Federal Energy Regulatory Commission Transmission Update - Nov. 3, 2023

 
Federal Energy Regulatory Commission
Transmission Update
 
Rob Thormeyer, Director
State, International, and Tribal Affairs Division
 
Nov. 3, 2023
 
DISCLAIMER
: Speaking on my own behalf and
my comments do not necessarily reflect the
views of the Commission, individual
Commissioners, or other Commission staff
members
 
About FERC
 
3
 
FERC regulates natural gas wholesale facilities
Considers applications to build interstate pipelines, onshore LNG facilities
and underground storage facilities that are tied to the wholesale market
Regulates the rates/tariffs of pipelines on a contract basis
FERC regulates the wholesale electric market
Sets rates/tariffs for wholesale transactions on interstate lines (100 KV and
higher)
Siting for transmission lines is primarily done at the state level
Backstop siting proposed rule and IIJA
FERC oversees NERC reliability standards, including cybersecurity
FERC provides licenses for non-federal hydro facilities (about half of
all hydro in the U.S.)
 
About FERC, cont.
 
Five Commissioners, appointed by the President, confirmed by the
Senate for staggered five-year terms
Chairman Willie Phillips (D)
Commissioner James Danly (R)
Commissioner Allison Clements (D)
Commissioner Mark Christie (R)
Vacancy
 
4
 
5
 
Upcoming Events
 
#ReliabilityWeek!
Nov. 9 Reliability Technical Conference
Winter Storm Elliott Final Report
Coming soon!
 
2024 Open Commission Meetings
Nov. 16
Agenda published on Nov. 9
Dec. 19
 
6
 
Priority Transmission Items
 
Interconnection Queue Reform
Finalized in July 2023
Published in Federal Register, Sept. 6, 2023
Compliance Filings Due: April 3, 2024
Backstop Transmission Siting Proposed Rulemaking
Still in rulemaking process
Long-Term Transmission Planning Proposed
Rulemaking
Still in rulemaking process
 
Slide 7
 
Finalized July 27, 2023; Published in Federal Register Sept. 6, 2023
Requires all utilities to adopt generator interconnection procedures
& agreements to enable interconnection customers (generators) to
connect their project to the grid i
n a reliable, efficient, transparent,
and timely manner, and to prevent undue discrimination
 
Huge order—literally and figuratively: approximately 1480 pages!
 
Improvements to Generator Interconnection
Procedures and Agreements (Order 2023)
 
Slide 8
 
Cluster Study Process
Streamlines process by requiring transmission providers (utilities, RTOs) to conduct larger
studies consisting of numerous generating facilities, rather than separate studies for each
facility—instead of first-come, first served it is now first ready, first served
 
Speed Up Interconnection Queue Processing
Requires firm deadlines and establishes penalties if transmission providers do not
complete interconnection studies on time
 
Incorporate Technological Advancements into the Interconnection Process
Permits flexibility for generators by allowing more than one generating facility  to co-locate
on a shared site behind a single interconnection point and requiring realistic operating
assumptions for storage resources
Requires consideration of alternative transmission technologies
 
Improvements to Generator Interconnection
Procedures and Agreements (Order 2023)
 
Slide 9
 
Next Steps
Rehearing Requests filed, currently under consideration
Commission Action, TBD
Publication of Order 2023 in Federal Register, Sept. 6
, 2023
Transmission Provider compliance filings due, April 3, 2024
 
Improvements to Generator Interconnection
Procedures and Agreements (Order 2023)
 
Slide 10
 
Issued Dec. 15, 2022, Docket No. RM22-7-000 (181 FERC ¶ 61,205), in
response to Infrastructure Investment and Jobs Act of 2021
Proposes to revise the Commission’s regulations governing
applications for permits to site electric transmission facilities under
section 216 of the Federal Power Act (FPA)
For a transmission project to be subject to this authority, it must be so
designated by the Department of Energy
After DOE designation, backstop authority “triggered” if a state has either: not acted
on a transmission siting application for a transmission project more than one year
after filing or outright denied an application
 
