Plant Constants in Construction Engineering

undefined
 
Developing Schedule/Constants of Plant in
Building and Civil Engineering Construction
BY
DR. RICHARD .A. KOLAWOLE
According to Okoye, Ngwu and Ugochukwu
(2015) it is trying to draw reliable
development projects or make exact quotes
with no accessible constants. While Wood
(1976) reasons that work or plant constants
for setting up the expense of work in the Bills
of Quantities need not be speculated,
envisioned or thought.
It thus becomes indispensable for the
construction professional not only to have a
complete understanding of the necessary
skills, but also to determine the ideal
composition of each skill in order to
accomplish a task at shorter duration and
decreased expense and this can only be
possible through the use technological
standards for labour and plant generally
given as constants (Okereke, 2002).
However, taking into account the distinctions
of each building site as far as climatic
conditions, social and social fluctuations in
the degree of innovative and the nature of
accessible machines and materials, it is
suggested that each construction
organization should establish its own
standards (Okoye, Ngwu & Ugochukwu,
2015).
increase in individual and collective
productivity of labour;
Objective tendering;
Rational use of available resources;
Adaptation of more progressive management
techniques.
Plant literature compilation
In-house data
Construction Plant Schedules/Constants
are a guide
of productivity and may be expressed as a quantity of
hours per unit (or minutes or days per unit) or unit
per hour (or unit per minute or day).
Rating Factor 
-This is expressed as a percentage of
the efficiency of representative operator, which
indicates how efficient an operator is in comparison
to some of his average fellow workers.
Construction Plants
refers to heavy machinery and
equipment used during construction work i.e
Excavators, Cranes, Dumper, Hoist etc
Work Study
Is a generic term for those techniques
particularly for method study and work
measurement Work study techniques are: time
study, motion study, fatigue study and method
study. Since this paper is not interested in
investing factors that affect the efficiency and
economy of a situation being reviewed in order
to effect improvement, but to establish
standard time required to complete work I will
be focusing on 
time study
Time Study
 – is a structured process of directly
observing and measuring plant/labour output
using a timing device (stop watch) to establish
the time required for completion of the work.
The main objective is to determine by direct
observation of plant output in a specific task
and hence establish the standard time.
In time study of Construction Plant, it may
not be possible to study machine time solely
because plant operation includes manual,
mental and machine times
 Manual time involves  three operations, i.e.
handling of tools, machines and materials.
Mental  time denotes  time taken by the worker for
thinking over some operation
Machine time refers to time taken by the plant in
doing its share of work
Observe the process –your study begins by
simply observing
Decide on the fixed beginning and ending
point
Define action endpoint (EP) and terminal
point (TP).
Endpoint of one action is beginning of
next
Break the process into steps and determine
their beginning and end point
Record your data
Number of observations will depend on
Accuracy desired
Confidence desired
Data variability
Note
Outliners are to be neglected
Now that you have recorded all the times, it’s
time to analyse them and do a little math to
arrive at a determination of the average time for
each step.
Adjust the observed time by rating factor to
obtain normal time for each element
Add the suitable allowances to compensate
for fatigue, personal needs, contingencies
etc. to give standard time for each element.
Compute allowed time for the entire job by
adding elemental standard times considering
frequency of occurrence of each element.
Make a detailed job description describing
the method for which the standard time is
established.
Test and review standards wherever
necessary.
Developing output of a Concrete mixer of 200 litres
capacity per day
Assuming that the average observed time for
batching material into a Concrete Mixer is
2.30mins with a rating of 120% .allowance of 10%
is allowed for the operation. The observed time
for adding water and mixing in the drum is 1min
and observed time for discharge is 1/2min. what
is the Mixer output?
Solution
Observed Time =    2.30mins
Rating              =      120%
Allowance        =      10%
Slide Note
Embed
Share

This academic piece delves into the significance of plant constants in building and civil engineering construction projects. It discusses the necessity of accurate quotes, reliable quantities, and standards for labor and plant to achieve efficiency and cost-effectiveness. The content emphasizes the importance of adapting to site-specific conditions, innovative management techniques, and boosting productivity. It also elaborates on construction plant schedules, operator efficiency ratings, and the role of heavy machinery in construction work.

