Update on TPC Electronics Activities - July 2019

Slide Note
Embed
Share

The upcoming short-term activities for ICARUS WA104 meeting on July 17th, 2019, at TPC Electronics include installation of cables, refurbishment of defective modules, and addressing excess noise issues in mini-crates. Detailed plans for interventions at FNAL from July 24th onwards involve repair actions on spare mini-crates and PS modules, installation of necessary components, and testing CAEN boards. Tests have been ongoing to understand and resolve noise issues in standard and corner mini-crates, with a focus on corner chimneys and replacement of noisy boards. Ongoing efforts are directed towards solving remaining noise issues and investigating corner chimneys further.


Uploaded on Oct 11, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. TPC electronics: update on the next short term activity ICARUS WA104 Meeting July 17th2019

  2. Next short term activity at FNAL Starting from July 24than intense 10 days intervention on the TPC electronics is planned to install cables on the top of the detector and to refurbish some defective module. At the same time an intense activity is planned finalized to better understand the origin of the limited excess of noise measured on mini-crates. In addition a working station, will be assembled (at D0?) in order to test anomalous CAEN board if/when required.

  3. Installation activities In the first couple of days, some repair action will be performed on the spare mini-crates and PS modules in order to allow an easy replacement if required: One PS: a missing 5V module will be installed. One PS: one defective 12V module will be replaced. On the two mini-crates backplanes need to be replaced. Moreover some missing dummy front panels will be installed to close some mini-crates already installed on the T600 top. A fully equipped test station of flange feed-through, cables, mini-crate, DBB boards will be installed (at D0 ?) for the check the CAEN boards functionality. According to the foreseen cable delivery on July 26th, the following cables will be connected to each mini-crate: Two SHV-SMA cables for wire biasing on the standard mini-crate; One SHV-SMA cable with one splitter for each mini-crate on the corners. One Lemo cable for TTLink to each mini-crate.

  4. Tests on the problematic crates 4 Since beginning of June, different tests have been performed to understand/solve the evident excess of noise visible in : 4 standard mini-crates EE08, EE12, EE18 and WW18 5 corner mini-crates EW20Top, WW20Top, EE01Middle, EW20Middle, EE20Middle where the RMS exceed 10 #ADCs in few boards; Main focus was on the corner chimneys, where the replacement of ~10 boards allowed to solve the most noisy crates, avoiding the flange opening. Besides the more comfortable situation, some extra noise is still present in few flanges requiring additional studies and tests: Tests have to be performed with the latest on-line DAQ working version; The online TPC signals monitoring while we collect the data is required to directly access in "real time" wire signal waveforms and then measure noise and pedestals per board or per crate. Slide# : 4

  5. Standard mini-crates: remaining issues 4 RMS (#ADC) RMS (#ADC) Crate EE12 Crate EE08 channel channel RMS (#ADC) RMS (#ADC) Crate EE18 Crate WW18 channel channel Slide# : 5

  6. Corner chimneys: to be further investigated 4 RMS (#ADC) WW20Top (#ADC) RMS EW20Top not used channels +15 chs flat cable cut not used channels channel channel EW20Middle (#ADC) (#ADC) (#ADC) RMS EE20Middle RMS RMS EE01Middle channel channel channel Slide# : 6

  7. Correlated noise 4 The average noise level in the corner chimneys results ~ 5 #ADC, higher with respect to the standard chimneys (~3 3.5 #ADC). In all flanges (standard and corner chimneys) is also evident a correlated noise that is enhanced in the corner flanges. This problem must be cured working on fine tuning on grounding. This might be an issue given to the permanent mixing of building and detector grounding. channels channels ticks ticks Top Middle Slide# : 7

Related


More Related Content