Horizon 2020 Grant Agreement Amendments Process

Amendments to the
 Grant Agreement
 
Amendments may not result in changes that
if known before awarding the grant — would have had an impact on
the decision to award it
 
Those are mostly changes that:
 
   may have had an impact on the assessment of the applicant with
 
regard to the 
eligibility and selection criteria
 
   breach the principle of 
equal treatment 
of applicants
 
   involve changes in the action and/or budget which may have affected
 
the assessment with regard to the 
award criteria 
established in the call
 
   do not comply with the 
Rules for Participation, Financial Regulation
 
or
 
provisions of 
the GA
Conditions
 
WHEN ?
WHEN ?
Requests must be submitted:
Requests must be submitted:
   * 
before the end of the action
   
 
Exception
: 
special cases where it is necessary to change:
   
  -  
coordinator
   
  -  bank account to make the payment of the balance
* 
sufficiently in advance 
to allow preparation and proper
 
   analysis before the changes are due to take effect
Requests must be unambiguous and complete
Requests must be unambiguous and complete
       
           
Example:
 
to correct an error made in a GA 
Coordinator
Coordinator
 - 
 - 
submits/signs/receives amendments on behalf of beneficiaries
    
  
Exception:  
if 
change of coordinator without its agreement request must be 
 
    
submitted by another beneficiary on behalf of the others
 
 
   
   
 
 Coordinator - 
 Coordinator - 
must ensure internally the agreement of the consortium
  
based on internal decision‑making processes set out in the consortium agreement
  
(e.g. unanimity, simple or qualified majority)
WHO ? 
WHO ? 
Requested by the parties
Requested by the parties
 
Prepared electronically 
Prepared electronically 
        Requesting party encodes the request in the Funding & Tenders Portal
          *  Indicate reasons 
          *  Upload supporting documents
          *  Get validations done before submitting the request
            
 
  
(e.g. new legal entity, bank account validations)
 
Submitted & signed electronically 
Submitted & signed electronically 
(by PLSIGN)
Counter signed electronically 
Counter signed electronically 
by receiving party (by PLSIGN)
HOW? 
HOW? 
            
   
 
 
 
NEW
Cases where
Cases where
an amendment
an amendment
is necessary
is necessary
(some examples)
(some examples)
 
 
 
 
 
A
M
E
N
D
M
E
N
T
S
 
T
T
e
e
r
r
m
m
i
i
n
n
a
a
t
t
i
i
o
o
n
n
 
 
b
b
y
y
 
 
C
C
o
o
m
m
m
m
i
i
s
s
s
s
i
i
o
o
n
n
/
/
A
A
g
g
e
e
n
n
c
c
y
y
 
 
(
(
A
A
r
r
t
t
i
i
c
c
l
l
e
e
 
 
5
5
0
0
.
.
3
3
)
)
 
 
  
 
'Contradictory procedure' 
(30 days)
 
 
  
 
'
Termination date
' 
either:
  
  
-
  date specified in notification confirming termination, or
  
  
-
  day after coordinator or beneficiary concerned receives the notification
 
 
 
  
 
Coordinator must submit within 60 days after termination
  
   
an amendment request with supporting documents 
!
!
 
 
I. Beneficiaries - changes
Commission/Agency
Commission/Agency
beneficiaries
beneficiaries
 
 Termination of participation  
 Termination of participation  
 
 
     
     
    
    
triggered by:
triggered by:
 
 
 
 
T
T
e
e
r
r
m
m
i
i
n
n
a
a
t
t
i
i
o
o
n
n
 
 
b
b
y
y
 
 
t
t
h
h
e
e
 
 
b
b
e
e
n
n
e
e
f
f
i
i
c
c
i
i
a
a
r
r
i
i
e
e
s
s
 
 
(
A
r
t
i
c
l
e
 
5
0
.
2
)
 
The coordinator:
 
  
notifies termination to Commission/Agency
 
  
submits the amendment request 
at the same time 
-
 
NEW
NEW
  
* 
 
Request must include opinion of the beneficiary whose participation
  
   
is terminated, or proof that it has been requested in writing
 
  
* 
 
‘Termination date’ must be after notification
 
 
Consequences:
 
