Understanding Demand Side Management in West Bengal
Demand Side Management (DSM) involves modifying consumer electricity demand through methods like financial incentives and consumer education. In West Bengal, utility providers aim to reduce energy usage during peak hours to avoid costly capacity additions. The need for DSM arises from increasing energy requirements, climate change threats, and energy security concerns. By encouraging consumers to shift energy use to off-peak hours, utilities can improve energy efficiency and meet peak demand effectively.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
Demand Side Management: Concept, Need and scenario in West Bengal Saroj Sarkar Engineer (Retd.) WBSEDCL 1
WHAT IS DEMAND SIDE MANAGEMENT? Demand Side Management is the modification of consumer s demand of electricity through various methods such as financial incentives and consumer education Usually the goal of DSM is to encourage the consumers to use less energy during peak hours or to move the time of energy use to the off-peak hours viz. night 2
UNDERSTANDING DEMAND AND SUPPLY Q) Who Demands electricity? A) The consumer Q) Who will manage demand for electricity by the consumers? A) The Service provider with equal participation from the Consumer. 3
Need for DSM Saving 1 unit of electricity at consumer end avoids nearly 2.5 times of capacity addition 1 MW capacity addition of thermal power requires Rs 6 crores for installation and another Rs 3 crores for Transmission and Distribution 4
Need for DSM ..(contd.) Increasing energy requirement Increasing threat of climate change and other environmental considerations Energy security Lack of other supply options Huge scope for energy efficiency measures 5
Peak Demand at 7.30 p.m. Since Full Lighting load, and other Commercial and Domestic loads Demand is huge between 5:30 p.m. and 9:30 p.m. Demand is minimum between 12 a.m. and 6 a.m. Usual Load Curve of an Utility for a 24 Hour period 6
Observations The peak demand of 4,300 MW is there for only 5-6 hours in the evening The base demand is 3,000 MW, which is much less than the peak demand of 4,300 MW To meet the extra demand utility has to arrange additional installed capacity or purchase power at high rate 7
Observations ..(contd.) Thus utility will always try to encourage consumers to: Use less energy during Peak hours (Peak Clipping) Shift energy use to off peak hours (Valley Filling) 8
Therefore consumers too have a very important role to play for achieving the objectives of DSM Consum er Utility DSM 9
HOW TO DO DSM? To charge higher prices during Peak Hours Improving the efficiency of various end uses by using energy efficient appliances, better house keeping and reducing energy leakages. This is important for agriculture where energy efficiency is very low (30-50%) Promoting use of Energy Efficient Technologies and addressing Aggregate Technical and Commercial (AT&C) Losses 10
Benefits of Demand Side Management Customer Benefits Utility Benefits Societal Benefits Satisfy electricity demands Reduce environmental degradation Lower cost of service Reduce / stabilize costs or electricity bill Improve operating efficiency, Flexibility Conserve resources Maintain/improve lifestyle and productivity Improve customer service Protect global environment 11
Present Scenario in West Bengal Major utility Service Provider WBSEDCL CESC Peak Load 4,600 MW 1,700 MW Type of Consumer Percentage of Electricity usage under WBSEDCL (2011) 30.3% 14.07% 10.25% 35.93% 9.36% Domestic Commercial Agriculture Industrial Others 12
Actions undertaken by WBSEDCL in West Bengal TOD meters for Industrial and Agricultural consumers 173 sodium vapour lamps replaced by LED Energy Audit undertaken in Government buildings and corrective measures are being undertaken Waste Heat Recovery in some industries undertaken Bachat Lamp Yojna 13