Backstop Transmission Siting
Proposal
 
Slide 11
 
Issued April 21, 2022, Docket No. RM21-17-000
Transmission Providers Would Be Required to:
Conduct regional transmission planning on a sufficiently long-term, forward looking basis
Identify grid needs through long-term scenarios incorporating minimum set of factors,
including federal, state, local laws & regulations impacting the future resource mix
Seek agreement of relevant state entities in transmission planning region regarding cost-
allocation for facilities selected as part of long-term regional planning
Establish a cost allocation method for transmission facilities selected as part of long-term
regional grid planning that is ex ante cost-allocation method or state-agreement process
Would amend Order 1000 Right of First Refusal requirements to allow
transmission providers’ federal rights for transmission facilities selected
through a regional plan for cost-allocation purposes, provided that incumbent
transmission provider establishes joint ownership
 
 
Long-Term Grid Planning Proposal
 
12
12
 
About the Office of External Affairs
 
FERC’s primary contact point with Congress, the States, Tribal
governments, International governments, the public, and the
media
 
Three divisions
Congressional Affairs
Media Relations
State, International, Tribal Affairs (SITA)
SITA
Responsible for communicating Commission activities/decisions/events to state,
local, Tribal, and international governments
Briefings, emails, conferences, meetings assistance
 
13
13
 
Office of Public Participation
 
Email: 
OPP@ferc.gov
Phone: (202) 502-6595
www.ferc.gov/OPP
 
Work
shOPPs
Inte
rvention in FERC proceedings
Natural Gas Pre-Filing Review Process
Tips for Powerful Comments
Technical Assistance
Explainers/Educational Resources
Order 2023/Interconnection
Energy  Markets
Energy Projects
 
14
14
 
Questions?
 
Rob Thormeyer
Director, State, International, and Tribal
Affairs Division
Federal Energy Regulatory Commission
Robert.Thormeyer@ferc.gov
202-502-8694 (office)
202-
465-5717 (ce
ll)
Slide Note

Thank you—glad to be here

Thanks to David/Chris Ayers for the invitation… and it is an honor to here

I will provide a brief overview of FERC itself, then highlight a few priority issues, before providing a brief look at my division within the Office of External Affairs, the State, International and Tribal Affairs Division;. I’ll mention at the very beginning that I am in external affairs—which means I am not a subject matter expert. Thankfully I work with a ton of much smarter people than me who can answer your detailed questions about policies etc.

Embed
Share

FERC, led by Director Rob Thormeyer, regulates natural gas wholesale facilities, interstate pipelines, onshore LNG facilities, wholesale electric market rates, and more. The Commission consists of five appointed Commissioners overseeing key initiatives like transmission planning proposals and interconnection queue reforms. Upcoming events include ReliabilityWeek! and open Commission meetings. Priority transmission items such as interconnection queue reform and backstop transmission siting proposed rulemaking are in progress, reflecting FERC's commitment to reliability and oversight in the energy sector.


Uploaded on Jul 02, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Federal Energy Regulatory Commission Transmission Update Rob Thormeyer, Director State, International, and Tribal Affairs Division Nov. 3, 2023

  2. DISCLAIMER: Speaking on my own behalf and my comments do not necessarily reflect the views of the Commission, individual Commissioners, or other Commission staff members

  3. About FERC FERC regulates natural gas wholesale facilities Considers applications to build interstate pipelines, onshore LNG facilities and underground storage facilities that are tied to the wholesale market Regulates the rates/tariffs of pipelines on a contract basis FERC regulates the wholesale electric market Sets rates/tariffs for wholesale transactions on interstate lines (100 KV and higher) Siting for transmission lines is primarily done at the state level Backstop siting proposed rule and IIJA FERC oversees NERC reliability standards, including cybersecurity FERC provides licenses for non-federal hydro facilities (about half of all hydro in the U.S.) 3

  4. About FERC, cont. Five Commissioners, appointed by the President, confirmed by the Senate for staggered five-year terms Chairman Willie Phillips (D) Commissioner James Danly (R) Commissioner Allison Clements (D) Commissioner Mark Christie (R) Vacancy 4

  5. Upcoming Events #ReliabilityWeek! Nov. 9 Reliability Technical Conference Winter Storm Elliott Final Report Coming soon! 2024 Open Commission Meetings Nov. 16 Agenda published on Nov. 9 Dec. 19 5