 
T
e
rmination date 
is added to the Preamble of the GA 
  - 
NEW
NEW
 
C
hange of Annexes 1 & 2
 
  
 
If termination is since the beginning
 
the 
applicable options will be
  
removed/
changed/become not applicable 
  
   
I. 
Beneficiaries - changes 
  
Before submission
:
 
 
New beneficiary must be validated & have a PIC
 
 
Required documents must be signed:
-
 
 
 
G
P
F
 
w
i
t
h
 
D
e
c
l
a
r
a
t
i
o
n
 
o
f
 
H
o
n
o
u
r
  
-    Annex 3 - 
Accession Form
  
-    Annex 3a, Annex 3b (if applicable)
Consequences:
 
 
 
 
 
New beneficiary and accession date are added to Preamble GA
 
 
 
 
 
C
hange of Annexes 1 & 2
 
 
 
 
 
GA options for that 
beneficiary will be added/changed/become applicable 
 
 
        (e.g. linked third party, IO) 
 
 
I. Beneficiaries - changes
Adding a new beneficiary
Partial takeover
’ means that 
some assets 
of the beneficiary have been
taken over 
by another entity 
(e.g. partial acquisition)
It must be clarified:
*
 
Contractual position
 
of former and new beneficiary 
(vis-à-vis
 
Commission/Agency and the other beneficiaries)
*
 
Financial liability
 
of the new beneficiary for the former beneficiary's
 
debts 
towards the Commission/Agency or the Guarantee Fund 
   
                 
I. Beneficiaries - changes
Change of beneficiary due to "partial takeover"
(FP7: ‘partial transfer of rights and obligations’)
 
 
 
Significant change of 
action tasks
 
(e.g. if tasks are 
 
added/removed) 
 
  
or their 
division
 among the beneficiaries
 
  
 
Changes concerning 
subcontracts 
or
 in-kind contributions
 
  
  
provided by third parties 
(against payment or free-of-charge) 
 
  
 
Changes concerning 
linked third parties
, tasks to be carried 
  
  
out and budget
 
 
 
 
Changes to the 
options 
in the GA 
(e.g. options removed or added)
 
 
 Example:  
adding the options to provide trans-national access to research 
 
    
     infrastructure requires normally a change of Annex 1 &/or Annex 2
 
III. Action or action implementation - changes
   Change to Annex 1 
- Description of the action
  B
udget transfers:
 
 
between beneficiaries 
or
 budget categories 
(or both) 
   
  
due to a significant change of Annex 1
 
 
to a form of costs that is not used by the beneficiary
 
 
Except for transfers
 
: 
 
 
within the personnel costs, and
       
to costs of internally invoiced goods and services
 
 
  
Example:  
access costs for transnational access to research infrastructure
  
   
     
 
 
 
     
     
  
  
 
 
  
  
Additional information on the estimated budget
    
If calculation of 
unit costs 
needs to be provided or updated
IV. Financial aspects - changes
   Change to Annex 2  - Estimated budget
Change of Annex 2a
Cases where an
Cases where an
amendment is
amendment is
not
not
necessary
necessary
A
M
E
N
D
M
E
N
T
S
 
Cases where NO amendment is needed:
Certain budget transfers
N
E
W
 
!
(
2
0
1
7
)
  
Change of name/address 
of beneficiaries & linked third party
 
Change of beneficiary due to universal takeover
 
(In FP7: ‘universal transfer of rights and obligations’)
Changes to name of the bank/address of branch/
 
name of account holder 
(validation of this data on the FP by the
 
Commission is sufficient)
P
P
R
R
O
O
C
C
E
E
D
D
U
U
R
R
E
E
 
 
t
t
o
o
 
 
c
c
h
h
a
a
n
n
g
g
e
e
 
 
t
t
h
h
i
i
s
s
 
 
i
i
n
n
f
f
o
o
r
r
m
m
a
a
t
t
i
i
o
o
n
n
Other cases where no amendment is needed:
 