  • Construction Engineering
  • Plant Constants
  • Labor Standards
  • Productivity
  • Construction Machinery

Uploaded on Oct 09, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Developing Schedule/Constants of Plant in Building and Civil Engineering Developing Schedule/Constants of Plant in Building and Civil Engineering Construction Construction BY BY DR. RICHARD .A. KOLAWOLE DR. RICHARD .A. KOLAWOLE

  2. According to Okoye, Ngwu and Ugochukwu (2015) development projects or make exact quotes with no accessible constants. While Wood (1976) reasons that work or plant constants for setting up the expense of work in the Bills of envisioned or thought. it is trying to draw reliable Quantities need not be speculated,

  3. It thus becomes indispensable for the construction professional not only to have a complete understanding of skills, composition accomplish a task at shorter duration and decreased expense and this can only be possible standards for labour and plant generally given as constants (Okereke, 2002). the necessary the in but also of to each determine skill ideal order to through the use technological

  4. However, taking into account the distinctions of each building site as far as conditions, social and social fluctuations in the degree of innovative and the nature of accessible suggested organization standards 2015). climatic machines that should (Okoye, and each establish Ngwu materials, construction its & it is own Ugochukwu,

  5. increase productivity of labour; Objective tendering; Rational use of available resources; Adaptation of more progressive management techniques. in individual and collective

  6. Plant literature compilation In-house data

  7. Construction of productivity and may be expressed as a quantity of hours per unit (or minutes or days per unit) or unit per hour (or unit per minute or day). Construction Plant Plant Schedules/Constants Schedules/Constants are a guide Rating the indicates how efficient an operator is in comparison to some of his average fellow workers. Rating Factor efficiency Factor -This is expressed as a percentage of of representative operator, which Construction equipment Excavators, Cranes, Dumper, Hoist etc Construction Plants Plants refers to heavy machinery and used during construction work i.e

  8. Work Study Is particularly measurement Work study techniques are: time study, motion study, fatigue study and method study. Since this paper is not interested in investing factors that affect the efficiency and economy of a situation being reviewed in order to standard time required to complete work I will be focusing on time Work Study a generic term method for those study techniques and for work effect improvement, but to establish time study study

  9. Time observing and measuring plant/labour output using a timing device (stop watch) to establish the time required for completion of the work. The main objective is to determine by direct observation of plant output in a specific task and hence establish the standard time. Time Study Study is a structured process of directly

  10. In time study of Construction Plant, it may not be possible to study machine time solely because plant operation includes manual, mental and machine times Manual handling of tools, machines and materials. Mental time denotes time taken by the worker for thinking over some operation Machine time refers to time taken by the plant in doing its share of work time involves three operations, i.e.

  11. Observe the process your study begins by simply observing Decide on the fixed beginning and ending point Define action endpoint (EP) and terminal point (TP). Endpoint of one action is beginning of next Break the process into steps and determine their beginning and end point

  12. Record your data Number of observations will depend on Accuracy desired Confidence desired Data variability Note Outliners are to be neglected Note

  13. Elemen t t A A B B C C D D E E Elemen Average Observed Time Average Observed Time 1 1 2 2 3 3 4 4 5 5

  14. Now that you have recorded all the times, its time to analyse them and do a little math to arrive at a determination of the average time for each step. Adjust the observed time by rating factor to obtain normal time for each element Add the suitable allowances to compensate for fatigue, personal needs, contingencies etc. to give standard time for each element. Compute allowed time for the entire job by adding elemental standard times considering frequency of occurrence of each element.

  15. Make a detailed job description describing the method for which the standard time is established. Test and review standards wherever necessary.

  16. Developing output of a Concrete mixer of 200 litres capacity per day Assuming that the average observed time for batching 2.30mins with a rating of 120% .allowance of 10% is allowed for the operation. The observed time for adding water and mixing in the drum is 1min and observed time for discharge is 1/2min. what is the Mixer output? Developing output of a Concrete mixer of 200 litres capacity per day material into a Concrete Mixer is Solution Observed Time = Rating Allowance 2.30mins 120% 10% = =

  17. Solution Observed Time = 2.30mins Rating = 120% Allowance = 10% Normal Time = Observed Time x ?????? 2.30 x 100 Add Allowance = 2.76 x Standard time = Normal time + Allowance = 2.76 +0.276 = 3.036mins Solution = 100 120 = 2.76mins 10 100 = 0.276mins

  18. Therefore, total time required for one batch of concrete =3.036 +1 +0.30 = 4.34mins per batch In a day of 8hours there will be effective mixing for 7hours Number of batch in 1 hour = 60 4.34= 13.82 say 14 Number of batches in 7hours = 14 x 7 = 98 Consider 90% efficiency output per batch = 200 x 90 100=180 litres Therefore output = 180 x 98 =17640litres or 17.64m 17.64m3 3