Progress on Pedestrian Bridges Programme in KwaZulu-Natal

undefined
T
r
a
n
s
p
o
r
t
 
I
n
f
r
a
s
t
r
u
c
t
u
r
e
 
&
R
e
g
i
o
n
a
l
 
S
e
r
v
i
c
e
s
P
R
O
G
R
E
S
S
 
O
N
 
P
E
D
E
S
T
R
I
A
N
 
B
R
I
D
G
E
S
 
P
R
O
G
R
A
M
M
E
3
0
 
J
a
n
u
a
r
y
 
2
0
1
9
P
r
e
s
e
n
t
a
t
i
o
n
 
O
u
t
l
i
n
e
1.
Background
2.
Summary of Pedestrian Bridges
3.
Progress to Date
4.
Implementation Plan for Pedestrian Bridges
2
B
a
c
k
g
r
o
u
n
d
3
A Desktop Study was conducted by the Department  in
2006, where schools with learners and teachers that had
missed more than a month of school because of lack of
access during heavy rains were identified.
The Department of Education was engaged to get the list
of schools that were affected and each school principal
was called to understand the problem, and then
Professional Service providers were sent to out to site to
do assessments.
That exercise identified that there was a need of 471
pedestrian bridges.
S
u
m
m
a
r
y
 
o
f
 
P
e
d
e
s
t
r
i
a
n
 
B
r
i
d
g
e
s
4
P
r
o
g
r
e
s
s
 
t
o
 
D
a
t
e
5
Department has since built over 116 Pedestrian
bridges from 2006/2007 Financial Year to 2018/2019
Financial Year.
Some of the Pedestrian Bridges changed to vehicular
bridges after detailed analysis identified that there was
a need for vehicular crossing as well.
The Department is in the process of quantifying
pedestrian bridges that have changed to vehicular.
P
l
a
n
 
f
o
r
 
t
h
e
 
I
m
p
l
e
m
e
n
t
a
t
i
o
n
 
o
f
 
P
e
d
e
s
t
r
i
a
n
B
r
i
d
g
e
s
 
P
r
o
g
r
a
m
m
e
6
The Department is committed to building more
pedestrian bridges.
The target for pedestrian bridges for the past five plan
was set at 10 Pedestrian bridges per financial year.
The Department will increase the target of number of
pedestrian bridges to be built to 13 in the outer FY.
P
l
a
n
 
f
o
r
 
t
h
e
 
I
m
p
l
e
m
e
n
t
a
t
i
o
n
 
o
f
 
P
e
d
e
s
t
r
i
a
n
B
r
i
d
g
e
s
 
P
r
o
g
r
a
m
m
e
7
The Department is in the process of implementing
Bailey Bridges Programme in order to fast track the
implementation of Pedestrian Bridges.
The MOA with the Office of the Premier, Department
of Public Works, and Provincial COGTA has been
finalized enabling the Department to utilize Public
Works and Defense for the implementation of
Pedestrian Bridges.
11 Bridges have been assessed and approved for
implementation using Bailey bridges.
P
l
a
n
 
f
o
r
 
t
h
e
 
I
m
p
l
e
m
e
n
t
a
t
i
o
n
 
o
f
 
P
e
d
e
s
t
r
i
a
n
B
r
i
d
g
e
s
 
P
r
o
g
r
a
m
m
e
8
This programme however has limitations of a span of
36m and maxing load capacity (Dead and Live) of
16Tons, so this means only Small River crossings can
be built using Bailey Bridges.
The Department plans to implement 8 bridges per
year using this programme.
T
H
A
N
K
 
Y
O
U
9
Slide Note
Embed
Share

Department of Transport in KwaZulu-Natal has made strides in building pedestrian bridges to enhance access to schools and communities. With over 116 bridges constructed since 2006, the program aims to increase safety and mobility for pedestrians.

  • Transport
  • Infrastructure
  • Pedestrian Bridges
  • KwaZulu-Natal
  • Progress

Uploaded on Feb 16, 2025 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Transport Infrastructure & Regional Services Department of Transport KwaZulu-Natal Umnyango Wezokuthutha PROGRESS ON PEDESTRIAN BRIDGES PROGRAMME 30 January 2019 Prosperity through mobility

  2. Presentation Outline Background Summary of Pedestrian Bridges Progress to Date Implementation Plan for Pedestrian Bridges 1. 2. 3. 4. Prosperity through mobility Prosperity through mobility Prosperity through mobility 2

  3. Background A Desktop Study was conducted by the Department in 2006, where schools with learners and teachers that had missed more than a month of school because of lack of access during heavy rains were identified. The Department of Education was engaged to get the list of schools that were affected and each school principal was called to understand the problem, and then Professional Service providers were sent to out to site to do assessments. That exercise identified that there was a need of 471 pedestrian bridges. Prosperity through mobility Prosperity through mobility Prosperity through mobility 3

  4. Summary of Pedestrian Bridges Number of Proposed Pedestrian Bridges 52 26 66 53 13 25 12 118 51 36 19 471 DC name Ugu uMgungundlovu Uthukela Umzinyathi Amajuba Zululand Umkhanyakude King Cetshwayo Ilembe Ethekwini Harry Gwala DC21 DC22 DC23 DC24 DC25 DC26 DC27 DC28 DC29 ETH DC43 TOTAL Prosperity through mobility Prosperity through mobility Prosperity through mobility 4

  5. Progress to Date Department has since built over 116 Pedestrian bridges from 2006/2007 Financial Year to 2018/2019 Financial Year. Some of the Pedestrian Bridges changed to vehicular bridges after detailed analysis identified that there was a need for vehicular crossing as well. The Department is in the process of quantifying pedestrian bridges that have changed to vehicular. Prosperity through mobility Prosperity through mobility Prosperity through mobility 5

  6. Plan for the Implementation of Pedestrian Bridges Programme The Department is committed to building more pedestrian bridges. The target for pedestrian bridges for the past five plan was set at 10 Pedestrian bridges per financial year. The Department will increase the target of number of pedestrian bridges to be built to 13 in the outer FY. Prosperity through mobility Prosperity through mobility Prosperity through mobility 6

  7. Plan for the Implementation of Pedestrian Bridges Programme The Department is in the process of implementing Bailey Bridges Programme in order to fast track the implementation of Pedestrian Bridges. The MOA with the Office of the Premier, Department of Public Works, and Provincial COGTA has been finalized enabling the Department to utilize Public Works and Defense for the implementation of Pedestrian Bridges. 11 Bridges have been assessed and approved for implementation using Bailey bridges. Prosperity through mobility Prosperity through mobility Prosperity through mobility 7

  8. Plan for the Implementation of Pedestrian Bridges Programme This programme however has limitations of a span of 36m and maxing load capacity (Dead and Live) of 16Tons, so this means only Small River crossings can be built using Bailey Bridges. The Department plans to implement 8 bridges per year using this programme. Prosperity through mobility Prosperity through mobility Prosperity through mobility 8

  9. THANK YOU Prosperity through mobility Prosperity through mobility 9

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#