Nuclear Power Plant Decommissioning Overview

 
Nuclear Power Plant
Decommissioning
Low-Level Waste Advisory Committee
Annual Meeting
October 4, 2019
 
 
Patrick McDonnell, Secretary
 
Tom Wolf, Governor
 
1
 
Removal of a facility from service and
reduction of residual radioactivity to a level
that permits termination of the NRC license
NRC requires the licensees to decommission
the nuclear plant after it ceases power
operations
NRC regulates and provides oversight of the
decommissioning process
 
What is Decommissioning?
 
2
 
DECON
 (immediate dismantling) - The equipment, structures and
portions of the facility containing radioactive contaminants are
removed and decontaminated to a level that permits release of
property and termination of the NRC license.
SAFSTOR
 (deferred dismantling) – The facility is maintained and
monitored in a condition that allows the radioactivity to decay;
afterwards the plant is dismantled and property decontaminated.
ENTOMB
 – Radioactive contaminants are permanently encased on site
in structurally sound material such as concrete and the facility is
maintained and monitored until radioactivity decays to a level that
permits termination of the license.
 
Decommissioning Methods
 
3
 
The licensee may decide to adopt a
combination of the first two choices (DECON
and SAFSTOR)
Reactor decommissioning actions start 5 years
before end of operating license
Decommissioning must be completed within
60 years of permanent cessation of operations
 
Decommissioning Methods (Cont.)
 
4
 
The licensee must establish or obtain a financial mechanism
to ensure there will be sufficient funds for ultimate
decommissioning of the facility
Prepayment, External Sinking Fund, Surety Method,
Insurance or other Guarantee Method
Each nuclear power plant must report to NRC every two years
the status of its decommissioning trust fund (DTF)
Once a plant is within 5 years of permanently ceasing
operations, NRC will begin to review the DTF annually
The report must estimate the minimum amount needed for
decommissioning using the formulas in 10 CFR 50.75
 
Decommissioning Funds
 
5
 
Phase 1. Transition from Operation to Decommissioning
Certificate of permanent cessation of operations
Certificate of permanent removal of fuel from reactor
Post shutdown decommissioning activity report
Phase 2. Major Decommissioning Activities
Permanent removal of major components
Owner can use up to 3 percent of funds for decommissioning planning
Phase 3. License Termination Activities
Submit a license termination plan for final radiation surveys and updated
estimates of remaining decommissioning costs
Requires NRC approval of a license amendment and a public meeting
NRC issues a letter terminating the operating license
 
Phases of Decommissioning
 
6
 
Licensee carries out decommissioning
activities
Licensee manages a decommissioning
contractor
Temporary license transfer to a
decommissioning company and return the
land and spent nuclear fuel to the utility
Asset sale and license transfer to a non-utility
 
U.S. Reactor Decommissioning Business Model
 
7
 
Post Shutdown Decommissioning Activities Report
(PSDAR) meeting
License Termination Plan (LTP) meeting
Opportunity for hearing when a licensee submits a
License Amendment Request (LAR)
Opportunity to provide comments whenever the
licensee submits a PSDAR, LTP or LAR
Opportunity to form a Citizens Advisory Panel for
decommissioning activities
 
Reactor Decommissioning Public Involvement
 
8
 
Adequacy of decommissioning funding
Decommissioning strategies: prompt vs.
deferred
Long-term storage of SNF
Transportation of SNF
Security of the facility
Emergency response reductions
Environmental monitoring
 
Current Decommissioning Issues of Public Stakeholders
 
9
 
10 commercial nuclear power plants
have been decommissioned in the U.S.
11 nuclear power plants are in active
decommissioning
11 nuclear power plants are in SAFSTOR
11 nuclear power plants have announced
shutdowns thru 2025
          Source: Nuclear Regulatory Commission (as of August 2019)
 
Status of Nuclear Power Plant Decommissioning
 
10
 
Independent Spent Fuel Storage Installation
 
11
 
Spent Nuclear Fuel (SNF) Inventory
Approximately 81,518 MTU and increases about 2-2.4K MTU
per year
ISFSI Storage
130,252 assemblies; 36,696 MTU (45%); 2,966 casks loaded;
72 operating ISFSIs; fuel from 119 reactors
Long-term commitment to ISFSIs
Licenses being extended to 60 years
License extensions approved at 30 sites
NRC has found 100 years storage to be safe
         
Source: Nuclear Energy Institute (as of 12/31/2018)
 
ISFSIs in the U.S.
 
12
 
13
 
        
Waste Type                                   Volume (cubic feet)
     High Activity Waste
Class B and C
    
1,770
Class A
     
28,152
     Low Activity Waste (Class A)
  
3,373
     Very Low Activity Waste (Class A)   
 
316,251
         
Source: TMI-1 Post Shutdown Decommissioning Activity report
 
Estimated LLRW Associated with TMI-1 Decommissioning
 
14
 
Questions?
Rich Janati, M.S.
Chief, Division of Nuclear Safety
Administrator, Appalachian Compact Commission
Phone: 717-787-2163
rjanati@pa.gov
Slide Note
Embed
Share

Decommissioning of nuclear power plants involves the removal of facilities from service and reducing residual radioactivity to a safe level for license termination. Methods include immediate dismantling, deferred dismantling, and entombment. Licensees must establish funds for the decommissioning process, with oversight by the NRC. Phases include transitioning from operation to decommissioning and undertaking major decommissioning activities.

