Long-term Operation of Superconducting Triplet Quadrupoles (STQ) with Cryocoolers at RIKEN

 
Introduction
 
BigRIPS & BI-beam Delivery line
 
STQ with cryocoolers
 
Operational Experiences
Maintenance
Long-term Operation of Cryocoolers
Troubles
 
Long-term Operation of the
Superconducting Triplet Quadrupoles (STQ)
with Cryocoolers
for BigRIPS In-flight Separator at RIKEN
 
KUSAKA Kensuke
RIKEN Nishina Center, BigRIPS Team
Contents
 
Introduction
 
Standard Operation of
SC Magnets
 
Thermal
 Cycle Operation
 
Operation of SC Magnets with Cryocoolers
 
Repeat . . . .
 
Never warm up SC magnet
 
Continuous operation of cryocoolers
 
longer than 10 years
 
BigRIPS and RI-beam Delivery Lines
 
Unique large aperture (ID 240mm) 100m-long Beam Lines
 
STQ18 on circular motion stage
 
No Transfer Line needed
 
Flexible in beam-line design
 
STQ18 is used in 2 beam lines
STQ with Cryocoolers
 
consists of 22 
“Stand-alone”
Superconducting Triplet Quadrapoles
 
STQ Magnet Specification
 
Conservative LTS Quads
 
Q500
 
Q500
 
Q800/Q1000
 
Superferric
 
Triplet in single cryostat
 
Flat Racetrack Coil
 
NbTi
 
LHe bath cooling
 
STQ with Cryocoolers
 
HTSC PLs
 
4K Cooler
 
Shield & PL Cooler
 
GM/JT cooler
2.5W@4.3K
 
Single-stage GM cooler
 90W@80K
 
Small Heat Load  < 2W
 
Large Cold Mass  ~10 ton
 
SHI CG308
 
SHI CG110
 
 He Vessel
 LHe ~500 L
 
Cryocooler with Gas Driven Displacer
 
Key of Cold Maintenance
 
room-temp. displacer can be put
in cold cylinder
 
Unique Thermal Cycle operation
 
Precooling
 
Room T (~300K) to 80 K
 
80 K to 4.5 K
 
GM/JT Cooler
Mounting
after  precooling
 
2005 ~ 2006
Continuous
Operation
of
Cryocoolers
 
Transferring liquid N
from CE tank
 
3000 ~ 4000 L
 
Transferring liquid He
from Dewar
 
~ 2000 L
 
Operation of Cryocoolers & STQ
 
Pressure of He
 
vessel
 
Kept in 7 ~8 kPaG
 
> P 
atmospheric
 
Heater in vessel
2W)
 
ON/OFF control
 
P
 
Back-Up of Electric Power & Cooling Water
 
Heater Output
 
Regular maintenance of Cryocoolers (yearly)
 
2007 ~ Present
 
Cooling capacity of GM/JT cooler (2.5W)
 
Fine tuning by JT valve (once ~ twice /year)
6500 kW-
Power 
C
lass
Gas Turbine
Cogeneration
 
Electric Power -> RIBF CGS & TEPCO
 
2 independent Cooling Water Systems
 
Spare Cryocoolers
   & Compressors
 
Excitation of Magnets
 
PL temp. interlock  < 70K
 
LHe level interlock  > 80%
 
He loss occurs when P > 20 kPaG
 
Cracking Pressure of safety check valve
 
Cryocooler Maintenance
 
Displacer Replacement
JT-circuit flushing
 
GM
 
Cooler Maintenance
Cold Maintenance
 
helium-purged gas bag
 
Exchange displacers
 
GM/JT
 
Cooler Maintenance
 
Till 2008
 
warm maintenance
 
Magnets in Cold State
 
Well-established by
Cryocooler maintainers
 
From 2009 to present
 
Heater-bar maintenance
 
2. JT-flushing with heater
   in Exp. displacer cylinder
 
without dismount GM/JT cooler from cryostat
 
1. Take out cold displacer
 
3. Insert new displacer
 
70~80 L of He loss
 
 less than 10 L of He loss
 
A Long-term Trend of Temperatures, LHe levels, etc.
 
e.g.  STQ7 (from Jan. 2008 to Jul. 2018)
 
PL & GM head Temperature
 
Scheduled (yearly) Maintenances
 
 by blocked gas flow in displacer
 
Constant LHe Level  & well-cooled (< 70K) PL Temp.
 