  6. Priority Transmission Items Interconnection Queue Reform Finalized in July 2023 Published in Federal Register, Sept. 6, 2023 Compliance Filings Due: April 3, 2024 Backstop Transmission Siting Proposed Rulemaking Still in rulemaking process Long-Term Transmission Planning Proposed Rulemaking Still in rulemaking process 6

  7. Improvements to Generator Interconnection Procedures and Agreements (Order 2023) Finalized July 27, 2023; Published in Federal Register Sept. 6, 2023 Requires all utilities to adopt generator interconnection procedures & agreements to enable interconnection customers (generators) to connect their project to the grid in a reliable, efficient, transparent, and timely manner, and to prevent undue discrimination Huge order literally and figuratively: approximately 1480 pages! Slide 7

  8. Improvements to Generator Interconnection Procedures and Agreements (Order 2023) Cluster Study Process Streamlines process by requiring transmission providers (utilities, RTOs) to conduct larger studies consisting of numerous generating facilities, rather than separate studies for each facility instead of first-come, first served it is now first ready, first served Speed Up Interconnection Queue Processing Requires firm deadlines and establishes penalties if transmission providers do not complete interconnection studies on time Incorporate Technological Advancements into the Interconnection Process Permits flexibility for generators by allowing more than one generating facility to co-locate on a shared site behind a single interconnection point and requiring realistic operating assumptions for storage resources Requires consideration of alternative transmission technologies Slide 8

  9. Improvements to Generator Interconnection Procedures and Agreements (Order 2023) Next Steps Rehearing Requests filed, currently under consideration Commission Action, TBD Publication of Order 2023 in Federal Register, Sept. 6, 2023 Transmission Provider compliance filings due, April 3, 2024 Slide 9

  10. Backstop Transmission Siting Proposal Issued Dec. 15, 2022, Docket No. RM22-7-000 (181 FERC 61,205), in response to Infrastructure Investment and Jobs Act of 2021 Proposes to revise the Commission s regulations governing applications for permits to site electric transmission facilities under section 216 of the Federal Power Act (FPA) For a transmission project to be subject to this authority, it must be so designated by the Department of Energy After DOE designation, backstop authority triggered if a state has either: not acted on a transmission siting application for a transmission project more than one year after filing or outright denied an application Slide 10

  11. Long-Term Grid Planning Proposal Issued April 21, 2022, Docket No. RM21-17-000 Transmission Providers Would Be Required to: Conduct regional transmission planning on a sufficiently long-term, forward looking basis Identify grid needs through long-term scenarios incorporating minimum set of factors, including federal, state, local laws & regulations impacting the future resource mix Seek agreement of relevant state entities in transmission planning region regarding cost- allocation for facilities selected as part of long-term regional planning Establish a cost allocation method for transmission facilities selected as part of long-term regional grid planning that is ex ante cost-allocation method or state-agreement process Would amend Order 1000 Right of First Refusal requirements to allow transmission providers federal rights for transmission facilities selected through a regional plan for cost-allocation purposes, provided that incumbent transmission provider establishes joint ownership Slide 11

  12. About the Office of External Affairs FERC s primary contact point with Congress, the States, Tribal governments, International governments, the public, and the media Three divisions Congressional Affairs Media Relations State, International, Tribal Affairs (SITA) SITA Responsible for communicating Commission activities/decisions/events to state, local, Tribal, and international governments Briefings, emails, conferences, meetings assistance 12

  13. Office of Public Participation Email: OPP@ferc.gov Phone: (202) 502-6595 www.ferc.gov/OPP WorkshOPPs Intervention in FERC proceedings Natural Gas Pre-Filing Review Process Tips for Powerful Comments Technical Assistance Explainers/Educational Resources Order 2023/Interconnection Energy Markets Energy Projects 13

  14. Questions? Rob Thormeyer Director, State, International, and Tribal Affairs Division Federal Energy Regulatory Commission Robert.Thormeyer@ferc.gov 202-502-8694 (office) 202-465-5717 (cell) 14

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#