PORTFOLIO COMMITTEE BRIEFING ON HUMAN SETTLEMENTS
This briefing covers the purpose of the presentation, conditional grants allocation, financial performance, progress on MINMEC priorities for FY 2023/24, challenges faced, recommendations, and conclusions. It also outlines the status and challenges in the implementation of projects concerning human settlements, including grants allocation and financial performance.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
PORTFOLIO COMMITTEE BRIEFING ON HUMAN SETTLEMENTS 20th SEPTEMBER 2023 1
PRESENTATION OUTLINE A. PURPOSE OF THE PRESENTATION B. CONDITIONAL GRANTS ALLOCATION C. FINANCIAL PERFROMANCE D. PROGRESS ON MINMEC PRIORITIES FOR 2023/24 FY Unblocking of blocked projects Military Veterans Mud Houses Work opportunities Replacement of Asbestos Roofs Upgrading of Informal Settlements Delivery of Bulk Infrastructure Progress made in the issuance of Title Deeds Natural Disasters E. CHALLENGES F. RECOMMENDATIONS G. CONCLUSIONS 2
A. PURPOSE OF PRESENTATION A. PURPOSE OF PRESENTATION This presentation will: Purpose of this presentation is to give an overview of the Free State Provincial Department of Human Settlements Development Grant and Informal Settlements Partnership Grant Business Plans for the financial years 2023/24 2025/26 To present the status quo on the performance of the MTSF Highlight progress on the implementation of projects that will contribute to the achievement of the MTSF targets Outline performance challenges and proposed interventions 3
B. CONDITIONALGRANT ALLOCATION 4
MTEF ALLOCATIONS 2023/24 2025/26 2025/26 MTEF 2023/24 MTEF 2024/25 MTEF BUDGET BUDGET GRANT FRAMEWORK BUDGET R 000 NEW TITLE SITES UNITS TRG SITES UNITS SITES UNITS R 000 R 000 HSDG 4805 1813 R886 197 000 4502 960 R925 888 000 2216 3521 R 848 099 000 3394 2925 2023/24 MTEF 2024/25 MTEF 2025/26 MTEF BUDGET BUDGET BUDGET GRANT FRAMEWORK SITES SITES SITES R 000 R 000 R 000 UISPG R252 209 2,469 R263 536 2 498 R275 342 2 498 5
C. FINANCIAL PERFORMANCE 6
2023/24 CONDITIONAL GRANT PERFORMANCE Current Budget Allocation 2023/24 Expenditure as at 31 August 2023 Available Budget % Spent Conditional Grants R'000 R'000 R'000 % HUMAN SETTLEMENTS DEVEL GRANT INFORM SETTL UPGR PART GRNT PROV EPWP INTEGRATED GRANT FOR PROV 848 099 80 467 767 632 9.5% 252 209 5 613 246 596 2.2% 2 591 556 2 419 2.1% Total 1 102 899 86 636 1 016 263 7.9% 7
HSDG PERFORMANCE PER PROGRAMME Current Budget Allocation 2023/24 Funds Received as at 31 August 2023 Expenditure as at 31 August 2023 Available Budget Human Settlements Development Grant % Spent R'000 R'000 R'000 R'000 Financial Interventions 1.1a Individual housing subsidies (R0 - R3 500) credit linked 1.1b Individual housing subsidies (R0 - R3 500) Non - Credit Linked 1.2 Housing finance linked Individual subsidies (FLISP) 1.7 Accredited Municipalities (level 1 & 2): 1.8 Operational Capital Budget 1.10 NHBRC enrolment (related to grant) Incremental Interventions 2.2a Integrated Residential Development Programme :Phase 1:Planning and Services 124 957 11 180 37 289 87 668 30% - - - - 0% 67 788 7 180 3 408 64 380 5% 12 000 3 000 11 320 680 94% 2 000 33 169 10 000 706 062 1 000 - - 67 464 - 2 000 10 709 9 899 0% 68% 1% 22 460 101 42 529 663 533 % 252 907 25 697 37 741 215 166 15% 2.2c Integrated Residential Development Programme :Phase 2:Top Structure Construction 451 274 41 767 4 788 446 486 11% 2.3a People's Housing process 2.6 Emergency Housing Assistance Social and Rental Interventions 1 830 - - 2 400 - - 1 830 51 16 431 0% 0% 0% 51 17 080 649 3.3b Community residential units (CRU) Constructed 17 080 2 400 649 16 431 4% Total 848 099 81 044 80 467 767 632 10% 8
