Booster RF 20Hz Testing & Results Summary

undefined
Booster RF 20Hz
Testing & Results
Victor Grzelak
October 24
th
, 2019
Fermi AD/RF
1
Overview
2
Booster 20Hz Thermal Scans and Testing
The Good
Bias power supplies capable of running 20Hz
Cavities capable of running 20Hz
The Bad
Power distribution is underrated for such a load
Bus bars potentially get hot -additional concern
at double penetrations
Further investigation required
Test configuration
3
Booster 20Hz Thermal Scans and Testing
Used existing infrastructure to test the 20Hz in
the tunnel
True viability check
Able to compare 20Hz to 15Hz on multiple cavities
Used new APG,CIG,BIAS, and Frequency curves
Used APG/CIG from c473 card
Used alternate LLRF VME “LLRF2” with 50mS limits
Used $BA 20Hz line locked signal for triggering
LLRF Curve Setup
4
Booster 20Hz Thermal Scans and Testing
Frequency curve start at 44.7MHz
Frequency curve derived from momentum curve
calculated using injection and extraction energies
of 800MeV and 8GeV respectively
Bias curve range between 500-2400Amps
Curve created from frequency curve.
Thanks C. Bhat & C.Y Tan for calculations
Bias Supply Tests
5
Booster 20Hz Thermal Scans and Testing
We began triggering 20Hz curves off the $17
event then switched to triggering all curves off
the $BA
We established RF on station 7 as a litmus test
that the curve was adequate for the frequency
ramp
After minor bias curve tuning we were able to lock
in using the phase detector feedback loop
We turned off the RF and began taking thermal
and power measurements of the bias supply
distribution system
We turned on all the east gallery bias supplies
Bias Supplies
6
Booster 20Hz Thermal Scans and Testing
Fast slewing, precision, shunt regulated power
supply
-15V to 35V output rails
200,000A/s on increasing side
Concern is on down ramp regulation
After tuning this was no longer an issue.
Supplies are power inefficient but highly reliable
Bias supply out of regulation
7
Booster 20Hz Thermal Scans and Testing
 
Bias supply in regulation
8
Booster 20Hz Thermal Scans and Testing
 
Bias supply voltage and current
9
Booster 20Hz Thermal Scans and Testing
Bias supply power results
10
Booster 20Hz Thermal Scans and Testing
Yard Transformer
rated at 1.2MVA
Distribution Breaker
set at 1600Amps,
read 1650Amps
West Gallery has
additional 92kVA
due to modulators
Not acceptable
for prolonged use
Bus Bar Temperatures
11
Booster 20Hz Thermal Scans and Testing
15Hz  average
current is
1100amps
20Hz average
current is
1600amps
Free space
temperature
rise of 20C
expected
IR Thermal Monitoring BRF01,2,3,4
12
Booster 20Hz Thermal Scans and Testing
IR Thermal Monitoring BRF19,20
13
Booster 20Hz Thermal Scans and Testing
Polybeads melt at 120C
(248F)
No bus bars in tunnel
exceeded 160F
Short term heating
measurements ~3Hours
On contact
thermometry was lower
in mostly all cases
Hottest temperature of
concern is inside
penetrations
Remote Thermal Monitoring
14
Booster 20Hz Thermal Scans and Testing
Bus bar temperatures
B:RFxxPB
  
Penetration temperature
Station 12 is having additional thermometry
added
Cavity Temperatures
B:TxxBKS
  
