2017 Streets Resurfacing Project Overview

Slide Note
Embed
Share

The 2017 streets resurfacing project in Palm Coast aims to resurface 13 miles of roadways, repair existing paths, and create new paths. The project includes trail resurfacing and rehabilitation, with a budget allocation of $1,675,000 for street resurfacing and path/trail construction. Halifax Paving, Inc. is the proposed contractor with a history of successful projects in the area.


Uploaded on Sep 30, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. 2017 Streets Resurfacing Construction Management & Engineering

  2. Project Purpose The purpose of this project is to resurface approximately 13 miles of roadways, resurface/repair existing asphalt paths and pave a new path along Old Kings Road and the FP&L easement.

  3. PROJECT CONTRACTOR Halifax Paving, Inc. is the proposed contractor based on their low-bid submission Halifax Paving, Inc. has performed numerous projects within the City of Palm Coast including: 2016 Street Resurfacing Pine Lakes Pkwy (North) Path Belle Terre Pkwy North Widening

  4. Street Resurfacing List Number of Street Being Resurfaced 38 Street Resurfacing Mileage 13.35

  5. Trail Resurfacing and Rehabilitation FP&L Asphalt Path New 10 Asphalt Path Along Existing FP&L path

  6. Trail Resurfacing and Rehabilitation Old Kings Road Trail New 8 Asphalt Path Connects existing sidewalk to new FP&L path

  7. Trail Resurfacing and Rehabilitation St. Joe Walkway Resurfacing

  8. Trail Resurfacing and Rehabilitation Pine Lake Path Path Repair

  9. BUDGET Current Budget Includes: $1,550,000.00 for Street Resurfacing $125,000.00 for Path/Trails

  10. COUNCIL ACTION Approve Work Order in the Amount of $1,675,000.00 for Street Resurfacing, construction of a new path and path resurfacing/repair

  11. Questions?