D. PERFORMANCE OF PROJECTS 9
UNBLOCKING OF BLOCKED PROJECTS No of projects on the business plan 19 18 31 10 20 98 DISTRICTS Total Planned units Mangaung Lejweleputswa Fezile Dabi Thabo Mofutsanyane Xhariep TOTAL 164 80 72 20 57 393 The Free State Province has 231 blocked projects which were not completed due to various reasons:- Cancellation of contracts due to non-performance and delay in appointment of replacement contractor. Lapse of contracts and delay in appointment of replacement contractor. slow process of title deeds registration Progress to date: For the 2023/2024 financial year, the Department has planned to finalize 98 blocked projects which consists of 393 units in all districts. Site verification on the number of units which are not complete on each project is almost complete. Downscaling of projects to approved beneficiaries is also underway, this will assist in closing projects where all approved beneficiaries have benefitted. 11
Military Veterans Programme 179 houses planned for Military veterans and 99 have been completed. PROJECT NUMBER PROJECT ALLOCATION PROGRESS % COMPLETE COMMENTS PROJECT NAME LOURIEPARK MILITARY VETERANS 30 27 NORMAL, 3 DISABLED UNITS 50 FOUNDATIONS, 50 WALLPLATES, 34 COMPLETIONS F15010009/1 30 100,00%Project complete HILLSIDE VIEW MILITARY VETERANS 50 F15080001/3 50 80,00% 7 FOUNDATIONS, 7 WALLPLATES, 2 COMPLETIONS KROONSTAD 9 MILITARY VETERANS VILJOENKROON 1 MILITARY VETEREANS F15010009/3 9 75,00% F15010009/5 1 1 COMPLETION 6 FOUNDATIONS, 6 WALLPLATES, 4 COMPLETIONS 100,00%Project complete PARYS MILITARY VETERANS 6 F15010009/4 6 90,00% 20 houses completed in Riebeeckstad, 42 houses in Redeerspark and Odendaalsrus done through individual subsidies. 20 FOUNDATIONS, 20 WALLPLATES, 20 COMPLETIONS, 9 COMPLETIONS. 12 HOUSES IN PROGRESS WELKOM 62 MILITARY VETERANS INDIVIDUAL SUBSIDY MILITARY VETERANS F170400034/1 62 32% F18040002/2 21 42,00% Developer started with preliminaries for the construction of MVH at Vista Park project MILITARY VETERANS VISTA PARK III TOTAL 30 179 0 99 completions 0% 12
MUD HOUSES PROGRAMME In the Province currently assessment of mud houses has been done in three districts, Mangaung, Thabo Mofutsanyane and Xhariep. There is a total of 342 mud houses that have been confirmed for the programme and the process of assessment has not been finalised. The Department has planned for 80 units in the current business plan to be done under the Rural Subsidy Communal Land Rights programme. 14
Work opportunities created per programme No of jobs to be created in 2023/2024 programmes No of jobs created IRDP: Phase 1 400 19 IRDP: Phase 2 100 0 TOTAL 500 19 The Province annual target for work opportunities across all programmes is 500. 19 work opportunities were created currently. The Province is still in a process of appointing contractors in most of the projects and this has resulted in a low number of work opportunities created. There will be improvement once the contractors have been appointed. 16
ASBESTOS REMOVAL AND REPLACEMENT PROJECT Contractors for the removal and replacement of the Asbestos are already on site across the Province. Asbestos roofed houses have already been identified through a previous survey and has been submitted to PSP for scope allocation to contractors Contractors will provide storage units for beneficiaries to store household contents before commencing with removal The removal and replacement process is estimated to last for a maximum of two weeks per unit provided the structural integrity assessment of such a unit is acceptable 17