Back Tuner Stem
B:TxxBTS
  
Bottom Tuner Stem
B:TxxFRS
  
Front Tuner Stem
B:TxxCC
  
Center Casting
Bus bar temperatures
15
Booster 20Hz Thermal Scans and Testing
 
Left -15Hz over 3 days
Right - 20 Hz(yellow) vs 15Hz Red over first 8 hours
Need more data over multiple days
RF Tests
16
Booster 20Hz Thermal Scans and Testing
We ran station 12 and 22 at 20 Hz with RF
We added thermometry in the penetrations
12 is a legacy station with a bus bar 4x1/4”
22 is a long run station that has 5x3/8” bus bars
21 & 22 share a penetration
We ran with various modulator voltages
22.5kV current operation
24.0kV PIP2 operations
Monitored internal cavity temperatures using
ACNET and point contact thermometry
Cavity Layout
17
Booster 20Hz Thermal Scans and Testing
Measurement Locations
18
Booster 20Hz Thermal Scans and Testing
Internal measurements taken at 6 places internal
to cavity
RF Tests
19
Booster 20Hz Thermal Scans and Testing
BC-1017 compared to test cave data
Temperature Data
20
Booster 20Hz Thermal Scans
Analysis
21
Booster 20Hz Thermal Scans and Testing
Cavities temperatures were acceptable.
Measurement techniques were not as swift as
cave thus reflecting lower values
Bias supplies regulated acceptably
Reliability of bias supplies running at 20Hz is
unknown, but should be okay
Bus bar temperature increase data insufficient
Scheduled additional test will clarify
Bias supply yard power insufficient
East is at 100% rating
West needs to have modulators removed from
pulsed feeder, then it too would be at 100%
Possible Remedies -Cavity
22
Booster 20Hz Thermal Scans and Testing
Increase cavity intrinsic frequency to reduce
cycle current and power
Intrinsic frequency of Booster cavity is 26MHz
PIP2 operation is 44.7MHz moving baseline
frequency closer to 40MHz could allow for a
greater decrease in operating power.
Wide aperture cavity can be a test bed for this
proposition
There are tradeoffs with tuner reconfigurations
Possible Remedies- WA Cavity
23
Booster 20Hz Thermal Scans and Testing
Wide aperture cavity current configuration has
an intrinsic frequency of 28MHz, which is too low
Possible Remedies- WA Cavity
24
Booster 20Hz Thermal Scans and Testing
Variety of new tuner configurations available
Standard cavities are 9 low-mu and 5 high mu
per side
Wide aperture is 12 low mu and 2 blanks per
side
Tuner reconfigurations 
are a bit of black magic
need to be studied and simulated
Possible Remedies- Bias Supplies
25
Booster 20Hz Thermal Scans and Testing
Design of a new power supply would be very
costly
R&D cost estimate greater than $1M
Sequential supplies $200k each
Bias supplies currently are highly reliable, but
power inefficiency improvements may pay for
itself in a number of years
Average current  could go down on bus bars
~1000Amps average is required for program
current supplies require 1602Amps
Writing a specification and getting an industry
quote
Possible Remedies- Bus Bars
26
Booster 20Hz Thermal Scans and Testing
After multiple day data, this problem can be
effectively analyzed
Increasing bus bar size would be very difficult
and expensive but would address ampacity
limitations
Water cooling may be a necessary option for
hot bus bars
High temp polybeads could replace the current
beads and the thermal dissipation just
monitored using RTDs
Possible Remedies- Power Upgrade
27
Booster 20Hz Thermal Scans and Testing
Increasing each yards pulsed power
transformer to 1.5MVA would be sufficient for
PIP2 operations
Cost estimate – $212k per yard
Transformer – $100k
Switchgear – $80k
Electricians (3days) - $12k
Crane - 20k
If the pad isn’t big enough civil infrastructure
cost would be significant
Using an oil transformer may be necessary
Plan of Action
28
Booster 20Hz Thermal Scans and Testing
Develop a specification for the bias supplies
and get a quote from industry
Investigate high temp polybeads radiation
shielding effects
Immediately plan to remove modulators from
west galleries
Try to find unloaded/underloaded transformer
for an alternative 480 for 1 bias supply in each
gallery
See if manufacter approved modificaitons to
present transformer could allow for it to run at
110% of rating
Conclusions
29
Booster 20Hz Thermal Scans and Testing
The 20Hz tests were a successful fact finding
mission
Cavities are sufficient
Bias supplies are sufficient
Power distribution is insufficient
Bus bar temperatures need further investigation
Acknowledgements
30
Booster 20Hz Thermal Scans and Testing
Thanks for listening
John R, Bob, Matt, Daren, Jeneen, Efrain, for
helping with the execution of this plan
Brian Schupach and Craig Drennan for helping
configure the LLRF for this test
Chandra Bhat for calculating Momentum, APG,
and Frequency curves
Kent Triplett, Jeff Larson and Salah Chaurize for
installing and monitor the additional
thermometry
Gregg Vogel for creating the line locked 20Hz
$BA event used in these tests.
Mike Kucera for setting up the IRMs to function
in 20Hz mode, along with other timers
Slide Note
Embed
Share

