Water Planning and Collaboration in Arizona

water planning scarcity and collaboration arizona l.w
1 / 10
Embed
Share

Arizona's water planning involves addressing scarcity through collaboration and agreements such as the DCP. Important aspects include legislative authorization requirements, reduction tiers, priority pools, and the LBDCP implementation plan focusing on mitigation strategies and infrastructure development.

  • Water planning
  • Collaboration
  • Arizona
  • DCP
  • Scarcity

Uploaded on | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. Water Planning: Scarcity and Collaboration Arizona and the DCP Kenneth C. Slowinski Chief Counsel Arizona Department of Water Resources August 13, 2019

  2. Authorization By Arizona Legislature Required for ADWR Director to Sign DCP Agreements A.R.S. 45-106 states: An agreement entered into between the [ADWR] director and the United States or a state or government involving a sovereign right or claim of this state is not effective unless approved by the legislature by concurrent resolution. 2

  3. Reduction Tiers For Arizona Under 2007 Guidelines and DCP 2007 Guidelines (Lake Mead Elevation projection as of January 1) Tier 1 at or below 1075 feet (320k reduction) Tier 2 below 1050 feet (400k reduction) Tier 3 below 1025 feet (480k reduction) 2007 Guidelines and DCP (Lake Mead Elevation projection as of January 1) Tier Zero at or below 1090 feet (192k reduction) Tier 1 at or below 1075 feet (320k + 192k reduction) Tier 2a below 1050 feet (400k + 192k reduction) Tier 2b below 1045 feet (400k + 240k reduction) Tier 3 below 1025 feet (480k + 240k reduction) 3

  4. CAP Priority Pools & Shortage 07 Guidelines + LBDCP 2007 Guidelines 1,600,000 1,600,000 Other Excess Other Excess 1,400,000 1,400,000 T Zero (0 + 192k) Ag Pool Ag Pool T1 (320k) T2 (400k) T3 (480k) 1,000,000 1,200,000 1,200,000 T1(320k + 192k) T2a(400k + 192k) 1,000,000 NIA Priority NIA Priority T2b(400k + 240k) T3(480k + 240k) Acre Feet Acre Feet 800,000 800,000 600,000 600,000 Indian Priority Indian Priority M&I Priority M&I Priority 400,000 400,000 200,000 200,000 Priority 3 Priority 3 0 0 4

  5. Arizona LBDCP Implementation Plan Process ADWR and CAWCD hosted 9 public Steering Committee meetings during 2018 and 2019 to discuss a DCP Implementation Plan. 5

  6. LBDCP Implementation Plan 2 Components Mitigation Component (to mitigate reductions in water) Wet water CAP ICS deliveries for mitigation of reductions Payment for reductions (compensated mitigation) when wet water mitigation is insufficient Money for new groundwater infrastructure for CAP AG Offset Component (to replace water used for mitigation) System conservation water in Lake Mead. ICS creation by GRIC Voluntary ICS creation without compensation Payment by U.S. and State for creation of ICS for pre-firming to meet their obligations under settlement agreements 6

  7. Mitigation Component - Key Terms 2020 2022 100% mitigation for NIA Pool (Cities and Indian Tribes) Fixed volume of CAP water for CAP Ag 2023 2025 No CAP Ag Mitigation (except USF to GSF and groundwater infrastructure) CAP M&I and Indian priority supplies fully mitigated first NIA 75% under T1 and T2a (until no supplies) NIA 50% under T2b (until no supplies) 2026 Zero mitigation No mitigation for any water user in T3 or 2026, whichever occurs first 7

  8. Offset Component Key Terms Conserve 400 kaf to offset use of CAP ICS for mitigation Offsets provided through: 100 kaf of ICS created by GRIC (to be paid by U.S.) Pre-firming for US Tribal firming obligation(s) 50 kaf of ICS created by GRIC (to be paid by AWBA) Pre-firming for Arizona s firming obligation to GRIC 50 kaf Additional ICS by GRIC 150 kaf of System Conservation created by CRIT (approx. $38 million paid by State and EDF) 50 kaf - CAP-SRP Exchange payback 8

  9. Participants in Funding & Water CAWCD: Funding and Water SRP: Water in exchange CAP M&I Users: Water for USF-GSF GRIC: Water for ICS and Firming CAP AG: Funding for GW infrastructure State of Arizona: Funding for GW infrastructure, System Conservation and Firming AWBA: LTSC for USF-GSF exchange, Firming US: Funding of GW Infrastructure and Firming NGOs (EDF): Funding for System Conservation CRIT: Water for System Conservation 9

  10. Drought Contingency Plan Recap Arizona DCP Implementation Plan Legislation January 31 Arizona Legislature passed & Gov. Ducey signed SB 1227 and Senate Joint Resolution 1001 The Resolution authorized ADWR Director to sign the Interstate DCP Agreements on behalf of Arizona 10