ASBESTOS ROOF REMOVAL AND REPLACEMENT Sasolburg Fezile Dabi 18
INFORMAL SETTLEMENT PARTNERSHIP GRANT 19
PROGRAMME OVERVIEW: CURRENT MTSF PROGRAMME OVERVIEW: CURRENT MTSF Number Comments Total No of IS in FS 161 (inc 47 in Mangaung Metro) Category A 63 Category B1 19 Category B2 5 Category C 62 Category A & C 11 Category B1 & C 1 Est number of House Holds in the FS IS 77 683 Total number of IS Categorized 161 Total number of Upgrading Plans Dev (as per NUSP) 148 The proposed ISUG allocation for 2022/23 R252 209 000 The number of settlements identified to receive funding in terms of UISPG 49 Planned to benefit 26,181 households 20
ISUPG BUDGET SUMMARY 2023/24 Financial YearSUMAY Number of Informal Settlements 9 1 Budgetary Arrangement % Activities in the Plan Total Budget 3% Social Facilitation Alternative Sanitation Social Facilitation Human Rights Package Social and Economic Amenities R883,349 R6,013,843 0,35% 2,31% N/A R0 0% 1 R133,900 0,05% Title Deed EIA Application (All Studies) Traffic Impact Study Geo Technical investigation TIA Township Layout Plan Land Surveying, Pegging and General Plan Township Register Opened Engineering Designs for Water Engineering Designs for Sewer Bulk and Link - Sanitation Construction Reticulation / Individual Municipal Engineering Services: Water Reticulation / Individual Municipal Engineering Services: Sanitation 7 R1,181,601 0,47% 15 8 15 18 R1,466,470 R1,087,118 R4,408,854 R9,334,419 0,58% 0,43% 1,75% 3,70% Security of Tenure and Formalisation 16 8 R4,013,031 R8,104,800 1,59% 3,21% 6,35% 9 R16,025,038 1 R27,618,870 10,95% 14 R111,931,842 44,42% Permanent Infrastructure 14 R60,005,860 23,83% R252 209 000.00 100% TOTAL 55 21
Running Projects Township Establishment EXPENDITURE TO DATE TOWN/SETTLEMENT/S PLANNED PROJECT BUDGET PROGRESS MUNICIPALITY Project completed, still to pay VO, busy with proclamation Brandfort Majwemasweu Slovo Park Brandfort, Majwemasweu: Slovo Park Township Establishment Masilonyana R1 105 700 R1,002,660.30 Project completed, busy with proclamation To be paid this month Social compact completed, Geo tech, services report completed NPT approval on 2 site, TIA finalization on third site Wesselsbron Nyakallong Khalinkomo & Vergenoeg Wesselsbron, Monyakeng: Vergenoeg Township Establishment Nala R337 287 R241,263.33 R2 859 903 Silahliwe Free State - Planning & Surveying (Bopa Lesedi) Portion 41 of Farm Dorps Gronden 131 Township Establishment R 2 360 189 Harrismith Intabazwe Portion 41 R295,639.99 Maluti-a-Phofung 1 828 000 Manyatseng Marikana and Palamente Marikana Township Establishment Mantsopa R 530 059 SG Submission Clocolan Hlohlolwane Internal Settlements Clocolan - Farm Clocolan Townland No. 40 Township Est Setsoto Application submitted to MPT Fauriesmith, Ipopeng and Riverdale Township Establishment Kopanong R 413 490 Fauriesmith - Ipopeng TOTAL R173 925 038 22
Running Projects - Infrastructure EXPENDITURE TO DATE TOWN/SETTLEMENT/S PLANNED PROJECT BUDGET PROGRESS MUNICIPALITY Metsimaholo 2962 Sasolburg Water and Sewer Zamdela Ext 18 Mooidraai Raymond Mohlaba 3075 Harrismith Makholokoeng - 1700 Households Water Reticulation Sasolburg Zamdela - Raymond Mohlaba and Mooidraai Consultant updating the design R32 745 908 Metsimaholo R64 900 000 R14 744 415 (captured) Contractor on site, project progressing well Makholokoeng Maluti-a-Phofung R1 155 600 00 30% Bothaville Kgotsong - Matlharantlheng Bothaville Matlharantlheng Water And Sewer Nula R34 629 502 80 sites connected with water and sewer (R7 856 235 (inv) R3 