TNMP is facing challenges with the upcoming AT&T 3G network sunset and supply chain impacts, leading to a shortfall in meters for their NextGen rollout. Efforts are underway to mitigate the impact, including implementing manual meter reading processes. The company is working towards finding solutions to address the communication loss with approximately 115,000 AMI meters starting in March 2022.


Uploaded on Aug 15, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Docket No. 51387 Supply Chain Impacts Review with RMS December 7, 2021

  2. AT&T 3G Sunset On February 21, 2019, AT&T notified TNMP of their intentions to turn down the 3G network in February 2022. Early discussions suggested that there was some fluidity to that date, however since then, TNMP has not received confirmation of any timing adjustment. TNMP Management has had numerous discussions with AT&T counterparts, so far to no avail. TNMP has made a formal request for a date extension.

  3. 3G Meters Deployed As of February 2020, there were 173,737 meters deployed on the AT&T 3G network throughout TNMP service territory, which is consistent with filings under Docket No. 51387. As of October 2021, there are 146,293 meters deployed on the AT&T 3G network.

  4. Supply Chain Impacts On July 16, 2021, TNMP s AMI vendor notified TNMP of potential supply chain disruptions due to COVID-19. While the notice did not quantify the impact, TNMP has experienced a significant shortfall of meters to support the NextGen rollout. TNMP had initially planned to receive and install NextGen meters to replace all 173,737 3G prior to the turndown. TNMP now expects to receive and install approximately 31,000 NextGen meters prior to the 3G turndown. TNMP expects to lose the ability to communicate with approximately 115,000 AMI meters beginning in March 2022.

  5. Mitigation TNMP is currently working with utility service provider(s) to implement a manual meter reading process in the interim. Current guidance, projects that TNMP will not receive enough meters to fully remediate the 3G turndown, until EOY 2022.

  6. TNMP Service Territory North Texas 3G 50,781 4G 27,016 Total customer base of 262,646 in four operating areas within Texas, covering 7,100 square miles. Central Texas 3G 20,295 4G 5,781 262,415* TNMP customers are AMI-enabled: 3G 146,293 4G 116,122 * As of Oct 2021 West Texas 3G 9,880 4G 9,474 Gulf Coast 3G 65,337 4G 73,851