Recap of WP1 Project Management and Achievements
WP1, managed and coordinated by Kristina Fiedler, focuses on strategic steering, project monitoring, administrative and financial support within the Horizon 2020 programme. Achievements include organizing ExCom meetings, setting up governance, risk management, financial support, and delivering project guidelines. Milestones achieved include the REMEDIA management framework.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
WP1 - Project Management & Coordination presented by Kristina Fiedler 30/09/2021 Review meeting 30/09/2021 This project has received funding from the European Union s Horizon 2020 research and innovation programme under grant agreement No 874753
WP1 Objectives for period 1 Organise kick-off and first Executive Committee (ExCom) meeting Transfer of prefinancing Set up management tools Set up governance Review meeting 30/09/2021 2
WP1 achievements Task 1.1: Strategic steering (M1-M60 ) Leader: P01-INSERM; Contributors: Executive Committee (WP leaders) Governance bodies (General Assembly & Executive Committee set up) Scientific Advisory Board recruited Monthly ExCom calls to discuss bottlenecks and prepare GA votes Decision on changing strategy for database set up: inclusion of new partner KADUCEO Task 1.2: Project monitoring and risk management (M1-M60) Leader: P01-INSERM, Contributors: P13-IT & Executive Committee (WP leaders) Regular monitoring of WPs and detection of bottlenecks/problems via monthly ExCom calls Assessment done on COVID sanitary measures impact First Risk management plan set up Review meeting 30/09/2021 3
WP1 achievements Task 1.3: Administrative and Financial Support (M1-M60) Leader: P01-INSERM, Contributors: P13-IT Prefunding distributed among partners First amendement organised (new partner: partner 15 Kaduceo; partner 6 LNI changed into partner 14 Wellspring; contribution of all partners to payment of external ethic advisor) First reporting coordinated and submitted in time Project Management Handbook sent to all partners Review meeting 30/09/2021 4
WP1 WP1 deliverables Del n Date Delivery Comment WP Partners Type Title Project Management Guidelines Project Risk Management Plan Data Management Plan P01a - Inserm P01a - Inserm P01a - Inserm D1.1 1 R 3 Approved Approved D1.2 1 R 3 6 Approved D1.4 1 ORPD Review meeting 30/09/2021 5
WP1 WP1 Milestones datePartners Comment P01a Inserm WP Due N Title Milestone REMEDIA management framework Achieved MS1 1 3 Review meeting 30/09/2021 6
WP1 Management Hurdles and bottlenecks: Only online meetings were possible (except kick-off!) Partner 7 CEGX announced its withdraw at end of first period Decisions/actions to be taken within the next months: Substitution for P7 CEGX: GA vote to be prepared and organised, then ammendment Review meeting 30/09/2021 7
WP1 Scientific Management Meetings organised: Kick-off meeting in Paris 23th-24th January 2020 (in person) ExCom calls once a month, one hour (starting in March 2020) Online consortium meeting 11-12th May 2021 Meetings to come: Consortium meeting to be scheduled for first trimester of 2022 (in person) Ongoing collaborations /connections to other WPs: Steady contact with all WPs via the monthly ExCom calls Review meeting 30/09/2021 8
WP1 Outlook: Objectives for period 2 Distribute first payment after report validation Organise replacement for Partner 7 CEGX via amendement Organise a (in person) consortium meeting Continue with monthly ExCom calls for project monitoring Review meeting 30/09/2021 9
WP1 backup slides -overview of tasks- end month 60 60 60 60 30 36 48 36 48 60 36 42 60 60 60 60 40 60 60 60 WP Task Title Start month statut task nb 1.1 1.2 1.3 2.1 2.2 2.3 2.4 3.1 3.2 3.3 4.1 4.2 4.3 5.1 5.2 5.3 6.1 6.2 6.3 7.1 WP1 WP1 WP1 WP2 WP2 WP2 WP2 WP3 WP3 WP3 WP4 WP4 WP4 WP5 WP5 WP5 WP6 WP6 WP6 WP7 Strategic steering Project monitoring and risk management Administrative and Financial Support Preexisting data integration Exposome data enrichment Descriptive analyses and phenotypic characterization Exposome-phenotype associations Development of an environment toolbox Development of a biomarker toolbox Development of an integrated sensor device Generation and characterization of complex representative atmosphere(s) Implementation of more complex simulated external exposome Exposure of preclinical models (na ve, COPD and Cystic Fibrosis) Machine learning supervised analyses and prediction models Causal inference modelling Pan European multicriteria risk assessment analyses Development of the econometric model Evaluation of Ethics and Legal impacts Development of Cost-Effectiveness simulations models Communication and dissemination activities Designing Effective Guidelines/Recommendations and presentation of the REMEDIA toolbox IP Management Exploitation of results Governance of the Network Set up an external Network Advisory Board (NAB) Periodic Human Exposome Network meetings Joint strategy for communication and dissemination and linking to policy Joint working groups 1 1 1 1 1 12 30 1 1 43 1 24 24 36 36 6 25 25 30 1 on schedule on schedule on schedule delayed on schedule delayed on schedule delayed delayed not started yet on schedule ahead schedule ahead schedule not started yet not started yet on schedule ahead schedule not started yet not started yet on schedule WP7 1 60 on schedule 7.2 7.3 7.4 8.1 8.2 8.3 8.4 8.5 WP7 WP7 WP8 WP8 WP8 WP8 WP8 1 1 46 1 46 1 1 60 60 60 3 60 18 60 on schedule on schedule on schedule on schedule on schedule on schedule on schedule Review meeting 30/09/2021 10
WP1 backup slides -overview deliverables- Deliverables of period 1 Nber Titel WP Partners Date Delivery Status Comments D1.1 Project Management Guidelines WP1 P01a -Inserm 3 submitted D1.2 Project Risk management plan WP1 P01a -Inserm 3 submitted submitted D1.4 WP1 P01a -Inserm Data Management Plan 6 D4.1 WP4 Atmosphere type Website, logo and communication tools P02-LISA 18 submitted D7.1 WP7 P13-IT 3 submitted D7.2 Intellectual property workshop WP7 P13-IT 12 submitted D8.1 WP8 Report 4: Joint Network Advisory Board Inserm 3 submitted new forecast date: September (M21) 8.2 WP8 Report 8: Policy Strategy Inserm 18 delayed 9.1 WP9 H - Requirement No. 2 Inserm 12 submitted 9.2 WP9 HCT - Requirement No.3 Inserm 3 submitted 9.3 WP9 HCT - Requirement No.4 Inserm 12 submitted New forecast date: September 2021 (M21) 9.4 WP9 POPD - Requirement No 5 Inserm 6 delayed 9.5 WP9 A - Requirement No. 6 Inserm 6 submitted 9.6 WP9 GEN - Requirement No. 8 Inserm 3 submitted 9.7 WP9 NEC - Requirement No.9 Inserm 6 submitted 9.8 WP9 EPQ - Requirement No.8 Inserm 12 submitted Review meeting 30/09/2021 11