750 000 R1 891 964,01 Project completed Mamahabane -Roma and DNDMatjhabeng: Water and Sewer for 500 sites in Mmamahabane Ext 4 R12 215 000 R1 809 086,61 Awaiting approval of VO Bronville - Rethuseng, Matlharantlheng (Bronville) and Ext 20 1&2 Matjhabeng: Water and Sewer for 800 sites in Thabong Ext 25 Homestead Matjhabeng R4 000 000 Contractor back on site Water and Sewer for 873 sites in Welkom, Thabong Ext 27 (Phokeng) Welkom Thabong - Phokeng block 1&2 and Kgotha Welkom Thabong - Freedom Square & C Section Matjhabeng Selatile Moloi - Water and Sewer for 390 sites in Welkom Thabong/Bronville Ext 26 (Freedom Square) - Phase 1 R8 750 000 Challenges with the contractor Awaiting municipal connection Ngwathe Tumahole Ext 7 W&S R3 500 000 Ngwathe Abazimeli 23
Projects under Procurement MUNICIPALITY TOWN/SETTLEMENT/S PLANNED PROJECT BUDGET Cornelia Ntswanatsatsi- Internal Settlements Cornelia Ntswanatsatsi Township Establishment R425 622 Frankfort Namahadi Internal Settelements Frankfort Namahadi Township Establishment R500 045 Mafube Villiers Qalabotjha Township Establishment R493 000 Villiers Qalabotjha Internal Settlements Tweeling Mafahlaneng Internal Settlements Twelling Mafahlaneng Subdivison and Rezoning R397 500 Tswelopele R227 998 Bultfontein Phameng Park 5229 Baipehi Bultfontein Subdivision And Rezoning - Phase 1 Wesselsbron Nyakallong Khalinkomo & Vergenoeg Nala R 587 000 Nala :erven 6819 And 10275 Township Est - Phase 1 R487 945 500 Section Subdivision and Rezoning, Erven 1174/75 and 1315/16 Tokologo R315 720 Manyatseng - Platberg Ext 15 Subdivision and Rezoning Mantsopa R 8 400 000 Memel Zamani Forster SEction Phumelela: Memel (foster Section) W&s (Phase) Phumelela R 1 971 100 Memel Zamani Forster Section Memel Township Establishment 24
Projects under Procurement TOWN/SETTLEMENT/S PLANNED PROJECT BUDGET MUNICIPALITY Kopanong R197 049 Mokoai Moletsane Reddersburg Township Establishment Kopanong R227 759 Ghost Park Edenhoogte Edenburg Township Establishment R620 042 Reitz Petsana - Hillview Petsana Subdivision And Rezoning - Phase 1 Nketoana R14 850 780 Total 25
Projects Planned for Accelerated Procurement TOWN/SETTLEMENT/S PLANNED PROJECT BUDGET MUNICIPALITY R 9 246 000 Brandfort Majwemasweu Slovo Park Brandfort - Water And Sewer - Phase 1 Masilonyana R 7 336 000 Winburg Makeleketla - Baipeing Winburg - Baipeing Water And Sewer - Phase 1 R1 900 000 Hennenman Phomolong - Baipehing Matjhabeng: Water and Sewer for 854 sites in Hennenman, Phomolong Matjhabeng Welkom Thabong - N1 Gugulethu R1 666 378 Matjhabeng: DoornPan N1 Township Est (Phase) R8 312 800 Harrismith Intabazwe Silahliwe Maluti-a-phofung Silahliwe (intabazw) W&s - Phase 1 Maluti-a-Phofung R 6 637 696 Manyatseng Marikana and Palamente Mantsopa Marikana W&s - Phase 1 Mantsopa Twelopele R 255 210 Bultfontein Phahameng- Baipeing Phahameng 200 Subdivison and Rezoning - Phase 1 Zastron, Matlakeng: Mooifontin Township Establishment Mohokare R2 852 523 Refengkgotso and Ezibeleni 26
Projects Planned for Accelerated Procurement TOWN/SETTLEMENT/S PLANNED PROJECT BUDGET MUNICIPALITY R 9 078 000 Senekal, Matwabeng Masaleng & Mokodumela Senekal, Matwabeng Ext 7: Water and Wewer + Pump station Setsoto R 867 000 Bohlokong - Captain Charles Relocation from Captain Charles to Ext. 5 Bakenpark Dihlabeng R 170 000 Bohlokong - Boipatong Relocation from Boipatong to Ext. 7 Bakenpark Dihlabeng R344 904 Units 3 & 7 Virginia unit 3 & 7 Water and Sewer Matjhabeng Mohokare R 7 352 000 Roleleathunya Baipeing Somerset Mohokare Baipehi (roleleathunya) W&s (Phase) Letsemeng R 7 414 671 Jacobsdal Phambili Letsemeng: Phambili Township Est - Phase 1 TOTAL R63 433 182 27