Safe excitation of Magnets
 
Discharge & Suction Pressures of GM comp.
 
GM cooler degradation
 
LHe Level, Shield Temp., excess cooling capacity (ave. heater output 
P
)
 
Rise of GM head, PLs & Shield Temp.
 
e.g.  STQ17 (from Jan. 2008 to Jul. 2018)
 
Unexpected rapid rises of GM head Temp.
 
Scheduled (yearly) Maintenances
 
flushing comp.
 
Rapid Increase
 
Degradation of cooling capacity of  GM/JT cooler
 
GM/JT cooler replaced
JT-circuit blockage
T
4K
 ~ 4.75K (4.3~4.5K)
Temp. of Expander Head
T
exp
 ~ 16 K  (<14K)
 
Unscheduled maintenances
 
Cooling capacity recovered  after warm-up
 
He loss,  p
vessel
 > 20 kpaG
 
A Long-term Trend of Temperatures, LHe levels, etc.
 
Unscheduled Maintenance of GM coolers
 & replaced GM/JT coolers
 
operation time
from last maintenance
 
1,200~6,700 h
 
Unscheduled Maintenances
of GM coolers
 
T
JT
  4.3 ~ 4.5 K
 
T
exp
  < 14K
 
Normal temp. of GM/JT cooler
 
Few hours beam time stops
 
Replaced (deteriorated) GM/JT coolers
 
Hardware failures
 
GM compressor (STQ14)   
 
t
op
  60,086 h
 
Schematic Diagram of GM/JT cooler system
 
Gass flow
 
decreased 20%,  (Oil SP,  P-control valve )
 
GM/JT compressor (STQ24)   
 
t
op
  17,245 h
 
Malfunction of Exp. Rotary Comp. (foreign substance)
 
Whole Unit
Replaced
 
Exp. Comp
Replaced
 
GM/JT compressor (STQ11)   
 
t
op
  71,775 h
 
Many sudden Stops (PLC error)
 
Aging deterioration of sensors
 
(P-sensor in HP line)
 
sudden stop of comp.
 
GM/JT comp.
 
GM comp.
 
STQ16 t
op
  70,087 h
STQ11 t
op
  82,448 h
STQ20 t
op
  100,023 h
STQ21 t
op
  100,563 h
 
STQ23 t
op
  89,603 h
STQ6   t
op
  103,855 h
 
PLC Replaced
 
JT valve of GM/JT cooler
 
STQ18 t
op
  69,190 h
STQ19 t
op
  78,737 h
 
cold head T didn’t change
 
JT valve Replaced
 
Summary & Conclusion
 
We have developed STQ with Cryocoolers
We improved the maintenance of GM/JT coolers
Heater bar maintenance to reduces He loss
We operate 22 STQ systems for more than 10 years
without warming up magnets.
Yearly maintenance is essential to avoid degradation of
cooling capacity.
Unexpected rise of GM head temperature is under
investigation. (impurity of coolant gas He)
Hardware failures by aging are becoming noticeable.
Preparing spare coolers & compressors are essential.
Solid infrastructure (electric power & cooling water) is
important for long-term operation.
 
SRC
 
IRC
 
SAMURAI
 
100m-long beam lines formed by
Stand-alone Superconducting Quads
 
5 STQ cooled by
Cryogenic Plant
 
RIBF Cryogenics
BigRIPS
1
st
 Stage
 
Linde TCF200
 
Linde TCF50S
 
Charactorized by
Beam Heat load
to Cryogenic System
 
22 STQ’s
Cooled by Cryocoolers
 
SHI CG308
 
Large Heat Load Fluctuation!
 
3T 880mm-gap
Superconducting Dipole
Cooled by Cryocoolers
 
He Loss during maintenance
1.5day
 
Blow to reduce P of He vessel
Stop of compressor longer than 30h
 
Compressor Stop
& Dismount cryocooler
 
Mount &
Restart compressor
P [kPaG]
 
Check valve
P 
Relief
 
 
=3psi
 
LHe
 
Loss
Level 82% -> 59%
    
~60L
 
70~100L of LHe transfer / 1 STQ
 
24h warm-up for JT flushing
 
STQ14 4K ref.
 