The Booster RF 20Hz Testing & Results conducted on October 24th, 2019 involved thermal scans and testing of power supplies and cavities for running at 20Hz. The testing highlighted concerns with power distribution and the potential for bus bars to get hot under load, requiring further investigation. The test configuration utilized existing infrastructure for true viability checks and comparisons between 20Hz and 15Hz on multiple cavities. The setup included new equipment for APG, CIG, BIAS, and frequency curves, with detailed LLRF curve setups and bias supply tests. The results indicated the need for minor tuning adjustments to ensure adequate performance.

  • Booster RF
  • Testing Results
  • Thermal Scans
  • Power Supplies
  • Cavities

Uploaded on Sep 28, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. October 24th, 2019 Booster RF 20Hz Testing & Results Victor Grzelak 1 Fermi AD/RF

  2. Booster 20Hz Thermal Scans and Testing 2 Overview The Good Bias power supplies capable of running 20Hz Cavities capable of running 20Hz The Bad Power distribution is underrated for such a load Bus bars potentially get hot -additional concern at double penetrations Further investigation required

  3. Booster 20Hz Thermal Scans and Testing 3 Test configuration Used existing infrastructure to test the 20Hz in the tunnel True viability check Able to compare 20Hz to 15Hz on multiple cavities Used new APG,CIG,BIAS, and Frequency curves Used APG/CIG from c473 card Used alternate LLRF VME LLRF2 with 50mS limits Used $BA 20Hz line locked signal for triggering

  4. Booster 20Hz Thermal Scans and Testing 4 LLRF Curve Setup Frequency curve start at 44.7MHz Frequency curve derived from momentum curve calculated using injection and extraction energies of 800MeV and 8GeV respectively Bias curve range between 500-2400Amps Curve created from frequency curve. Thanks C. Bhat & C.Y Tan for calculations

  5. Booster 20Hz Thermal Scans and Testing 5 Bias Supply Tests We began triggering 20Hz curves off the $17 event then switched to triggering all curves off the $BA We established RF on station 7 as a litmus test that the curve was adequate for the frequency ramp After minor bias curve tuning we were able to lock in using the phase detector feedback loop We turned off the RF and began taking thermal and power measurements of the bias supply distribution system We turned on all the east gallery bias supplies

  6. Booster 20Hz Thermal Scans and Testing 6 Bias Supplies Fast slewing, precision, shunt regulated power supply -15V to 35V output rails 200,000A/s on increasing side Concern is on down ramp regulation After tuning this was no longer an issue. Supplies are power inefficient but highly reliable

  7. Booster 20Hz Thermal Scans and Testing 7 Bias supply out of regulation

  8. Booster 20Hz Thermal Scans and Testing 8 Bias supply in regulation

  9. Booster 20Hz Thermal Scans and Testing 9 Bias supply voltage and current

  10. Booster 20Hz Thermal Scans and Testing 10 Bias supply power results Yard Transformer rated at 1.2MVA Distribution Breaker set at 1600Amps, read 1650Amps West Gallery has additional 92kVA due to modulators Not acceptable for prolonged use Power Per station Real (kW) Reactive(KVAR) Apparent (kVA) 15Hz 27.7 104.9 108.6 20Hz 33.7 119.9 124.6 Delta 6 15 16 Percent 21.66% 14.30% 14.73% Power with 10 stations Real (kW) Reactive(KVAR) Apparent (kVA) 15Hz 277 1049 1086 20Hz 337 1199 1246 60 150 160 21.66% 14.30% 14.73% Current Current A Current B Current C 1376 1344 1404 1379 1589 1635 1604 1525 213 291 200 146 15.48% 21.65% 14.25% 10.59% Voltage Voltage A-N Voltage B-N Voltage C-N 454 263 262 263 453 261 261 263 -1 -2 -1 0 -0.22% -0.76% -0.38% 0.00%

