January 2022 REPORTING Report to MPOs and RPOs whether they met deadlines for Annual Reports and the Annual Listing of Obligated Projects. Report any findings on the Comprehensive Financial Plans on the Federal Aid Clearinghouse.

  8. January 2022 WORK PROGRAMS AND UPWPS Calculate FY-2023 MPO and RPO funding Calculate MPO carryover funding Provide the MPO and RPO apportionment for the following fiscal year Provide the MPO and RPO carryover from the previous fiscal year Provide the MPO / RPO with new rules via memo, meeting, or other means

  9. February, 2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS February 1st Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months See if MPOs agree with contract prices for the January Letting February 15th See if MPOs agree with contract estimates for Feb. and March Lettings

  10. February 2022 REPORTING Enter CMAQ Reporting Information here: https://fhwaapps.fhwa.dot.gov/. Approve CMAQ Reporting Information here: https://fhwaapps.fhwa.dot.gov/.

  11. February 2022 EVENTS Co-host Jimmy Carroll s Financial / Legislative Training in Tuscaloosa

  12. March,2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS March 1st See if MPOs agree with contract prices for the February Letting March 10th Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months See if MPOs agree with contract estimates for April Lettings

  13. March 2022 PERFORMANCE MEASURES Provide OE with Performance Measures resolutions (PM1 or Combined)

  14. April 2022 WORK PROGRAMS AND UPWPS Attend kickoff meeting with Office Engineering Bureau (OE)

  15. March / April,2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS March 29th See if MPOs agree with contract prices for the March Letting See if MPOs agree with contract estimates for April and May Lettings April 6th Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months

  16. May 2022 (First Week) WORK PROGRAMS AND UPWPS Give OE amended FY-2022 SPR Part 1 with MPO FY-2021 carryover Give OE FY-2023 SPR Part 1 & 3 with FY-2023 appt. and FY-2021 carryover

  17. May 2022 WORK PROGRAMS AND UPWPS Amend FY-2022 MPO projects in CPMS Create FY-2023 MPO and RPO projects into CPMS Submit Process Letter to FHWA for PL distribution procedure

  18. May 3rd, 2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months See if MPOs agree with contract prices for the April Letting See if MPOs agree with contract estimates for May and June Lettings

  19. May 2022 CUBE Add Cube Voyager to OE s future year SPR Work Program /

  20. May 2022 LETTINGS & AGREEMENTS Prepare UAH Agreement and give to Agreement Specialist Prepare other consultant Agreement and give to Agreement Specialist Prepare Birmingham Agreement (5) and give to Agreement Specialist

  21. May 2022 CERTIFICATION Attend Lillian TMA Certification Meeting

  22. May / June 2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS May 31st Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months June 8th See if MPOs agree with contract prices for the February Letting See if MPOs agree with contract estimates for March and April Lettings

  23. July 2022 PERFORMANCE MEASURES Provide OE with Performance Measures resolutions (PM2/PM3 or combined)

  24. July 2022 PERFORMANCE MEASURES State whether each MPO met their Performance Target deadlines (letter) Provide OE with Performance Measures resolutions (2 Transits or combined)

  25. June / July 2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS June 28th Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months July 6th See if MPOs agree with contract prices for the February Letting See if MPOs agree with contract estimates for March and April Lettings

  26. July 6th, 2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months

  27. July 2022 (by July 31st, 2022) WORK PROGRAMS AND UPWPS Review Draft UPWPs and Work Programs; distribute to FHWA and FTA Make sure Final UPWP is on the last meeting agenda of the fiscal year

  28. August 2022 EVENTS Attend Title VI Meeting (Attachment A) Prepare responses for Title VI Meeting

  29. August 2022 Reporting Assess Birmingham CBD or other project financial reporting

  30. August 1st, 2022 WORK PROGRAMS AND UPWPS Complete the letter to FHWA for FY-2023 UPWPs notes in Teams

  31. August 1st, 2022 PERFORMANCE MEASURES Receive information on PM1 Perf. Measures and Methodology from Safety Section Provide information on PM1 Performance Measures and Methodology to MPOs