He vessel Pressure during maintenance
 
Level 87% -> 85%
LHe Loss
~ 
Few L
 
50~70L of  LHe transfer / STQ in 2~3 years
 
STQ17
 
Heater-bar maintenance
 
JT flushing without dismounting
cryocooler from cryostat
 
Warm-up JT circuit by heater-bar
in Expander Cylinder
 
~5h
 
Compressor
Stop
 
Restart
 
Improvement of GM/JT Cooler Maintenance II
P [kPaG]
 
Save ~ 1000L of LHe  / year !
Slide Note
Embed
Share

Introduction to the operational experiences, maintenance, and long-term operation of the Superconducting Triplet Quadrupoles (STQ) with cryocoolers for the BigRIPS In-flight Separator at RIKEN. Details include standard operation of SC magnets, unique features of BigRIPS and RI-beam delivery lines, STQ magnet specifications, cryocooling system with shields and PL coolers, precooling process, and the continuous operation of cryocoolers with STQ from 2007 to the present.

  • RIKEN
  • Superconducting
  • Cryocoolers
  • BigRIPS
  • Triplet Quadrupoles

Uploaded on Sep 18, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Long-term Operation of the Superconducting Triplet Quadrupoles (STQ) with Cryocoolers for BigRIPS In-flight Separator at RIKEN Contents KUSAKA Kensuke Introduction RIKEN Nishina Center, BigRIPS Team BigRIPS & BI-beam Delivery line STQ with cryocoolers Operational Experiences Maintenance Long-term Operation of Cryocoolers Troubles

  2. Introduction Standard Operation of SC Magnets Fabrication Thermal Cycle Operation Operation of SC Magnets with Cryocoolers Excitation Maintenance Excitation Maintenance Cold Repeat . . . . Cold Never warm up SC magnet Continuous operation of cryocoolers longer than 10 years

  3. BigRIPS and RI-beam Delivery Lines Unique large aperture (ID 240mm) 100m-long Beam Lines consists of 22 Stand-alone Superconducting Triplet Quadrapoles STQ with Cryocoolers No Transfer Line needed Flexible in beam-line design STQ18 on circular motion stage STQ18 is used in 2 beam lines

  4. STQ Magnet Specification Q500/Q800/Q100 Field gradient [T/m] 14.1 1.15 Conductor size [mm] Cu/super ratio 6.5 # of turns 1405 Ic/Iop 3.5 NbTi Nominal current [A] 142 / 137 / 135 Flat Racetrack Coil Superferric Current density [A/ mm2] 115 / 110 / 109 Stored energy [MJ] Q500/Q800/Q100 0.13 / 0.19 / 0.27 Q500 Effective length [m] ~ 0.54 / ~0.84 / ~1.04 Q800/Q1000 Q500 Pole-tip dia. [mm] 340 240 Warm bore dia. [mm] Length of iron [mm] OD of yoke [mm] 440 / 740 / 940 960 Triplet in single cryostat LHe bath cooling Total Cold mass ~ 9.4/10.2 tons Conservative LTS Quads

  5. STQ with Cryocoolers Shield & PL Cooler 4K Cooler GM/JT cooler 2.5W@4.3K Single-stage GM cooler 90W@80K SHI CG110 SHI CG308 HTSC PLs Cryocooler with Gas Driven Displacer Key of Cold Maintenance room-temp. displacer can be put in cold cylinder He Vessel LHe ~500 L Small Heat Load < 2W Large Cold Mass ~10 ton Unique Thermal Cycle operation

  6. Precooling 2005 ~ 2006 Room T (~300K) to 80 K 80 K to 4.5 K Continuous Operation of Cryocoolers Transferring liquid He from Dewar Transferring liquid N from CE tank GM/JT Cooler Mounting after precooling ~ 2000 L 3000 ~ 4000 L

