Support Structure Fabrication Project Overview

K. Hanzel
Support Structure Fabrication
Procurement Strategy
Plan to procure all items individually
Focus on suppliers capable of production
fabrication
2
7/16/15
Budgetary Estimates
Budgetary estimates of pricing and leadtime
were obtained for the following:
Yokes, Collars, Loadpads
Master, False Coil
Aluminum Shells
Nitronic End Plates
Axial & Tension Rods
Estimates based upon redline CERN prints
Updated for domestically available materials and
correction to lengths
3
7/16/15
Yokes, Loadpads & Collars
Budgetary estimates received from 6 vendors
Pricing for all Yokes, Loadpads & Collars range
from $100k – $700k
3 vendor estimates are between $280-$400k
Leadtimes range from 4-16 weeks
Tolerances driving cost
4
7/16/15
Master & False Coil
Budgetary estimates received from 3 vendors
(2 No Bids)
Tolerances are an issue
Tight profile tolerance along length, slots common
zone true position along length
Possible mitigations
Apply tolerances in constrained state, loosen tolerances
Large pricing spread $50k -$450k
2 Vendors under $100k
Leadtime 16 weeks
5
7/16/15
Aluminum Shells
Budgetary estimates from 3 forging vendors, 2
final machining vendors & 3 vendors for forging +
final machining
Pricing for final machined shells
Range $80k-$200k
3 vendors below $120k
Preference is for vendor to procure forging and
provide final machined part
Leadtimes range from 16-29 weeks for finished
machined parts
Tight tolerances, concern with impact of final end
milling on ID concentricity
6
7/16/15
Nitronic End Plates, Axial Rods, & Tension Rods
Budgetary Estimates –
Nitronic End Plates (2 Each):
Estimated Cost -  $26.7k
Leadtime - 10 weeks
Axial Rods (4 each):
Estimated Cost - $11k
Leadtime - 8 weeks
Yoke Tension Rods (8 each):
Estimated Cost - $11k
Leadtime – 8 weeks
7
7/16/15
Procurement Costing Estimate
Estimates (LBNL Burdened @ 24.5%)
Yokes, Loadpads & Collars - $371k
Master, False Coil - $100k
Aluminum Shells - $148k
Nitronic End Plates - $33.3k
Axial & Tension Rods - $27.4k
Total (No Contingency)= $680k
30% Contingency = $204k
Total with Contingency = $884k
8
7/16/15
LBNL Procurement Leadtimes
Procurement Processing Times after Requisition
Submitted
Up to $25k – 14 Days
$25k-$150k – 25 Days
$150k - $500k
Requires competitive sourcing, leadtimes vary (likely 6-
8 weeks)
Above $500k
Advance Acquisition Alert 30 Days prior to requisition
required, additional approvals required, leadtimes on
the order of several months
Financial year close will impact procurements
9
7/16/15
Aluminum Shells Fabrication Schedule
 
10
7/16/15
Yokes, Collars & Loadpads Fabrication Schedule
 
11
7/16/15
Master & False Coil Fabrication Schedule
 
12
7/16/15
Quality Assurance
Collars, Yokes, Load pads
Vendor 1
st
 article inspections & LBNL sample
inspection
Vendor production inspections
LBNL receipt sample inspections
Master & False Coil
Vendor inspection & LBNL receipt inspection
Aluminum Shells
Material certification
Non destructive examination of forging
Vendor inspection & LBNL receipt inspection
13
7/16/15
Slide Note
Embed
Share

An overview of a support structure fabrication project by Hanzel, focusing on procurement strategy, budgetary estimates, vendor quotes, and lead times for various components like yokes, loadpads, collars, master and false coils, aluminum shells, nitronic end plates, axial rods, and tension rods. The project involves obtaining budgetary estimates, analyzing pricing spreads, lead times, tolerances, and possible mitigations for tight tolerance issues. Various vendors have provided estimates and the project aims to procure items individually from suppliers capable of production fabrication.

  • Fabrication project
  • Procurement strategy
  • Budget estimates
  • Vendor quotes
  • Lead times

Uploaded on Sep 25, 2024 | 1 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. Support Structure Fabrication K. Hanzel

  2. Procurement Strategy Plan to procure all items individually Focus on suppliers capable of production fabrication 7/16/15 2

  3. Budgetary Estimates Budgetary estimates of pricing and leadtime were obtained for the following: Yokes, Collars, Loadpads Master, False Coil Aluminum Shells Nitronic End Plates Axial & Tension Rods Estimates based upon redline CERN prints Updated for domestically available materials and correction to lengths 7/16/15 3

  4. Yokes, Loadpads & Collars Budgetary estimates received from 6 vendors Pricing for all Yokes, Loadpads & Collars range from $100k $700k 3 vendor estimates are between $280-$400k Leadtimes range from 4-16 weeks Tolerances driving cost 7/16/15 4

  5. Master & False Coil Budgetary estimates received from 3 vendors (2 No Bids) Tolerances are an issue Tight profile tolerance along length, slots common zone true position along length Possible mitigations Apply tolerances in constrained state, loosen tolerances Large pricing spread $50k -$450k 2 Vendors under $100k Leadtime 16 weeks 7/16/15 5

  6. Aluminum Shells Budgetary estimates from 3 forging vendors, 2 final machining vendors & 3 vendors for forging + final machining Pricing for final machined shells Range $80k-$200k 3 vendors below $120k Preference is for vendor to procure forging and provide final machined part Leadtimes range from 16-29 weeks for finished machined parts Tight tolerances, concern with impact of final end milling on ID concentricity 7/16/15 6

  7. Nitronic End Plates, Axial Rods, & Tension Rods Budgetary Estimates Nitronic End Plates (2 Each): Estimated Cost - $26.7k Leadtime - 10 weeks Axial Rods (4 each): Estimated Cost - $11k Leadtime - 8 weeks Yoke Tension Rods (8 each): Estimated Cost - $11k Leadtime 8 weeks 7/16/15 7

  8. Procurement Costing Estimate Estimates (LBNL Burdened @ 24.5%) Yokes, Loadpads & Collars - $371k Master, False Coil - $100k Aluminum Shells - $148k Nitronic End Plates - $33.3k Axial & Tension Rods - $27.4k Total (No Contingency)= $680k 30% Contingency = $204k Total with Contingency = $884k 7/16/15 8

  9. LBNL Procurement Leadtimes Procurement Processing Times after Requisition Submitted Up to $25k 14 Days $25k-$150k 25 Days $150k - $500k Requires competitive sourcing, leadtimes vary (likely 6- 8 weeks) Above $500k Advance Acquisition Alert 30 Days prior to requisition required, additional approvals required, leadtimes on the order of several months Financial year close will impact procurements 7/16/15 9

  10. Aluminum Shells Fabrication Schedule 7/16/15 10

  11. Yokes, Collars & Loadpads Fabrication Schedule 7/16/15 11

  12. Master & False Coil Fabrication Schedule 7/16/15 12

  13. Quality Assurance Collars, Yokes, Load pads Vendor 1st article inspections & LBNL sample inspection Vendor production inspections LBNL receipt sample inspections Master & False Coil Vendor inspection & LBNL receipt inspection Aluminum Shells Material certification Non destructive examination of forging Vendor inspection & LBNL receipt inspection 7/16/15 13

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#