Romeo Malette Forest 2019-20 Annual Work Schedule Overview

Romeo Malette Forest
2019-20
 Annual Work Schedule
Period
April 1, 2019 to March 31, 2020
Year 1
First AWS of the 2019 FMP
2
Harvest Area
3
Harvest Area
Phase 2 blocks from 2009-2019 FMP (bridging
blocks have one year to cut them) about 1,013
ha
4
Overlapping Licenses
EACOM and RYAM have 45% each of SPF
volume.
Little John has 10% of SPF volume
Georgia Pacific has all poplar and birch OSB
Rockshield has all poplar veneer
5
Mills
RYAM – SPF Sawlogs; Cochrane
EACOM – SPF Sawlogs; Timmins and Ostrom
GP Northwoods – Po/Bw OSB; Englehart
Little John – Sawlogs; Timmins
Millson – Bw Fuelwood; Timmins
Rockshield – Po Veneer, Cochrane
6
Silviculture
-  
 
Site Preparation ~ 1,100 ha
- 
 
Natural regeneration ~ 2,000 ha
-
Planting ~ 1,100 ha
-
Seedlings ~ 1.71 million
-
Aerial Tending ~ 1,500 ha
-
Slash piling
7
Roads
Horwood Peninsular Road – Primary may build
Straighten  Penhorwood Road at 16 km
Branch and operational road construction to
access harvest allocations
Road Maintenance
8
Crossing Removals and Replacements
Potential Removals
-Kaneki bridge
-Pharand bridge
- Bl 364, Fripp Road, Bl 348, Bl 357.
Potential Replacement
- 
Nat River Bridge - Malette Road
9
Forestry Aggregate Pits
Aggregate pits used to build forest access
roads
Established within harvest blocks, approved
road corridors or operational road boundaries
Can be active for up to 10 years
Six to expire this year
10
Regeneration Surveys
2,000 ha scheduled for survey this year
- By helicopter
11
Questions or Comments?
 
12
Slide Note
Embed
Share

This document provides an overview of the annual work schedule for Romeo Malette Forest from April 1, 2019, to March 31, 2020. It includes information on the scheduled harvest area, phase 2 blocks, overlapping licenses, mills involved, silviculture activities, and road development plans. The content also addresses specific details such as harvest area allocations, license distribution, and forestry operations within the designated period.

  • Forest Management
  • Annual Schedule
  • Harvest Area
  • Silviculture
  • Road Development

Uploaded on Sep 22, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Romeo Malette Forest 2019-20 Annual Work Schedule

  2. Period April 1, 2019 to March 31, 2020 Year 1 First AWS of the 2019 FMP 2 Rayonier Advanced Materials Confidential and Proprietary Information

  3. Harvest Area Forest Unit Annual Avg Harvest Area (ha) 2018-19 Scheduled Harvest Area (ha) BW1 110 272 LC1 456 1,252 MC2 426 1009 MW1 236 746 MH2 703 1,439 Pj1 131 575 Pj2 78 133 Po1 399 778 SB1 1,168 2,333 SF1 268 635 SP1 1,121 2,638 Total 5,096 11,810 3 Rayonier Advanced Materials Confidential and Proprietary Information

  4. Harvest Area Phase 2 blocks from 2009-2019 FMP (bridging blocks have one year to cut them) about 1,013 ha 4 Rayonier Advanced Materials Confidential and Proprietary Information

  5. Overlapping Licenses EACOM and RYAM have 45% each of SPF volume. Little John has 10% of SPF volume Georgia Pacific has all poplar and birch OSB Rockshield has all poplar veneer 5 Rayonier Advanced Materials Confidential and Proprietary Information

  6. Mills RYAM SPF Sawlogs; Cochrane EACOM SPF Sawlogs; Timmins and Ostrom GP Northwoods Po/Bw OSB; Englehart Little John Sawlogs; Timmins Millson Bw Fuelwood; Timmins Rockshield Po Veneer, Cochrane 6 Rayonier Advanced Materials Confidential and Proprietary Information

  7. Silviculture - Site Preparation ~ 1,100 ha - Natural regeneration ~ 2,000 ha - Planting ~ 1,100 ha - Seedlings ~ 1.71 million - Aerial Tending ~ 1,500 ha - Slash piling 7 Rayonier Advanced Materials Confidential and Proprietary Information

  8. Roads Horwood Peninsular Road Primary may build Straighten Penhorwood Road at 16 km Branch and operational road construction to access harvest allocations Road Maintenance 8 Rayonier Advanced Materials Confidential and Proprietary Information

  9. Crossing Removals and Replacements Potential Removals -Kaneki bridge -Pharand bridge - Bl 364, Fripp Road, Bl 348, Bl 357. Potential Replacement - Nat River Bridge - Malette Road 9 Rayonier Advanced Materials Confidential and Proprietary Information

  10. Forestry Aggregate Pits Aggregate pits used to build forest access roads Established within harvest blocks, approved road corridors or operational road boundaries Can be active for up to 10 years Six to expire this year 10 Rayonier Advanced Materials Confidential and Proprietary Information

  11. Regeneration Surveys 2,000 ha scheduled for survey this year - By helicopter 11 Rayonier Advanced Materials Confidential and Proprietary Information

  12. Questions or Comments? 12 Rayonier Advanced Materials Confidential and Proprietary Information

More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#