Lostock Sustainable Energy Plant Local Liaison Committee Meeting Summary

 
Lostock Sustainable Energy Plant (SEP)
 
Local Liaison Committee
 
29
th
 November 2018
 
2
 
 AGENDA
 
 
Welcome & Introductions
Proposed Power Upgrade Application
Update on Site Works Since Last Meeting
Proposed Work Activities in Next 3 to 6 Months
Subsequent Project Works
Date of Next Meeting
AOB
 
 
 
 
 
 
3
 
Welcome & Lostock Site Rules
 
Welcome to the seventh Lostock SEP Local Liaison
Committee
 
Office Rules
 
TATA representative will act as Guardian
 
No fire alarm test planned for today. If alarm sounds
follow Guardian to muster point in staff car park at the
rear of the building
 
 Toilet facilities on this floor
 
Smoking Prohibited in the office.
 
 
 
4
 
Project Overview
 
Lostock Site History and Overview
 
Lostock Site commenced soda ash production in 1907; Brunner Mond (now
TATA Chemicals Europe Ltd) acquired the site in 1904. Demolished and rebuilt
new manufacturing plant.
 
Soda ash produced from brine (NaCl) and carbon dioxide (CO2)
Brine supplied from the Holford salt cavities operated by Inovyn
Carbon dioxide produced from the thermal decomposition of limestone
with coke.  Limestone railed in from Buxton
Ammonia is used as a catalyst (pH conditioner) to assist the chemical
reaction
Soda Ash production is energy (heat) intensive.  Steam required to drive the
chemical reactions and dry the product.
 
The site operated its own coal fired power station (six boilers) up to the year
2000.  Decommissioned when new gas fired CHP power plant started at
Winnington
 
 
 
 
 
 
 
 
5
 
Lostock Site Aerial
 
 
 
 
6
 
Lostock SEP:  Project Overview
 
 
 
 
 
7
 
Lostock SEP Project
 
 
 
Power Upgrade Variation Application
 
 
 
 
 
8
 
Power Upgrade Variation Application
 
Background
 
As previously reported, technical studies conclude that the electrical power output
the plant could deliver to the national grid could be increased.
 
Proposal developed for an electrical power increase of up to a further 30 MWe
This increase is delivered :
Without change in any of the parameters permitted under the existing
consent granted by the Secretary of State on 2
nd
 October 2012 for
construction and operation of a EFW station generating up to 60 MWe
Enabled by efficiency improvements since consent was granted.
 
Special Local Liaison Committee meeting held on 15
th
 March with Chris LeCointe,
RPS, in attendance
Information leaflet and CD provided to allow local information sharing
and opportunity to ask questions.
 
 
 
 
 
 
 
9
 
Power Upgrade Variation Application
 
Progress Update
 
A Variation Application was formally submitted to DBEIS seeking to vary the 2012
Consent to increase the power output of the Plant from the currently consented 60
MW to up to 90 MW.
 
DBEIS provided notice to TATA under Regulation 4(6) of the Variation Regulations
that it considers the Variation Application to be suitable for publication.
 
TATA consequently published notice in accordance with Regulation 5(3) & (5) of the
Variation Regulations on Thursday 2
nd
 and 9
th
 August 2018.
Application documents made available for inspection:
 On SEP website: 
www.lostockpower.co.uk
At Northwich Library and at CWACC, Wyvern House, Winsford
Representations on the Variation Application were invited until 7
th
 September
2018.  Statutory consultation concluded on 4
th
 October
 
 
 
 
 
 
 
10
 
Power Upgrade Variation Application
 
Progress Update (2)
 
Statutory Consultees included: Cheshire West and Chester Council and the
Environment Agency
 
TATA has, via RPS responded to DBEIS on the points raised in the representations
received.
 
The redacted representations and TATA’s response are now uploaded to the SEP
website: 
lostockpower.co.uk
 .
DBEIS will consider the Variation Application and representations received and may
consent to vary the 2012 Consent or may refuse to vary the consent.
 
 
 
 
 
 
 
11
 
Power Upgrade Variation Application
 
Progress Update (2)
 
Three main themes within the representations received for the variation
application:
Fuel type
HGV Movements
Air Quality Impact
 
Fuel Type – Pre-treated waste and C&I was as dictated within Condition 31 and
Condition 32.
 