Beneficiaries must keep 
information stored in the ‘Beneficiary
 
Register’ up to date 
via the Funding & Tenders Portal 
(Article 17.2)
 
The LEAR of the beneficiary updates this information
 
Beneficiaries have to inform as well the coordinator (offline)
 
Validation Services validate the information in the IT system
 
The validated changes will be notified via the Portal
 Note:  
 Note:  
If Commission/Agency considers change affects the action
  
   implementation, it will inform the coordinator
  
   Example: 
beneficiary changes its legal address to a third country
How is this information updated?
Amendment Procedure
     
NEW
 
     
A request containing several changes 
to the GA will be 
  
 
     considered 
 
as a 
package
 
 
- 
 
cannot be divided into several requests
  
- 
 
request will be agreed or rejected as 
 
a whole
  
An amendment 
request cannot be changed
  
A request can be 
withdrawn
 at any moment before signature
 
   
There is 
no tacit approval 
of amendments 
 
Amendment procedure
👉
👉
 
An amendment 
enters into force 
enters into force 
and is binding 
and is binding 
from the
 
moment both parties sign it 
(in the electronic exchange system)
👉
👉
 
An amendment 
takes effect 
takes effect 
(
the changes will start to apply):
 
  
 
when the amendment enters into force, 
or
 
  
 
on the date agreed by the parties 
  
* 
This date should normally be 
after
 the entry into force
  
* If an amendment request involves several changes, they could take effect
  
   on 
different dates.
 
Example: 
change of Annex 1 & change of bank account
  
* 
Depending on the type of change, the date of taking effect may have an
  
   
impact on the eligibility of costs. 
Example: 
addition of new beneficiary
Entry into force and taking effect
ADDITIONAL INFO:
Funding & Tender opportunities Portal
h
t
t
p
s
:
/
/
e
c
.
e
u
r
o
p
a
.
e
u
/
i
n
f
o
/
f
u
n
d
i
n
g
-
t
e
n
d
e
r
s
/
o
p
p
o
r
t
u
n
i
t
i
e
s
/
p
o
r
t
a
l
/
s
c
r
e
e
n
/
p
r
o
g
r
a
m
m
e
s
/
h
2
0
2
0
 
H
2
0
2
0
 
A
n
n
o
t
a
t
e
d
 
M
o
d
e
l
 
G
r
a
n
t
 
A
g
r
e
e
m
e
n
t
 
(
A
G
A
)
 
(
A
r
t
i
c
l
e
 
5
5
)
h
t
t
:
/
/
e
c
.
e
u
r
o
p
a
.
e
u
/
r
e
s
e
a
r
c
h
/
p
a
r
t
i
c
i
p
a
n
t
s
/
d
a
t
a
/
r
e
f
/
h
2
0
2
0
/
g
r
a
n
t
s
_
m
a
n
u
a
l
/
a
m
g
a
/
h
2
0
2
0
-
a
m
g
a
_
e
n
.
p
d
f
Guidance: 'Amendment types & supporting documents'
h
t
t
p
:
/
/
e
c
.
e
u
r
o
p
a
.
e
u
/
r
e
s
e
a
r
c
h
/
p
a
r
t
i
c
i
p
a
n
t
s
/
d
a
t
a
/
r
e
f
/
h
2
0
2
0
/
o
t
h
e
r
/
g
m
/
h
2
0
2
0
-
g
u
i
d
e
-
a
m
e
n
d
-
t
y
p
e
s
_
e
n
.
p
d
f
H
o
r
i
z
o
n
 
2
0
2
0
 
O
n
-
l
i
n
e
 
M
a
n
u
a
l
h
t
t
p
:
/
/
e
c
.
e
u
r
o
p
a
.
e
u
/
r
e
s
e
a
r
c
h
/
p
a
r
t
i
c
i
p
a
n
t
s
/
d
o
c
s
/
h
2
0
2
0
-
f
u
n
d
i
n
g
-
g
u
i
d
e
/
g
r
a
n
t
s
/
a
p
p
l
y
i
n
g
-
f
o
r
-
f
u
n
d
i
n
g
/
r
e
g
i
s
t
e
r
-
a
n
-
o
r
g
a
n
i
s
a
t
i
o
n
_
e
n
.
h
t
m
Thank you very much
Thank you very much
for your attention!
for your attention!
 