BULK AND INFRASTRUCTURE PROJECTS 28
Bakenpark Exts. 6&7 Name of Contractor MSK Construction (PTY) LTD BAKENPARK EXTs. 6 & 7 Name of Consultant Aphane Consulting (PTY) LTD Institutional Arrangements: MTOP Project Name Bakenpark Ext 6 & 7 Internal Services: Water, sewer, roads and storm water installation for 181 sites in Ext. 6 and 1 273 sites in Ext. 7 Bulk: Construction of 3ML Reservoir, Ext. 6 Pump Station, Ext. 7 Pump Station, outfall sewer lines and rising mains Type & Description Ward 3, Bethlehem CBD, Dihlabeng Local Municipality, Free State Location Client Details Free State Human Settlements Participating Organizations FSHS, HDA & DLM Implementing Agent Role of HDA Service Provider Consultant Contractor Commencement date 21 September 2021 21 September 2021 Original Completion date 10 December 2023 21 September 2024 Revised Completions date None None PROJECT STATUS Bulk work Actual Completion date None None Internal work Bulk Sewer 400mm pipe is at 96% 315mm pipe is at 93% 250mm pipe is at 77% 200mm pipe is at 88% Bulk water 250mm pipe is at 16% Reservoir Mass Earthworks is at 100% Ext 6 Water and Sewer is complete. Box cutting is at 100% Sub-base & base layers are at 100% Kerbing is at 94% Ext 7 110mm Water network is at 96% 160mm Sewer network is at 90% Box cutting is at 85% Project Value R11 530 222.37 R328 357 954.76 R3 371 948.12 R127 290 208.00 Budget (23/24 FY) Project Expenditure (23/24 FY) R 205 224.50 R22 314 577.91 Project Expenditure (to date) R8 363 498.75 R131 898 802.60 GL Code 3403 None 29
Bakenpark Exts. 6&7 The Free State Department of Human Settlements appointed the HDA as the Implementing Agent for Bakenpark Exts. 6 and 7 Integrated Mixed Housing Development that includes BNGs, FLISPS, Social Housing, and Open Market Bonded Units. The project is currently at the installation of bulk and internal civil engineering services which are the following: Bulk: Construction of 3ML Reservoir, Ext. 6 Pump Station, Ext. 7 Pump Station, outfall sewer lines and rising mains Internal Services: Water, sewer, roads and storm water installation for 181 sites in Ext. 6 and 1273 sites in Ext. 7, totaling to 1454 sites for both extensions. - In the 2022/23 FY, 1058 sites were serviced with an internal water and sewer network. - Currently (2023/24 FY), 282 sites are serviced with an internal water and sewer network. 30
Vista Park II Name of Developer Emendo Inc VISTA PARK II Ilifa Africa Name of Consultant Institutional Arrangements: Implementation protocol (IP) Project Name Vista Park II Provision of services to mixed use development Type & Description Ward 19, Mangaung Metropolitan Municipality Location Mangaung Metropolitan Municipality Client Details NDHS, FSHS, HDA & MMM Participating Organizations Implementing Agent Role of HDA 14 September 2014 Commencement date Original Completion date 31 October 2032 TBC Revised Completions date PROJECT STATUS TBC The Developer is currently working on the amendment to the Township Layout Plan, which will allow the finalization of the draft TIA report. The Developer has yet to re-submit the draft TIA to the MMM Traffic Department with the incorporated comments. The Developer has received an instruction from Mangaung Metro to construct a bulk sewer line along Vereeniging Road. The Developer reestablished the construction site and the site handover meeting took place on June 28th, 2023. Construction Material was delivered on site on July 28th, 2023. Site Clearance, grubbing and setting out is ongoing. Actual Completion date TBC Project Value Budget (23/24 FY) R 15 485 093.40 Project Expenditure R 2 418 269.94 None GL Code 31