  11. Booster 20Hz Thermal Scans and Testing 11 Bus Bar Temperatures 15Hz average current is 1100amps 20Hz average current is 1600amps Free space temperature rise of 20C expected

  12. Booster 20Hz Thermal Scans and Testing 12 IR Thermal Monitoring BRF01,2,3,4

  13. Booster 20Hz Thermal Scans and Testing 13 IR Thermal Monitoring BRF19,20 Polybeads melt at 120C (248F) No bus bars in tunnel exceeded 160F Short term heating measurements ~3Hours On contact thermometry was lower in mostly all cases Hottest temperature of concern is inside penetrations

  14. Booster 20Hz Thermal Scans and Testing 14 Remote Thermal Monitoring Bus bar temperatures B:RFxxPB Station 12 is having additional thermometry added Penetration temperature Cavity Temperatures B:TxxBKS B:TxxBTS B:TxxFRS B:TxxCC Back Tuner Stem Bottom Tuner Stem Front Tuner Stem Center Casting

  15. Booster 20Hz Thermal Scans and Testing 15 Bus bar temperatures Left -15Hz over 3 days Right - 20 Hz(yellow) vs 15Hz Red over first 8 hours Need more data over multiple days

  16. Booster 20Hz Thermal Scans and Testing 16 RF Tests We ran station 12 and 22 at 20 Hz with RF We added thermometry in the penetrations 12 is a legacy station with a bus bar 4x1/4 22 is a long run station that has 5x3/8 bus bars 21 & 22 share a penetration We ran with various modulator voltages 22.5kV current operation 24.0kV PIP2 operations Monitored internal cavity temperatures using ACNET and point contact thermometry

  17. Booster 20Hz Thermal Scans and Testing 17 Cavity Layout

  18. Booster 20Hz Thermal Scans and Testing 18 Measurement Locations Internal measurements taken at 6 places internal to cavity

  19. Booster 20Hz Thermal Scans and Testing 19 RF Tests BC-1017 compared to test cave data 22.5kV 15Hz 46.87 48.72 48.05 42.7 24kV 15Hz 49.6 52.4 46.5 57.5 Parameter (Degree C) Front tuner Thermistor Back Tuner Thermistor Bottom Tuner Thermistor Center casting Thermistor 20Hz 45.35 42.34 45.21 45.4 20Hz 46.67 43.39 46.57 46.74 1.52 6.38 2.84 -2.7 Front tuner Thermistor Back Tuner Thermistor Bottom Tuner Thermistor Center casting Thermistor 2.93 9.01 -0.07 10.76 DVM (Degree F) Back Tuner Front Tuner Bottom Tuner DS Beam Tube DS SS collar DS Ceramic US Beam Tube US SS collar US Ceramic DVM (Degree F) Back Tuner Front Tuner Bottom Tuner DS Beam Tube DS SS collar DS Ceramic US Beam Tube US SS collar US Ceramic 114 113.1 112.5 145.8 148.9 142.5 147.5 146.7 139 114 3.8 5.5 13 12.1 27.8 6.5 4.7 15 123 122 111.3 145.5 149 145.6 157 159 156.6 109.3 107 132.8 136.8 114.7 141 142 124 102.8 102 144 148.2 136.1 137 141.5 137 19.2 9.3 1.5 0.8 9.5 20 17.5 19.6

  20. Booster 20Hz Thermal Scans 20 Temperature Data 170 160 150 140 130 Degrees (F) 120 110 100 90 80 Front tuner Thermistor Back Tuner Thermistor Bottom Tuner Thermistor Center casting Thermistor Back Tuner Front Tuner Bottom Tuner DS Beam Tube DS SS collarDS Ceramic US Beam US SS collarUS Ceramic Tube 15Hz-22.5kV 20Hz-22.5kV 15Hz-24kV 20Hz-24kV