Slide Note
Embed
Share

Horizon 2020 grant agreements can be amended to change specific data or options, with conditions in place to ensure fairness and compliance with rules. Requests for amendments must be submitted before the end of the action, primarily by the Commission/Agency or Consortium, following a paperless process prepared electronically.

  • Grant Agreement
  • Amendments
  • Horizon 2020
  • Process
  • Electronic Submission

Uploaded on Sep 27, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. HORIZON 2020 HORIZON 2020 Amendments to the Grant Agreement

  2. Article 55 MGA WHAT ? An amendment to the grant agreement is necessary to change the terms and conditions of a GA (only specific data, options), Annexes 1 and 2 Consequences The amended provisions become an integral part of the GA All other provisions remain unchanged and have full effect

  3. Conditions Amendments may not result in changes that if known before awarding the grant would have had an impact on the decision to award it Those are mostly changes that: may have had an impact on the assessment of the applicant with regard to the eligibility and selection criteria breach the principle of equal treatment of applicants involve changes in the action and/or budget which may have affected the assessment with regard to the award criteria established in the call do not comply with the Rules for Participation, Financial Regulationor provisions of the GA

  4. WHEN ? Requests must be submitted: * before the end of the action Exception: special cases where it is necessary to change: - coordinator - bank account to make the payment of the balance * sufficiently in advance to allow preparation and proper analysis before the changes are due to take effect Requests must be unambiguous and complete

  5. WHO ? Requested by the parties Commission/Agency Consortium Example:to correct an error made in a GA Coordinator - submits/signs/receives amendments on behalf of beneficiaries Exception: if change of coordinator without its agreement request must be submitted by another beneficiary on behalf of the others Coordinator - must ensure internally the agreement of the consortium based on internal decision-making processes set out in the consortium agreement (e.g. unanimity, simple or qualified majority)

  6. HOW? NEW are PAPERLESS Amendments H2020 Prepared electronically Requesting party encodes the request in the Funding & Tenders Portal * Indicate reasons * Upload supporting documents * Get validations done before submitting the request (e.g. new legal entity, bank account validations) Submitted & signed electronically (by PLSIGN) Counter signed electronically by receiving party (by PLSIGN)

  7. Cases where an amendment is necessary AMENDMENTS (some examples)

  8. I. Beneficiaries - changes beneficiaries Termination of participation triggered by: Commission/Agency Termination by Commission/Agency Termination by Commission/Agency (Article 50.3) 'Contradictory procedure' (30 days) 'Termination date' either: - - date specified in notification confirming termination, or - - day after coordinator or beneficiary concerned receives the notification Coordinator must submit within 60 days after termination an amendment request with supporting documents !

  9. I. Beneficiaries - changes Termination Termination by by the the beneficiaries beneficiaries (Article 50.2) The coordinator: notifies termination to Commission/Agency submits the amendment request at the same time - NEW * Request must include opinion of the beneficiary whose participation is terminated, or proof that it has been requested in writing * Termination date must be after notification Consequences: Termination date is added to the Preamble of the GA - NEW Change of Annexes 1 & 2 If termination is since the beginningthe applicable options will be removed/changed/become not applicable

  10. I. Beneficiaries - changes Adding a new beneficiary Before submission: New beneficiary must be validated & have a PIC Required documents must be signed: - GPF with Declaration of Honour - Annex 3 - Accession Form - Annex 3a, Annex 3b (if applicable) Consequences: New beneficiary and accession date are added to Preamble GA Change of Annexes 1 & 2 GA options for that beneficiary will be added/changed/become applicable (e.g. linked third party, IO)

  11. I. Beneficiaries - changes Change of beneficiary due to "partial takeover" (FP7: partial transfer of rights and obligations ) Partial takeover means that some assets of the beneficiary have been taken over by another entity (e.g. partial acquisition) It must be clarified: * Contractual position of former and new beneficiary (vis- -vis Commission/Agency and the other beneficiaries) * Financial liability of the new beneficiary for the former beneficiary's debts towards the Commission/Agency or the Guarantee Fund