Vista Park II The Vista Park II Development aims to generate a mixed-use development. The scope identified to oversee the Vista Park II Development is as follows: Installation of bulk and internal civil engineering services; Installation of electrical engineering services; Construction of top structures for mixed-use purposes. Project Progress The project is at the Township Establishment stage. The Developer is currently working on the amendment to the Township Layout Plan, which will allow the finalization of the draft TIA report. For this Financial Year (2023/24), The Developer is busy with the construction of a bulk sewer line along Vereeniging Road. 32
Vista Park III Name of Developer Calgro M3 (PZR) VISTA PARK III Name of Consultant Bigen Africa Institutional Arrangements: Implementation Protocol (IP) Vista Park III Project Name Provision of services to mixed use development Type & Description Ward 19, Mangaung Metropolitan Municipality Location Mangaung Metropolitan Municipality Client Details NDHS, FSHS, HDA & MMM Participating Organizations Role of HDA Implementing agent Commencement date 14 September 2014 Original Completion date 31 October 2032 Revised Completions date TBC PROJECT STATUS Extensions 261, 262, and 263 Electrical Infrastructure is100% complete. Extensions 261, 262 and 263 Civil Infrastructure is 100% complete. Addendum 2 Link and Cedar Roadworks are 100% complete. The Developer has submitted the concept layout plans for the construction of Military Veteran Top Structures Addendum 3 to the SLA and LAA was finalized and signed by the Developer and Mangaung Metro. Site establishment was completed on July 4th, 2023, in Ext. 257, for the installation of the internal water and sewer network. Excavation for the internal sewer network is 750m complete Actual Completion date None Project Value TBC Budget (23/24 FY) R 88 682 000.00 Project Expenditure (23/24 FY) R 9 883 384.54 GL Code None 34
Vista Park III The Vista Park III Development aims to generate a mixed-use development. The scope identified to oversee the Vista Park II Development is as follows: Installation of bulk and internal civil engineering services; Installation of electrical engineering services; Construction of top structures for mixed-use purposes. Project Progress Extensions 261, 262, and 263 Electrical Infrastructure is100% complete. Extensions 261, 262 and 263 Civil Infrastructure is 100% complete. Addendum 2 Link and Cedar Roadworks are 100% complete. For the current FY (2023/24), the Developer is busy with internal civil and electrical engineering services for Ext. 257 and an internal stormwater network for Ext. 258 35
Meloding Units 3 and 7 Casnan Civils CC Name of Contractor MELODING UNIT 3 & 7 Makhaotse Narasimuli & Associates Name of Consultant MTOP Institutional Arrangements: Meloding unit 3 & 7 Project Name Installation of internal Sewer and Water network, and Top Structures to 104 sites Type & Description Unit 3 known as Mahala park, Unit 7 known as Baleseng In Meloding, Virginia, Matjhabeng Local Municipality, Free State Unit 3 Unit 7 S 28 8'26.89 S 28 8'25.35 E 26 53'8.73 E 26 53'41.24" Location Free State Human Settlements Client Details FSHS, HDA, MLM Participating Organizations Implementing Agent Role of HDA Contractor Consultant Service Provider 11 February 2022 06 November 2020 Commencement date 31 August 2022 06 May 2022 Original Completion date 31 December 2022 31 December 2022 Revised Completions date PROJECT STATUS 31 December 2022 31 December 2022 32 sites have been serviced at Unit 7 72 sites have been serviced at Unit 3 Actual Completion date R 412 379.00 R 4 962 020.00 Project Value The services project was completed on 31 December 2022. The Top Structures project is at the service providers procurement stage. R 113 867.58 R 4 009 847.99 Budget (22/23 FY) R 93 655.21 R 2 920 286.62 Project Expenditure (22/23 FY) R 392 166.63 R 3 845 458.63 Project Expenditure (to date) 6250-05-029 6250-19-040 GL Code 38
