Understanding Outage Coordination Processes and New Equipment
This presentation focuses on enhancing understanding of outage coordination timelines, maintenance level outage requirements, group outage sizes, and the process order for new equipment in the ERCOT system. It covers definitions, timelines for planned transmission and resource outages, as well as maintenance timeline definitions to prevent forced outages.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
Outage Coordination Process and New Equipment 1
Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal processes 2
Objectives At the completion of this course of instruction you will: Identify the ERCOT Outage Coordination timelines Identify the timeline requirement for a maintenance level outage Identify the maximum size of a group outage Identify the correct process order for new equipment in the ERCOT system 3
Definitions NOMCR Network Operations Model Change Request ResTran RESource Owned TRANsmission Equipment 4
Outage Coordination Planned Transmission Timeline Request for Approval* ERCOT must Approve or Reject* More than 90 days 75 days 46 90 days 30 days 9 45 days 4 days 4 8 days No later than 1800 hours 3 days 3 days No later than 1800 hours 2 days *Prior to Planned Start Date/Time 5
Outage Coordination Planned Resource Timeline QSE Request for Approval ERCOT Approval or Rejection Three days 1800 hours, two days prior to start of proposed Outage Four to eight days 1800 hours, three days prior to start of proposed Outage Five Business days after submission. Outages are automatically accepted if not rejected at the end of the fifth Business Day following receipt of request. Greater than 45 days ERCOT must accept, but may discuss reliability and scheduling to minimize cost. Nine to 45 days 6
Outage Coordination Planned Resource Timeline Timelines for Reliability Resource Planned Outages (RMR and Black Start) Request for Approval Not less than 30 days More than 45 days ERCOT Approval or Rejection 15 days before start of proposed Outage 30 days before the start of proposed Outage Note: ERCOT may, at its discretion, relax the 30 day Notice requirement. 7 7
Outage Coordination Maintenance Timeline Definition: Initiated manually to remove equipment from service to perform work on components than could be postponed briefly but is required to prevent potential forced outage and cannot be postponed until the next planned outage. Level 1: Applies to equipment which must be removed from service within 24 hours. (M1) Level 2: Identifies equipment which must be removed from service within 7 days. (M2) Level 3: Applies to equipment which must be removed from service within 30 days. (M3) 8
ResTran Forms are available on resquest Email forms to ResTranOutages@ercot.com Different forms for Forced Outages 9
ResTran Outage Form ALWAYS review the outages after they were submitted by ERCOT on your behalf to make sure that the outage does exactly what you want it to do when you want it to. To update an outage email the most up-to- date form with the new updated information added. 16
Outage Coordination Approvals Approved Outages can be withdrawn any time before it is completed. Planned transmission outages are always studied. Approved -> Done by coordinators Accepted -> Automatic 17
Outage Coordination Availability Short Term: M-F 6AM-6PM, Sa-Su 6AM 2PM Rotating Shifts* Long Term: M-F 6AM-5PM Use OC Blast Accounts Email: OPSOutageCoordination@ERCOT.com Phone: (512) 248 6841 No Voicemail* 18
New Equipment Create plan for switching from old to new equipment May require pseudo equipment i.e. Breakers to switch between equipment Submit a NOMCR for all new and pseudo equipment 19
New Equipment Pseudo Equipment Pseudo Breaker Breaker New Breaker Old Breaker 20
NOMCRs A 21
NOMCRs 22
NOMCRs 23
NOMCRs 24
NOMCRs A 25
New Equipment Outages After the NOMCR has been processed and the equipment has been added to the OS Database Planned End Date is the Energization Date NOMCR >> OS >> Model 26
**BONUS** Extending an outage New Planned End Date Unlimited extensions FR->FE || (PL,M1,M2,M3)->UE Adding Requestor Notes 1000 Characters Only once per group outage The maximum Group Outage size is 30 pieces of equipment 27
**BONUS MIS** Proposed Transmission Outages *All reports are automatically updated every hour on the hour Outage Submitted *When an outage is added to one report it is removed from the previous report Rejected Transmission Outages Approved and Accepted Transmission Outages Planned End > 1 Yr. Old Outage Withdrawn Withdrawal of Approved and Accepted Transmission Outages Removed from MIS Planned End > 1 Yr. Old 28
Questions 29
Questions 1. The last day to enter a Planned Transmission Outage is ________ before the Planned Start Date. A) 1 Day B) 3 Days C) 8 Days D) 45 Days 30
Questions 2. Planned Resource Outages must be accepted when entered ______ before the Planned Start Date. A) >3 Days B) >9 Days C) >30 Days D) >45 Days 31
Questions 3. A level 2 maintenance outage (M2) means that the outaged equipment must be removed _______ to prevent a forced outage. A) <7 Days B) <30 Days C) <7 Hours D) <1 Hour 32
Questions 4. The maximum size of a group outage is _______. A) 10 pieces of equipment B) Unlimited C) 30 pieces of equipment D) 2 megabytes of equipment 33
Questions 5. What is the correct process order for new equipment in the ERCOT system? A) NOMCR >> OS >> Model B) NOMCR >> Model >> OS C) OS >> Model >> NOMCR D) Model >> NOMCR >> OS 34