Union Square Project Update - 6/14/2023

Slide Note
Embed
Share

Project update for Union Square on 6/14/2023 includes reported schedules, current activities, CEG approvals, sanitary sewer relocation, firehouse relocation, and more. Progress has been made in various aspects of the development, with upcoming tasks outlined for the next quarter.


Uploaded on Sep 12, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. 6/14/2023 UNION SQUARE Old Town Companies 1

  2. Project Schedule Reported Previous Quarter Original Schedule Current Garage 11/23/23 Garage 1/8/24 Garage 3/25/24 Apartments 5/31/24 Apartments 8/14/24 Apartments 4/1/25 Future Building 1 TBD Future Building 2 - TBD 2 Union Square 6/14/2023

  3. Project Activites Last 90 Days Next 90 Days CEG Approval of Stream bypass and Water/Sanitary Permits Sanitary Sewer Relocation. Anna Kendall Drain bypass Hamilton County Drainage Board Approval for the Anna Kendall Drain Encapsulation & Maintenance Relocation and Encapsulation of the legal drain. Temporary relocation of firehouse building. Finalizing review and comments of the Section 106 with USACE. Site Grading & RAPs Demolition of non-historic sections of the firehouse and site preparations. Storm water detention vault #1 3 Union Square 6/14/2023

  4. Sanitary Relocation and Bypass 4 Union Square 6/14/2023

  5. Firehouse 6 Union Square 6/14/2023