Botharnia 9: Phase 2 Name of Contractor Masheleni Trading and Projects BOTHARNIA 9 PHASE 2 Name of Consultant SLB Consulting Institutional Arrangements: MTOP Project Name Botharnia 9 Phase 2 Internal Services: Water and sewer installation for 429 sites at Botharnia in Bothaville Type & Description Bothaville, Nala Local Municipality in Free State S 27 23 10.83 E 26 37 50.21 Location Free State Department of Human settlements Client Details Participating Organizations FSHS, HDA, NLM Role of HDA Implementing Agent Service provider Consultant Contractor Commencement date TBC 21 December 2022 Original Completion date TBC 31 December 2023 TBC None Revised Completions date PROJECT STATUS Excavation of 160mm sewer line is at 62%,110mm and 75mm water line are 20%. Pipelaying of 160mm sewer line is at 44% and 75mm water is at 10% 66 sites have been serviced with both water and sewer. Procurement and delivery of material for the internal water and sewer infrastructure is 100% complete. Actual Completion date TBC TBC TBC R 33 799 501.88 Project Value Budget (2023/24) TBC R 33 799 501.88 None R 2 624 381.42 Project Expenditure GL Code TBC 3515 40
Botharnia 9: Phase 2 The Botharnia 9 Phase 2 project is for the Installation of an internal water and sewer for 429, and a pump station to support the sewer generation. Project Progress Currently (2023/24 FY), 66 sites have been serviced with an internal water and sewer network. 41
SECURITY OF TENURE MTSF Outcome MTSF Indicators National 2024 Targets Provincial Target Actual delivery 2023/24 Annual Target 400 Comments 45 535 outstanding pre-1994 title deeds registered 500 845 outstanding post- 1994 title deeds registered 346 842 outstanding post- 2014 title deeds registered 300 000 new title deeds registered No. of title deeds 1 162 Eradicate backlog and issuing of Title Deeds Several challenges were experienced by conveyancers: (1) The floating of Township Titles amongst conveyancers caused delays for other conveyancers. This is a continuous process in the conveyancing practise but the Department addresses the matter on such a basis when it occurs. During March 2023, the Department succeeded to lodge 1 town title deeds at the Deeds Office. Explanatory Note. Floating of town title deeds is when the Deeds Office issued the client's copy of the original title deed to a conveyancer that needs it to do deeds of transfers. Other conveyancers also wants to make use of the very same town title deed just not to find it with the conveyancer to whom the Deeds Office issued the town title to. In summary the original title deeds float amongst conveyancers. (2) Township registers were opened but proclamation did not follow. The Department will continuously engage with the conveyancers and Department of COGTA to address this matter. (3) Estates were not reported and finalized. This is also a factor that hampered the finalization of transfers. (4) Disputes amongst family members are being addressed on a continuous basis. 2 591 6 363 4509 1 169 1797 16 821 2 364 530 44
