Advanced Hardware Installation Project Overview

Slide Note
Embed
Share

Explore the progress of the hardware installation project, including frames, readout plates, calibration system, and installation details. Follow the development of feedthroughs, cooling systems, cabling, and mounting solutions as the project nears completion.


Uploaded on Oct 01, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Hardware Hubert van Hecke Sanghoon Lim Alex Wickes Shaun Newman

  2. Frames 4 frames for 1x1x80 cm bars 4 frames for 2x2x100 cm bars Mostly finished To be done: Feedthroughs and/or patch panels for cables Cooling air feedthroughs

  3. Readout plates Fibers and preamps in the front SiPMs connect with pigtails in the back Fabrication bids are out front back Full-scale mockup for cable routing and connector finger space

  4. Calibration system Use existing pulser board design from Pat 1mm plastic fiber output Fan out to 7 (19) clear 1mm fibers Insert these into each scintillator bar To be done: Lay out pulser board with n pulsers, and build Cut and polish pulser fibers Design mounting 3D print 1->7 fanout

  5. Installation 4 boxes joined 2 vertical beams hold this assembly Anchored to floor and overhead beams To be done: Details of mounting points Safety review Determine external cable routing Cooling fans

Related


More Related Content