  32. August 2nd, 2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months See if MPOs agree with contract prices for the July Letting See if MPOs agree with contract estimates for August and September Lettings

  33. August 2022 LTPS REPORTS (August 30th) See if MPOs agree with contract prices for the August Letting See if MPOs agree with contract estimates for September and October Lettings

  34. August 2022 LETTINGS & AGREEMENTS Tell Mike Hora to authorize UAH, Auburn, and Birmingham (5) Agreements

  35. September 2022 (by Sept.1st 2022) WORK PROGRAMS AND UPWPS Receive Final UPWPs and Work Programs (4); distribute to FHWA (1) and FTA (1)

  36. September 7th, 2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months

  37. September 2022 LRTPs and TIPs Long Range Transportation Plans and Transportation Improvement Programs Attend Office Engineering Bureau s STIP kickoff meeting TIP Kickoff meeting with MPOs

  38. October 2022 REPORTING Fill out MPO invoice information here: https://www.fsrs.gov

  39. October 2022 LETTINGS & AGREEMENTS Revise MPO 3C and RPO Cooperative Agreement Identify changes to MPO and RPO Bylaws Advise MPOs on changes to bylaws; Receive bylaws from MPOs

  40. October 2022 WORK PROGRAMS AND UPWPS Confirm the amount of the MPO and RPO Work Program for the current fiscal year Request the Consolidated Planning Grant from FTA for the previous fiscal year

  41. October 4th, 2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months See if MPOs agree with contract prices for the September Letting See if MPOs agree with contract estimates for November and December Lettings

  42. October 2022 CUBE Procure Cube Voyager using the Quote and the Sole Source Letters (2) Provide Cube Voyager Quote and Sole Source Letters (2) to Administrative Asst.

  43. October 2022 CERTIFICATION Develop MPO Self-Certification Questionnaire and Form (work with FHWA)

  44. November 2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS November 1st Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months November 8th See if MPOs agree with contract prices for the November Letting See if MPOs agree with contract estimates for December and January Lettings

  45. November2022 PERFORMANCE MEASURES Receive information on PM2 Perf. Measures from Maintenance Bureau Provide information on PM2 Performance Measures to MPOs Receive information on PM3 Performance Measures from Planning Studies Section Provide information on PM3 Performance Measures to MPOs

  46. November 2022 Before 1st invoice is processed REPORTING Collect MPO and RPO Annual Reports Compile MPO and RPO Annual Reports and necessary reporting for OE Process MPO and RPO audit requests Request approval from the Finance Bureau regarding the ICAP

  47. November 2022 December and before 1st invoice is processed REPORTING Verify MPO Annual Listings of Obligated Projects are on the MPO website

  48. December 6th, 2022 Upon completion of Scheduling Meeting (per Kenneth s e Upon completion of Scheduling Meeting (per Kenneth s e- -mail) mail) URBAN FUNDS, LETTING, LTPS REPORTS Send Urban Funds Report to MPOs Review Letting List or Toni Arrington s report for 6 months See if MPOs agree with contract prices for the December Letting See if MPOs agree with contract estimates for January and February Lettings

  49. As Needed Level 1 Pay MPO and RPO invoices Manage project agreements Request checks to refill SWA Accounts; physically refill the account Make sure check is received from project sponsor Mail invoices following letting

  50. As Needed Level 2 Request the Region edit CPMS per MPO resolutions prior to the MPO meeting Verify that CPMS matches the MPO resolutions following the MPO meeting Submit Functional Classification resolutions to Supervisor; file Attend Cube Training Submit Language Assistance Plan resolutions to Supervisor; file Submit Bicycle and Pedestrian Plan resolutions to Supervisor; file Submit Bicycle and Pedestrian Plan resolutions to Supervisor; file Submit Freight Plan resolutions to Supervisor; file Submit Congestion Management Plan resolutions to Supervisor; file Receive new census boundary from the MPO File Continuity of Operations Plan Develop and Attend MPO Certification Meetings File ADA Transition Plans