Status Update of Beam Dump System Integration in CCC by Eric VEYRUNES
Update on the integration status of the beam dump system in CCC by Eric VEYRUNES on behalf of SPSOP. The summary includes details about SBDS devices, MKD and TSU status, GUI, TSU Expert, SBDS Control, SBDS devices conclusion, and various SBDS statuses as of April 15, 2020.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
Status of integration of beam dump system in CCC E. VEYRUNES On behalf of SPSOP https://codimd.web.cern.ch/zcOf3GU7TLG8DX1uNlNaRQ#SPS-beam-dump- system SPS MCM 15. April 2020
SUMMARY SIS SBDS Devices MKD and SBDS SBDS Status SBDS Devices GUI TSU Expert SBDS Control SBDS Devices CONCLUSION ANNEXE 15.04.20 Eric VEYRUNES 2
SUMMARY SIS SBDS Devices MKD and SBDS SBDS Status SBDS Devices GUI TSU Expert SBDS Control SBDS Devices CONCLUSION ANNEXE 15.04.20 Eric VEYRUNES 3
SIS : SBDS devices MKD Status Permit RF Device in Lab Interface TSU ready EARLY1 enable ABT_State Not available EARLY2 enable Trigger enable XTIM Standard enable Not visible in SIS ABT_Tank (1-2-..) Temperature SIS Vacuum SBDS Permit LVDTs BemCtrl Energy Temperatures SMM beamPermit FAN Vacuum from PVSS Water Cooling 15.04.20 Eric VEYRUNES 4
SIS : MKD and SBDS MKD and TSU status SBDS Status 15.04.20 Eric VEYRUNES 5
SUMMARY SIS SBDS Devices MKD and SBDS SBDS Status SBDS Devices GUI TSU Expert SBDS Control SBDS Devices CONCLUSION ANNEXE 15.04.20 Eric VEYRUNES 6
SBDS Status : SBDS devices ABT_State Devices Monitored Device in Lab RF TSU Interface ABT_TANK Not available (1-2- ) Temperature Vacuum ABT_STATE ABT_TIMING EARLY1 EARLY DUMP XTIM SBDS status EARLY2 STANDARD DUMP BCT BemCtrl Energy BLM LVDTs IPOC Temperatures SMM Cooling beamPermit Vacuum from PVSS FAN 15.04.20 Eric VEYRUNES 7
SBDS Status : GUI 15.04.20 Eric VEYRUNES 8
SBDS Status : TSU Expert 15.04.20 Eric VEYRUNES 9
SUMMARY SIS SBDS Devices MKD and SBDS SBDS Status SBDS Devices GUI TSU Expert SBDS Control SBDS Devices CONCLUSION ANNEXE 15.04.20 Eric VEYRUNES 10
SBDS Control : SBDS devices Interface Temperature Device in Lab ABT_TANK (1-2- ) Not available Vacuum ABT_STATE SBDS Control EARLY1 ABT_TIMING EARLY DUMP EARLY2 XTIM STANDARD DUMP 15.04.20 Eric VEYRUNES 11
SUMMARY SIS SBDS Devices MKD and SBDS SBDS Status SBDS Devices GUI TSU Expert SBDS Control SBDS Devices CONCLUSION ANNEXE 15.04.20 Eric VEYRUNES 12
CONCLUSION ABT_Tank missing ABT_Timing missing TSU Clients definition, from N. Magnin Lab Devices SIS Resume signals from MKD, TSU and SMM MKD Status provide diagnostics for MKD, TSU and SMM 15.04.20 Eric VEYRUNES 13
ANNEXE LSS5 Beam dump cooling and ventilation https://edms.cern.ch/document/2363972/0.1 Page 6 About this line : To prevent the beam dump to be operated with a lack of air-cooling, it will be connected to the SPS Beam Interlock System (BIS) via the Software Interlock System (SIS). An air flow switch will be connected to SIS via EN/STI supervision. For me the comportement will be : To prevent the beam dump to be operated with a lack of air-cooling, it will be connected to the SPS Beam Interlock System (BIS) to a dedicated input and the Software Interlock System (SIS). An air flow switch will be part of this protection. 15.04.20 Eric VEYRUNES 14