Vacuum System Engineering for Beam Transport Challenges

 
Vacuum System for Beam Transport
 
Catalin M. Ticos
National Institute for Lasers, Plasma and Radiation Physics (INFLPR),
077125 Bucharest, Romania
 
Engineering issues related to beam delivery to
target
 
Motivation:
Identify engineering issues related to beam propagation in vacuum
 
Steps:
1. generation of PW laser beam (in compressor)
2. transport of PW laser beam to target
 
Peculiarities:
Max beam diam. 90 cm, large and heavy optics/vacuum compatible
Transport over large distances (~30m) with little distortions
!
 
Large beams are in vacuum
 
Challenge:
Lasers and target areas on 2 
different
concrete floors
.
Both floors are supported by a
number of springs
 
m to mm 
displacement within beam line
mechanical stress
 optical misalignment
 
 
 
Main issues
 
 
Required:
1.
10
-5
 - 10
-6
 torr vacuum in beam pipes/compressors/chambers
2.
Low (or no) vibrations along the beam line and at target chambers
3.
Cooling of pumps (pipes /target chamber as well?)
 
Needed:
Proper vacuum system with integrated remote controls
 
(pumps, gauges, valves, gas containers, filters, exhausts, etc)
Reduce vibrations from mechanical/turbo pumps to pipes/compressor/
chamber
Water/air cooling system for pumps
 
Vibration/stability issues (2)
 
Large weight on floor can cause tilting
To estimate mass we need to identify thickness and type of
material for compressor/target chamber/piping
e.g. Al large target chamber 3 t
Same SS target chamber can have 9 t (
ρ
SS
/
ρ
Al
 =8/2.7)
 
Vacuum solutions
 
For Ø90 cm pipe 
 
every 2 to 5m a turbo+roughing system
Roughing (mechanical): atm. to 10
-2 
torr; turbo: 10
-2 
to 10
-6 
torr
Vacuum line segmented with pneumatically operated gate valves
Cryogenic pumps on compressor and target chambers (~10
4
 l/s)
Backup system on compressor/target chambers based on turbopumps
(repair or regeneration of cryopumps)
 
Vibrations solutions
 
Laser interferometer for measuring the micro-motion
between the 2 floors (laser and experimental areas) & for
alignment of large optics
Large bellows in the beam line
Special stands for roughing pumps (w. damping springs)
Special supports for target chambers (based on polymer
layers)
Cryopumps instead of turbo pumps
 
Other issues
 
Large flanges with windows, also large viewing windows on
compressor/target chamber
Filters on exhausts for containing nuclear debris
Separate vacuum pumps for Target Positioner System, or
instrument manipulator (eg. TIM at LANL)etc
 
Conclusions
 
Prerequisite for a good design is to identify and set the system
parameters
Tight collaboration with laser and civil engineering groups
Learn from the experience of other facilities worldwide
Work closely with companies to deliver the right solution
 
Thank you!
Slide Note
Embed
Share

Addressing engineering issues related to beam delivery in a vacuum environment for the ELI-NP project, focusing on maintaining low vacuum levels, reducing vibrations, cooling pumps, and ensuring stability with large beams. Solutions include segmented vacuum lines, cryogenic pumps, and integrated remote controls for the vacuum system.

  • Vacuum System
  • Beam Transport
  • Engineering Challenges
  • ELI-NP Project
  • Vacuum Solutions

Uploaded on Sep 16, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Vacuum System for Beam Transport Catalin M. Ticos National Institute for Lasers, Plasma and Radiation Physics (INFLPR), 077125 Bucharest, Romania ELI-NP The Way Ahead-Workshop March 10-11, 2011

  2. Engineering issues related to beam delivery to target Motivation: Identify engineering issues related to beam propagation in vacuum Steps: 1. generation of PW laser beam (in compressor) 2. transport of PW laser beam to target Peculiarities: Max beam diam. 90 cm, large and heavy optics/vacuum compatible Transport over large distances (~30m) with little distortions! ELI-NP The Way Ahead-Workshop March 10-11, 2011

  3. Large beams are in vacuum Challenge: Lasers and target areas on 2 different concrete floors. Both floors are supported by a number of springs m to mm displacement within beam line mechanical stress optical misalignment ELI-NP The Way Ahead-Workshop March 10-11, 2011

  4. Main issues Required: 1. 10-5- 10-6torr vacuum in beam pipes/compressors/chambers 2. Low (or no) vibrations along the beam line and at target chambers 3. Cooling of pumps (pipes /target chamber as well?) Needed: Proper vacuum system with integrated remote controls (pumps, gauges, valves, gas containers, filters, exhausts, etc) Reduce vibrations from mechanical/turbo pumps to pipes/compressor/ chamber Water/air cooling system for pumps ELI-NP The Way Ahead-Workshop March 10-11, 2011

  5. Vibration/stability issues (2) Large weight on floor can cause tilting To estimate mass we need to identify thickness and type of material for compressor/target chamber/piping e.g. Al large target chamber 3 t Same SS target chamber can have 9 t ( SS/ Al=8/2.7) ELI-NP The Way Ahead-Workshop March 10-11, 2011

  6. Vacuum solutions For 90 cm pipe every 2 to 5m a turbo+roughing system Roughing (mechanical): atm. to 10-2 torr; turbo: 10-2 to 10-6 torr Vacuum line segmented with pneumatically operated gate valves Cryogenic pumps on compressor and target chambers (~104l/s) Backup system on compressor/target chambers based on turbopumps (repair or regeneration of cryopumps) ELI-NP The Way Ahead-Workshop March 10-11, 2011

  7. Vibrations solutions Laser interferometer for measuring the micro-motion between the 2 floors (laser and experimental areas) & for alignment of large optics Large bellows in the beam line Special stands for roughing pumps (w. damping springs) Special supports for target chambers (based on polymer layers) Cryopumps instead of turbo pumps ELI-NP The Way Ahead-Workshop March 10-11, 2011

  8. Other issues Large flanges with windows, also large viewing windows on compressor/target chamber Filters on exhausts for containing nuclear debris Separate vacuum pumps for Target Positioner System, or instrument manipulator (eg. TIM at LANL)etc ELI-NP The Way Ahead-Workshop March 10-11, 2011

  9. Conclusions Prerequisite for a good design is to identify and set the system parameters Tight collaboration with laser and civil engineering groups Learn from the experience of other facilities worldwide Work closely with companies to deliver the right solution Thank you! ELI-NP The Way Ahead-Workshop March 10-11, 2011

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#