The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. ITF Space Needs

  2. Total Number of packages per trip Weight per unit Units per package Type of package Package weight Type of trip Number of Hoist Trips Description Contact Date Number of Units Width Height Length Comment m m m kg kg ea. Dataroom Setup 118 Apr-18 1 Cage 1 fork lift Assume one forklift to move pallets and crates. Assume around 15 tables for lunch, meetings, workstations Oct-18 15 25 4 pallets 1.2 1 1.5 100 2 Cage 2 Tables 25 25 1 pallet 1.2 1 0.8 25 3 Cage 9 Chairs Need roughly 10 chairs and 10 benches. 3 refrigerators, 4 microwaves, one cabinet, three bottled water dispensers Oct-18 Cage 3 kitchen outfitting Stk pallet box Oct-18 5 25 5 1.2 2 0.8 100 1 Cage 1 Workstations for data room Assume around 5 workstations 52 racks total each rack on a pallet and 3 pallets in the cage Oct-18 52 100 1 Pallet 0.8 2 1.2 1 4 Cage 13 Dataroom Racks Guess how many trips for conduit wire and whatever to connect the racks Oct-18 5 Rack Power infrastructure Stk pallet box Oct-18 2184 5 10 1.2 2 0.8 50 3 Cage 73 Take the maximum assuming 1U high, 42U racks and 52 racks. Then assume each module is 150mm high with packaging and put them in the pallet boxes stacked two high. 5U per box and 10 U per stacked box DAQ electronics modules One trip will take 6 stacked pallet boxes which should be enough. Oct-18 Cage 1 DAQ cables Guess(step ladders, coat racks, shelves, tools, oscilloscopes, ) Oct-18 Cage 10 DAQ Misc.

  3. Total Number of packages per trip Weight per unit Units per package Type of package Package weight Number of Hoist Trips Description Contact Date Number of Units Width Height Length Type of trip Comment Oct-18 95 Installation SP Setup Oct-18 100 90 6 Pallet 0.8 2.5 1.2 540 3 Cage 6 DSS feedthroughs Assume 6 feedthrough per pallet Oct-18 45 132 15 Crate 0.6 1 5 1980 1 Slung 3 DSS I-Beams Main I-Beams Assume 15 I-beams bundled in a crate Oct-18 5 50 5 Crate 250 1 Cage 1 DSS switchyard beams Assume 5 beam segments 50 kg each as a first guess Oct-18 Pallet 0.8 1 1.2 500 3 Cage 4 Components include beam crawlers, trollies, safety switches, hardware, leak tester, seals, survey equipment. Design is at an early stage here so make a guess at 12 pallets DSS switchyard Misc. Oct-18 2 200 1 Crate 2 1 3 200 Slung 2 DSS feedthrough installation tooling Tripods and portable cleanrooms Oct-18 2 500 1 Crate 0.8 1 4 1000 Slung 2 TCO beams and mounts Guess Oct-18 Oct-18 Cage 10 Cleanroom Guess: Lighting, fire, power ventilation Oct-18 Slung 10 Cleanroom Guess TCO Roof, Beam to hold curtains, Plastic curtains, conduits, Pipe Oct-18 2 Cage 20 Installation towers Guess: Stairs, Small Beams, flooring, Oct-18 2 Slung 20 Installation towers I-Beams Oct-18 Changing room outfitting Oct-18 2 25 1 Pallets 0.8 2 2 35 2 Cage 1 Labcoat Rack Oct-18 6 6 Pallets 0.8 1 2 1 Cage 1 Locker racks + Shelves Benches, shoe cleaner, air purifyer, locker bins Oct-18 Cage 2 Oct-18 1 100 1 Pallet 0.8 2 1.2 100 0.3 Cage 1 Storage cabinet Oct-18 Install Equipment Oct-18 3 3 Manlifts one under bridge two in the cryostat Oct-18 Cryostat lighting Oct-18 Cage 5 Bridge Crane under bridge Guess: 5 cage trips Oct-18 2 200 1 Pallets 0.8 1 1.2 2 Cage 1 Tool Boxes Oct-18 3 50 1 Pallets 0.8 2 1.2 50 3 Cage 1 Storage Cabinets Oct-18 1 100 1 Pallets 0.8 1 1.2 100 1 Cage 1 APA installaiton fixtures Oct-18 1 100 1 Pallets 0.8 1 1.2 100 1 Cage 1 CPA Installaiton Fixture

  4. Number of packages per trip Total Number of Units Number of Hoist Trips Weight per unit Units per package Type of packageWidth Height LengthPackage Type of trip Description Contact Date Comment weight Assume near maximum number of racks. 100 racks Assume air cooling and one air handler per row of 3 racks Oct-18 90 SP cryostat roof outfitting Oct-18 34 50 1 Pallet 0.8 0.5 1.2 50 3 Cage 12 Rack Cooling Air Handlers Water pipe to air handlers Racks Cable Trays Rack power Oct-18 2 Cage 4 Guess Pipe, Valves, insurlation, Tools, Oct-18 Oct-18 Oct-18 100 100 1 Pallet 0.8 2 1.2 50 3 Cage 34 20 20 WAG WAG

  5. Number of packages per trip Total Number of Units Number of Hoist Trips Weight per unit Units per package Type of packageWidth Height LengthPackage Type of trip Description Contact Date Comment weight Oct-18 Oct-18 Oct-18 7 4 1 Endwall #1 installaiton Endwall Field Cage Panel Misc. Beams 16 4 Crate 1.4 1 3 4 5 1 Slung Cage 0.5 Transvers beams? Fixtures, Tools, Test Equip, Installation hoist, tooling Oct-18 0.8 1.2 Cage 2 Misc. pallets

  6. Number of packages per trip Total Number of Units Number of Hoist Trips Weight per unit Units per package Type of packageWidth Height LengthPackage Type of trip Description Contact Date Comment weight Oct-18 Oct-18 Oct-18 APA installation phase APA CPA Field cage top bottom modules 150 150 2 1 Box Crate 1.4 1 7 2.5 3 1 4 Slung Cage 75 38 0.5 Oct-18 150 2 Crate 1.4 4 3 1 Slung 75 If 2 APA per box then the cables come down separate. If one APA per box then the cables come in palets. Assume 4 pallets per APA APA yokes, cable ducts, test equipment, tooling Oct-18 600 1 Pallet 0.8 1 1.2 3 cage 200 Cables Oct-18 0.8 1.2 20 Misc. pallets

  7. Number of packages per trip Total Number of Units Number of Hoist Trips Weight per unit Units per package Type of packageWidth Height LengthPackage Type of trip Description Contact Date Comment weight Oct-18 Oct-18 Oct-18 7 4 1 Endwall #2 installaiton Endwall Field Cage Panel Misc. Beams 16 4 Crate 1.4 1 3 4 5 1 Slung Cage 0.5 Transvers beams? Fixtures, Tools, Test Equip, Installation hoist, tooling Oct-18 0.8 1.2 Cage 2 Misc. pallets