Status Update on Magnet Structures and Coils
The provided content discusses the current status of magnet structures and coils, including completion reports, testing updates, and coil availability. Key points include the disassembly of coils for testing, updated specifications for magnet excursions, and the arrival and review of various coils from different locations. Additionally, the post touches on ongoing work, such as new technician training and collaboration efforts with CERN for sourcing bladders.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
302.02.07 Structures Status Magnet Status Notes Pre-Series MQXFA03 Complete; report released MQXFA04 Complete; report released MQXFA05 Complete; report released MQXFA06 Complete; report released MQXFA07b Complete Series No coil SG data with 2ndthermal cycle MQXFA08b Complete; report released MQXFA10 Complete; report released MQXFA11 Complete; report released MQXFA14b Test complete Fab & Test report drafts completed MQXFA15 Complete At FNAL MQXFA16 Direct to FNAL10/13 Fabrication Report drafts edited 302.02.07 Structures Status, 12-Aug-24 1
302.02.07 Structures Status Magnet Series MQXFA09 Status Notes Two coils no longer available (in A14b, A15); Structures used in MQXFA11; will be renamed MQXFA24 Disassembled Dye penetrant testing to be performed before finishing work Work to be completed before MQXFA17 starts. Dye penetrant should be applied this week, probably before Wednesday MQXFA12b First thermal cycle complete; SG data shown after this update MQXFA13b Could Coil 242 be candidate for replacement? (reviewed with magnet originally) MQXFA17 Arrived from BNL; will be worked on after MQXFA18 moves to shipping crate Placing in the crate will be done this week. Hands off and specs. meeting scheduled for Thursday and Friday this week Could ship as early as 8/24. MQXFA18 should be shipped before MQXFA16 arrives. We don t have space for so many magnets (we currently have MQXFA12b, 18 and 17 onsite) MQXFA18 Will be on hold until A17 rework is completed MQXFA19 302.02.07 Structures Status, 12-Aug-24 2
302.02.07 Structures Status 2 Series Magnets (cont.) Updated Magnet specifications to allow for 120 MPa excursions, increased from 110 MPa MQXFA07b, MQXFA16, MQXFA15 reload did not require 120 MPa MQXFA17 reached 120 MPa during preload MQXFA13b coil 2 reached 126 Mpa in last excursion 302.02.07 Structures Status, 12-Aug-24 3
Coils in Storage at LBNL Coil Reviewed in Magnet Notes LE CMM + Nom. CMM RE CMM + (Was) Replacement coil for MQXFA13b (large) 241 A13b * * Small coil (was originally for MQXFA12b) 158 A12b + Spare (was for MQXFA17 and/or MQXFA13b) 242 A17/13b * * On Hold. (Too small spare for MQXFA16) 234 13b Arrived from BNL 12/4; CMM complete 240 Arrived from BNL 12/4; CMM complete 248 Arrived from BNL 2/5/24 244 A18 CMM Measurements on LE/RE 3x; repeatability meas. 161 A18 Arrived from BNL 4/1/24 251 FNAL Coil arrived 4/15 156 Arrived from BNL 7/20 245 Arrived from BNL 7/20 247 Averaged 3x extra measurements taken on ends + Measured 6+ additional profiles on LE and RE * Measured 3+ additional profiles on LE and RE 302.02.07 Structures Status, 12-Aug-24 4
302.02.07 Structures Status Other topics Technicians New techs are getting up to speed Bladders: Working with CERN to source 60-100 bladders of their style for MQXFA lengths Planning upgrade for HP cart to accommodate additional circuits Extra ARMCO is stored in Berkeley Property Transfer from LBNL to FNAL MQXFA07b, MQXFA15 property documents processed Transfers to happen in bulk MQXFA spare parts Shells, yokes orders placed; Shells forgings QC report accepted Bladders PO s placed; First Articles ready Magnetic Shims PO arrived last week Axial rods PO placed 302.02.07 Structures Status, 12-Aug-24 5
Additional slides 302.02.07 Structures Status, 12-Aug-24 6