HGV movements – as Condition 9 within the Planning Consent
 
BEIS assessed that the impact of the proposed variation and determined that no
EIA was required as it was unlikely to have a significant impact.
 
 
 
 
 
 
 
12
 
Lostock SEP Project
 
 
 
Update on Site Works Since Last Meeting
 
 
 
 
 
13
 
Work Activities Since Last Meeting
 
Asbestos Removal
Specialist contractor working on site removing asbestos within the two main
redundant power station buildings.
Expect to complete site works Quarter 1 of 2019.
 
Site Surveys
 
GPR survey of the entire site
Drain service CCTV survey
Bird netting of the power station buildings
 
Detailed Design of Enabling Work activities
 
Detailed design of the new water treatment plant and electrical sub-station being
progressed.  Aim to build and commission next year
 
Design specification for tie-ins.  Aim to be completed in new year
 
 
 
 
 
 
 
 
 
14
 
Lostock SEP Project
 
 
 
Proposed Work Activities Over Next 3 to 6 Months
 
 
 
15
 
Work Activities in Next 3 to 6 Months
 
Installation of temporary workshops, amenities, offices and laboratory
Ground preparation for temporary facilities
Provision of required services
Demolish existing structures to make land areas available for the
commencement of construction activities
 
Commence civil works for the new water purification plant and the new electrical
sub-station
 
Complete identified tie-ins to allow water treatment plant to be commissioned
 
Commence demolition of sections of the redundant power station buildings
 
Submit planning applications for new Office block and workshops
 
Prepare areas for the construction of the new office block and workshops.
 
Environmental Permitting
Conclude with Environment Agency the TATA and LSEP permit boundaries
 
 
 
 
 
 
 
 
 
 
 
 
 
 
16
 
Lostock SEP Project
 
 
 
Subsequent Project Works
 
 
 
17
 
Lostock SEP: Subsequent Project Works
 
 
Efforts during early 2019 will largely focus on:
Commence demolition of the old coal fired power station buildings
 
Relocation of services to allow construction works to commence later in the
year.
 
 
 
 
 
18
 
Lostock SEP: Date of Next Meeting
 
Proposed Dates for Future Meetings:
 
Thursday 28
th
 February 2019
Thursday 23
rd
 May 2019
Thursday 12
th
 September 2019
Thursday 28
th
 November 2019
 
 
 
 
 
 
19
 
Lostock SEP Project
 
AOB
 
 
 
Slide Note
Embed
Share

The Lostock Sustainable Energy Plant (SEP) held a Local Liaison Committee meeting discussing a proposed power upgrade, site works, project overview, and power variation application. The meeting included site rules, history, and an aerial view of the plant. An application for an electrical power increase was submitted, aiming for a further 30 MWe without changing existing parameters. The progress update highlighted the formal submission for varying the 2012 Consent. The meeting provided information sharing and an opportunity for questions.

  • Energy plant
  • Local liaison committee
  • Power upgrade
  • Project overview
  • Sustainable energy

Uploaded on Oct 05, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. 2.jpg Lostock Sustainable Energy Plant (SEP) Local Liaison Committee 29th November 2018

  2. 2.jpg AGENDA Welcome & Introductions Proposed Power Upgrade Application Update on Site Works Since Last Meeting Proposed Work Activities in Next 3 to 6 Months Subsequent Project Works Date of Next Meeting AOB 2

  3. 2.jpg Welcome & Lostock Site Rules Welcome to the seventh Lostock SEP Local Liaison Committee Office Rules TATA representative will act as Guardian No fire alarm test planned for today. If alarm sounds follow Guardian to muster point in staff car park at the rear of the building Toilet facilities on this floor Smoking Prohibited in the office. 3

  4. 2.jpg Project Overview Lostock Site History and Overview Lostock Site commenced soda ash production in 1907; Brunner Mond (now TATA Chemicals Europe Ltd) acquired the site in 1904. Demolished and rebuilt new manufacturing plant. Soda ash produced from brine (NaCl) and carbon dioxide (CO2) Brine supplied from the Holford salt cavities operated by Inovyn Carbon dioxide produced from the thermal decomposition of limestone with coke. Limestone railed in from Buxton Ammonia is used as a catalyst (pH conditioner) to assist the chemical reaction Soda Ash production is energy (heat) intensive. Steam required to drive the chemical reactions and dry the product. The site operated its own coal fired power station (six boilers) up to the year 2000. Decommissioned when new gas fired CHP power plant started at Winnington 4