  21. Booster 20Hz Thermal Scans and Testing 21 Analysis Cavities temperatures were acceptable. Measurement techniques were not as swift as cave thus reflecting lower values Bias supplies regulated acceptably Reliability of bias supplies running at 20Hz is unknown, but should be okay Bus bar temperature increase data insufficient Scheduled additional test will clarify Bias supply yard power insufficient East is at 100% rating West needs to have modulators removed from pulsed feeder, then it too would be at 100%

  22. Booster 20Hz Thermal Scans and Testing 22 Possible Remedies -Cavity Increase cavity intrinsic frequency to reduce cycle current and power Intrinsic frequency of Booster cavity is 26MHz PIP2 operation is 44.7MHz moving baseline frequency closer to 40MHz could allow for a greater decrease in operating power. Wide aperture cavity can be a test bed for this proposition There are tradeoffs with tuner reconfigurations

  23. Booster 20Hz Thermal Scans and Testing 23 Possible Remedies- WA Cavity Wide aperture cavity current configuration has an intrinsic frequency of 28MHz, which is too low BC-3001 v BC-1017 53 52 51 50 49 48 Frequency MHz 47 46 45 44 43 42 41 40 39 38 37 36 0 500 1000 1500 2000 2500 Bias Current Amps 3001 1017

  24. Booster 20Hz Thermal Scans and Testing 24 Possible Remedies- WA Cavity Variety of new tuner configurations available Standard cavities are 9 low-mu and 5 high mu per side Wide aperture is 12 low mu and 2 blanks per side Tuner reconfigurations are a bit of black magic need to be studied and simulated

  25. Booster 20Hz Thermal Scans and Testing 25 Possible Remedies- Bias Supplies Design of a new power supply would be very costly R&D cost estimate greater than $1M Sequential supplies $200k each Bias supplies currently are highly reliable, but power inefficiency improvements may pay for itself in a number of years Average current could go down on bus bars ~1000Amps average is required for program current supplies require 1602Amps Writing a specification and getting an industry quote

  26. Booster 20Hz Thermal Scans and Testing 26 Possible Remedies- Bus Bars After multiple day data, this problem can be effectively analyzed Increasing bus bar size would be very difficult and expensive but would address ampacity limitations Water cooling may be a necessary option for hot bus bars High temp polybeads could replace the current beads and the thermal dissipation just monitored using RTDs

  27. Booster 20Hz Thermal Scans and Testing 27 Possible Remedies- Power Upgrade Increasing each yards pulsed power transformer to 1.5MVA would be sufficient for PIP2 operations Cost estimate $212k per yard Transformer $100k Switchgear $80k Electricians (3days) - $12k Crane - 20k If the pad isn t big enough civil infrastructure cost would be significant Using an oil transformer may be necessary

  28. Booster 20Hz Thermal Scans and Testing 28 Plan of Action Develop a specification for the bias supplies and get a quote from industry Investigate high temp polybeads radiation shielding effects Immediately plan to remove modulators from west galleries Try to find unloaded/underloaded transformer for an alternative 480 for 1 bias supply in each gallery See if manufacter approved modificaitons to present transformer could allow for it to run at 110% of rating

  29. Booster 20Hz Thermal Scans and Testing 29 Conclusions The 20Hz tests were a successful fact finding mission Cavities are sufficient Bias supplies are sufficient Power distribution is insufficient Bus bar temperatures need further investigation

  30. Booster 20Hz Thermal Scans and Testing 30 Acknowledgements Thanks for listening John R, Bob, Matt, Daren, Jeneen, Efrain, for helping with the execution of this plan Brian Schupach and Craig Drennan for helping configure the LLRF for this test Chandra Bhat for calculating Momentum, APG, and Frequency curves Kent Triplett, Jeff Larson and Salah Chaurize for installing and monitor the additional thermometry Gregg Vogel for creating the line locked 20Hz $BA event used in these tests. Mike Kucera for setting up the IRMs to function in 20Hz mode, along with other timers

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#