  12. III. Action or action implementation - changes Change to Annex 1 - Description of the action Significant change of action tasks(e.g. if tasks are added/removed) or their division among the beneficiaries Changes concerning subcontracts or in-kind contributions provided by third parties (against payment or free-of-charge) Changes concerning linked third parties, tasks to be carried out and budget Changes to the options in the GA (e.g. options removed or added) Example: adding the options to provide trans-national access to research infrastructure requires normally a change of Annex 1 &/or Annex 2

  13. IV. Financial aspects - changes Change to Annex 2 - Estimated budget Budget transfers: between beneficiaries or budget categories (or both) due to a significant change of Annex 1 to a form of costs that is not used by the beneficiary Except for transfers: within the personnel costs, and to costs of internally invoiced goods and services Example: access costs for transnational access to research infrastructure Change of Annex 2a Additional information on the estimated budget If calculation of unit costs needs to be provided or updated

  14. Cases where an amendment is not necessary AMENDMENTS

  15. Cases where NO amendment is needed: Certain budget transfers Budget transfers and re-allocation Amendment needed? From one beneficiary to another NO From one budget category to another NO Re-allocation of Annex 1 tasks YES YES if the 'form' receiving the transfer was not included in the budget (a new unit cost under column F) Transfers between forms of costs (actual costs, unit costs, etc.) Transfers within personnel costs NO NEW ! (2017) Transfers to costs of internally invoiced goods and services NO New subcontracts YES (strongly advised)

  16. Other cases where no amendment is needed: Change of name/address of beneficiaries & linked third party Change of beneficiary due to universal takeover (In FP7: universal transfer of rights and obligations ) Changes to name of the bank/address of branch/ name of account holder (validation of this data on the FP by the Commission is sufficient) PROCEDURE PROCEDURE to change this information to change this information

  17. How is this information updated? Beneficiaries must keep information stored in the Beneficiary Register up to date via the Funding & Tenders Portal (Article 17.2) The LEAR of the beneficiary updates this information Beneficiaries have to inform as well the coordinator (offline) Validation Services validate the information in the IT system The validated changes will be notified via the Portal Note: If Commission/Agency considers change affects the action implementation, it will inform the coordinator Example: beneficiary changes its legal address to a third country

  18. Amendment Procedure NEW After submission of request receiving party has 45 days for evaluation and validation Agreement Rejection Request for additional information Extension of the deadline for assessment If no reaction within deadline, tacit rejection

  19. Amendment procedure A request containing several changes to the GA will be considered as a package cannot be divided into several requests - request will be agreed or rejected as a whole - An amendment request cannot be changed A request can be withdrawn at any moment before signature There is no tacit approval of amendments

  20. Entry into force and taking effect An amendment enters into force and is binding from the moment both parties sign it (in the electronic exchange system) An amendment takes effect (the changes will start to apply): when the amendment enters into force, or on the date agreed by the parties * This date should normally be after the entry into force * If an amendment request involves several changes, they could take effect on different dates.Example: change of Annex 1 & change of bank account * Depending on the type of change, the date of taking effect may have an impact on the eligibility of costs. Example: addition of new beneficiary

  21. ADDITIONAL INFO: Funding & Tender opportunities Portal https://ec.europa.eu/info/funding-tenders/opportunities/portal/screen/programmes/h2020 H2020 Annotated Model Grant Agreement (AGA) (Article 55) htt://ec.europa.eu/research/participants/data/ref/h2020/grants_manual/amga/h2020-amga_en.pdf Guidance: 'Amendment types & supporting documents' http://ec.europa.eu/research/participants/data/ref/h2020/other/gm/h2020-guide-amend-types_en.pdf Horizon 2020 On-line Manual http://ec.europa.eu/research/participants/docs/h2020-funding-guide/grants/applying-for- funding/register-an-organisation_en.htm

  22. HORIZON 2020 Thank you very much for your attention!