Key discussions at the Primrose Elementary School meeting on October 26, 2022 included introductions, a review of events from May to October, next steps regarding well issues, and Q&A sessions. The meeting covered challenges faced by the school related to water supply, well failures, and measures being taken to address these issues for the well-being of students and staff.


Uploaded on Sep 30, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Primrose Elementary School Oct. 26, 2022

  2. Agenda Introductions Review of events May to October Next Steps Questions and Answers

  3. Introductions Marianne Millsap, Principal Ashley Hopkins, Vice-Principal Belal Taha, Superintendent Brent McDonald, Executive Superintendent Dilip Parmar, Senior Facilities Manager Glen Regier, Executive Superintendent

  4. Review of Events Focus on events since May 2022 Investigations underway were regarding the taste of the water and water pressure September 7th Washrooms were not working due to low water pressure September 8th School was closed for the day September 9th School reopened with portable toilets

  5. Review of Events September 12th well completely failed September 13th Well contractor attempted to remediate the well and was not successful September 19th Trailer style bathrooms arrived on site September 20th Water tanker connected to school and is providing adequate water supply to the school Sept current New well specifications

  6. Next Steps New well: Well specifications received Well drilling contracting process underway Test drilling to be completed New well site to be drilled Evaluation and determination of next phase of work Quality of well water will impact next steps

  7. Next Steps Additional measures for improving resilience of systems Application of lessons learned across other school sites with wells Review of enrolment levels at Primrose

  8. Questions and Answers - Options Ask at microphone Follow-up questions with staff this evening Follow-up questions after meeting should continue to be directed to the school Communications on updates will also continue to come through the school