ISSUANCE OF TITLE DEEDS NUMBER OF TITLE DEEDS STILL TO BE ISSUED Fezile Dabi 5 490 Lejweleputswa 4 314 Thabo Mofutsanyana 3 102 Xhariep 844 Mangaung 0 TOTAL 13 750 HANDED OVER TO BENEFICIARIES Handed over Mangaung 1 021 Metsimaholo/Zamdela 1 010 Xhariep 755 TOTAL 2 786 45
Jaggersfontein Disaster: Progress Human Settlements was initially tasked with overseeing the enrollment of new houses to be built through NHBRC and identifying parcels of land through the assistance of HDA, should there be a need to relocate the affected community members. The 6 parcels of land where previously identified, however due to the length of time it would have taken to develop new parcels of land, the rebuilding is being done in-situ where the disaster occurred with a few exceptions where infill sites were made available by the Municipality for the relocation of beneficiaries that indicated that they were too traumatized to remain on the same sites where the disaster occurred. The Municipality has identified 47 infill sites which are more than enough to cater for the few beneficiaries who would like to be relocated. 1. Progress on NHBRC enrollment a. Late Enrolment. The files for four late enrolment housing units were submitted by the contractor to NHBRC on 22 August 2023 after engagements and challenges to obtain required supporting documents from the contractor. The financial guarantee and late enrolment invoices will be issued to the home builder on 28 August 2023. The late enrolment will only be concluded once the contractor has paid for the late enrolment fees and submitted a financial guarantee to NHBRC. b. Normal Enrolments x 68 demolish and rebuild units. The contractor requested an extension on 27 June 2023 as they were struggling to obtain support documents from their engineer. An extension was granted by NHBRC, However, through site inspections it has been discovered that the contractor carried on with construction of new houses prior to the enrolment process being duly concluded. The contractor has been issued with a non- compliance notice and if the contractor violates the non-compliance disclaimer, and carries on with the construction work, then NHBRC will file an urgent court interdict application to stop construction until compliance is in place. 49
Jaggersfontein Disaster: Progress The non-compliance of NHBRC enrollment processes has a negative impact on beneficiaries. Under normal circumstances when enrollment is done prior building of houses, NHBRC inspect the building of houses per milestone until final completion of the houses, thereby providing quality assurance throughout the building process. In the case of late enrollment, NHBRC is unable to provide quality assurance and beneficiaries are robbed of that benefit. In instances where houses are not enrolled at all, the NHBRC warranty cover will not be in place and beneficiaries are left with the risk and financial burden of repairing their houses should there be defects at a later stage. 2. Progress on the rebuilding process: The contractor is working on 68 houses that needed to be rebuilt and 64 houses that require refurbishment which include removal and replacement of asbestos roofs. To date there are 3 houses completed, 1 house at wall plate level, 11 houses at foundation level, 22 houses have been demolished, 21 houses are being repaired, 57 asbestos roofs have been removed and 1 asbestos roof has been replaced. The contractor s progress is slow. The sub-contractors expressed challenges in accessing building materials in Jagersfontein which could be one of the contributing factors for the slow progress of work. 50