  • Nuclear Power Plant
  • Decommissioning
  • Radioactivity
  • NRC
  • Funds

Uploaded on Sep 12, 2024 | 2 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Nuclear Power Plant Decommissioning Low-Level Waste Advisory Committee Annual Meeting October 4, 2019 Tom Wolf, Governor Patrick McDonnell, Secretary 1

  2. What is Decommissioning? Removal of a facility from service and reduction of residual radioactivity to a level that permits termination of the NRC license NRC requires the licensees to decommission the nuclear plant after it ceases power operations NRC regulates and provides oversight of the decommissioning process 2

  3. Decommissioning Methods DECON (immediate dismantling) - The equipment, structures and portions of the facility containing radioactive contaminants are removed and decontaminated to a level that permits release of property and termination of the NRC license. SAFSTOR (deferred dismantling) The facility is maintained and monitored in a condition that allows the radioactivity to decay; afterwards the plant is dismantled and property decontaminated. ENTOMB Radioactive contaminants are permanently encased on site in structurally sound material such as concrete and the facility is maintained and monitored until radioactivity decays to a level that permits termination of the license. 3

  4. Decommissioning Methods (Cont.) The licensee may decide to adopt a combination of the first two choices (DECON and SAFSTOR) Reactor decommissioning actions start 5 years before end of operating license Decommissioning must be completed within 60 years of permanent cessation of operations 4

  5. Decommissioning Funds The licensee must establish or obtain a financial mechanism to ensure there will be sufficient funds for ultimate decommissioning of the facility Prepayment, External Sinking Fund, Surety Method, Insurance or other Guarantee Method Each nuclear power plant must report to NRC every two years the status of its decommissioning trust fund (DTF) Once a plant is within 5 years of permanently ceasing operations, NRC will begin to review the DTF annually The report must estimate the minimum amount needed for decommissioning using the formulas in 10 CFR 50.75 5

  6. Phases of Decommissioning Phase 1. Transition from Operation to Decommissioning Certificate of permanent cessation of operations Certificate of permanent removal of fuel from reactor Post shutdown decommissioning activity report Phase 2. Major Decommissioning Activities Permanent removal of major components Owner can use up to 3 percent of funds for decommissioning planning Phase 3. License Termination Activities Submit a license termination plan for final radiation surveys and updated estimates of remaining decommissioning costs Requires NRC approval of a license amendment and a public meeting NRC issues a letter terminating the operating license 6

  7. U.S. Reactor Decommissioning Business Model Licensee carries out decommissioning activities Licensee manages a decommissioning contractor Temporary license transfer to a decommissioning company and return the land and spent nuclear fuel to the utility Asset sale and license transfer to a non-utility 7

  8. Reactor Decommissioning Public Involvement Post Shutdown Decommissioning Activities Report (PSDAR) meeting License Termination Plan (LTP) meeting Opportunity for hearing when a licensee submits a License Amendment Request (LAR) Opportunity to provide comments whenever the licensee submits a PSDAR, LTP or LAR Opportunity to form a Citizens Advisory Panel for decommissioning activities 8

  9. Current Decommissioning Issues of Public Stakeholders Adequacy of decommissioning funding Decommissioning strategies: prompt vs. deferred Long-term storage of SNF Transportation of SNF Security of the facility Emergency response reductions Environmental monitoring 9

  10. Status of Nuclear Power Plant Decommissioning 10 commercial nuclear power plants have been decommissioned in the U.S. 11 nuclear power plants are in active decommissioning 11 nuclear power plants are in SAFSTOR 11 nuclear power plants have announced shutdowns thru 2025 Source: Nuclear Regulatory Commission (as of August 2019) 10

  11. Independent Spent Fuel Storage Installation 11

  12. ISFSIs in the U.S. Spent Nuclear Fuel (SNF) Inventory Approximately 81,518 MTU and increases about 2-2.4K MTU per year ISFSI Storage 130,252 assemblies; 36,696 MTU (45%); 2,966 casks loaded; 72 operating ISFSIs; fuel from 119 reactors Long-term commitment to ISFSIs Licenses being extended to 60 years License extensions approved at 30 sites NRC has found 100 years storage to be safe Source: Nuclear Energy Institute (as of 12/31/2018) 12

  13. 13

  14. Estimated LLRW Associated with TMI-1 Decommissioning Waste Type Volume (cubic feet) High Activity Waste Class B and C Class A Low Activity Waste (Class A) Very Low Activity Waste (Class A) Source: TMI-1 Post Shutdown Decommissioning Activity report 1,770 28,152 3,373 316,251 14

  15. Questions? Rich Janati, M.S. Chief, Division of Nuclear Safety Administrator, Appalachian Compact Commission Phone: 717-787-2163 rjanati@pa.gov

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#