  5. 2.jpg Lostock Site Aerial 5

  6. 2.jpg Lostock SEP: Project Overview 6

  7. 2.jpg Lostock SEP Project Power Upgrade Variation Application 7

  8. 2.jpg Power Upgrade Variation Application Background As previously reported, technical studies conclude that the electrical power output the plant could deliver to the national grid could be increased. Proposal developed for an electrical power increase of up to a further 30 MWe This increase is delivered : Without change in any of the parameters permitted under the existing consent granted by the Secretary of State on 2nd October 2012 for construction and operation of a EFW station generating up to 60 MWe Enabled by efficiency improvements since consent was granted. Special Local Liaison Committee meeting held on 15th March with Chris LeCointe, RPS, in attendance Information leaflet and CD provided to allow local information sharing and opportunity to ask questions. 8

  9. 2.jpg Power Upgrade Variation Application Progress Update A Variation Application was formally submitted to DBEIS seeking to vary the 2012 Consent to increase the power output of the Plant from the currently consented 60 MW to up to 90 MW. DBEIS provided notice to TATA under Regulation 4(6) of the Variation Regulations that it considers the Variation Application to be suitable for publication. TATA consequently published notice in accordance with Regulation 5(3) & (5) of the Variation Regulations on Thursday 2nd and 9th August 2018. Application documents made available for inspection: On SEP website: www.lostockpower.co.uk At Northwich Library and at CWACC, Wyvern House, Winsford Representations on the Variation Application were invited until 7th September 2018. Statutory consultation concluded on 4th October 9

  10. 2.jpg Power Upgrade Variation Application Progress Update (2) Statutory Consultees included: Cheshire West and Chester Council and the Environment Agency TATA has, via RPS responded to DBEIS on the points raised in the representations received. The redacted representations and TATA s response are now uploaded to the SEP website: lostockpower.co.uk . DBEIS will consider the Variation Application and representations received and may consent to vary the 2012 Consent or may refuse to vary the consent. 10

  11. 2.jpg Power Upgrade Variation Application Progress Update (2) Three main themes within the representations received for the variation application: Fuel type HGV Movements Air Quality Impact Fuel Type Pre-treated waste and C&I was as dictated within Condition 31 and Condition 32. HGV movements as Condition 9 within the Planning Consent BEIS assessed that the impact of the proposed variation and determined that no EIA was required as it was unlikely to have a significant impact. 11

  12. 2.jpg Lostock SEP Project Update on Site Works Since Last Meeting 12

  13. 2.jpg Work Activities Since Last Meeting Asbestos Removal Specialist contractor working on site removing asbestos within the two main redundant power station buildings. Expect to complete site works Quarter 1 of 2019. Site Surveys GPR survey of the entire site Drain service CCTV survey Bird netting of the power station buildings Detailed Design of Enabling Work activities Detailed design of the new water treatment plant and electrical sub-station being progressed. Aim to build and commission next year Design specification for tie-ins. Aim to be completed in new year 13

  14. 2.jpg Lostock SEP Project Proposed Work Activities Over Next 3 to 6 Months 14

  15. 2.jpg Work Activities in Next 3 to 6 Months Installation of temporary workshops, amenities, offices and laboratory Ground preparation for temporary facilities Provision of required services Demolish existing structures to make land areas available for the commencement of construction activities Commence civil works for the new water purification plant and the new electrical sub-station Complete identified tie-ins to allow water treatment plant to be commissioned Commence demolition of sections of the redundant power station buildings Submit planning applications for new Office block and workshops Prepare areas for the construction of the new office block and workshops. Environmental Permitting Conclude with Environment Agency the TATA and LSEP permit boundaries 15

  16. 2.jpg Lostock SEP Project Subsequent Project Works 16

  17. 2.jpg Lostock SEP: Subsequent Project Works Efforts during early 2019 will largely focus on: Commence demolition of the old coal fired power station buildings Relocation of services to allow construction works to commence later in the year. 17

  18. 2.jpg Lostock SEP: Date of Next Meeting Proposed Dates for Future Meetings: Thursday 28th February 2019 Thursday 23rd May 2019 Thursday 12th September 2019 Thursday 28th November 2019 18

  19. 2.jpg Lostock SEP Project AOB 19

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#