  7. Operation of Cryocoolers & STQ 2007 ~ Present Pressure of He vessel Kept in 7 ~8 kPaG Heater in vessel 2W) > P atmospheric ON/OFF control P Heater Output Cooling capacity of GM/JT cooler (2.5W) Fine tuning by JT valve (once ~ twice /year) Excitation of Magnets PL temp. interlock < 70K LHe level interlock > 80% He loss occurs when P > 20 kPaG Cracking Pressure of safety check valve Spare Cryocoolers & Compressors Back-Up of Electric Power & Cooling Water Electric Power -> RIBF CGS & TEPCO 2 independent Cooling Water Systems 6500 kW- Power Class Gas Turbine Cogeneration Regular maintenance of Cryocoolers (yearly)

  8. Cryocooler Maintenance Magnets in Cold State GM Cooler Maintenance Cold Maintenance Well-established by Cryocooler maintainers helium-purged gas bag Exchange displacers GM/JT Cooler Maintenance Displacer Replacement JT-circuit flushing Heater-bar maintenance without dismount GM/JT cooler from cryostat 1. Take out cold displacer 2. JT-flushing with heater in Exp. displacer cylinder 3. Insert new displacer From 2009 to present less than 10 L of He loss Till 2008 70~80 L of He loss warm maintenance

  9. e.g. STQ7 (from Jan. 2008 to Jul. 2018) A Long-term Trend of Temperatures, LHe levels, etc. PL & GM head Temperature Discharge & Suction Pressures of GM comp. GM cooler degradation Rise of GM head, PLs & Shield Temp. by blocked gas flow in displacer Scheduled (yearly) Maintenances LHe Level, Shield Temp., excess cooling capacity (ave. heater output P) Constant LHe Level & well-cooled (< 70K) PL Temp. Safe excitation of Magnets

  10. A Long-term Trend of Temperatures, LHe levels, etc. e.g. STQ17 (from Jan. 2008 to Jul. 2018) Unexpected rapid rises of GM head Temp. Rapid Increase Unscheduled maintenances flushing comp. Scheduled (yearly) Maintenances Degradation of cooling capacity of GM/JT cooler Temp. of Expander Head Texp~ 16 K (<14K) JT-circuit blockage T4K~ 4.75K (4.3~4.5K) He loss, pvessel> 20 kpaG Cooling capacity recovered after warm-up GM/JT cooler replaced

  11. Unscheduled Maintenance of GM coolers & replaced GM/JT coolers Unscheduled Maintenances of GM coolers Replaced (deteriorated) GM/JT coolers Year STQ system Date of Stop Operation time from maintenance (total) Reason 2008 STQ17 May 2011 6,476 (38,773) h TJT~ 4.8K 2009 STQ8 STQ17 Jun 2012 6,719 (47,913) h Texp~ 16K 2010 STQ8, STQ11 STQ13 Mar 2013 5,113 (69,439) h Texp~ 23K 2011 STQ9 STQ15 Nov 2014 1,518 (82,003) h Texp~ 18K 2012 STQ6, STQ8, STQ9, STQ14, STQ18 STQ10 Nov 2014 1,855 (83,017) h Texp~ 17K 2013 STQ16 STQ11 Jun 2017 5,983 (106,985) h TJT~ 4.6K 2014 Texp< 14K 2015 STQ17 Normal temp. of GM/JT cooler TJT4.3 ~ 4.5 K 2016 STQ9, STQ10, STQ25 2017 STQ21 operation time from last maintenance 1,200~6,700 h Few hours beam time stops

  12. Hardware failures GM/JT compressor (STQ24) top17,245 h Malfunction of Exp. Rotary Comp. (foreign substance) Exp. Comp Replaced GM compressor (STQ14) top60,086 h Gass flow decreased 20%, (Oil SP, P-control valve ) Whole Unit Replaced GM/JT compressor (STQ11) top71,775 h Many sudden Stops (PLC error) JT valve of GM/JT cooler cold head T didn t change PLC Replaced STQ18 top69,190 h STQ19 top78,737 h JT valve Replaced Schematic Diagram of GM/JT cooler system Aging deterioration of sensors sudden stop of comp. (P-sensor in HP line) P-cntrl valve P-cntrl valve Expander Surge Tank check valve Ballast Tank ADS ADS GM/JT comp. STQ16 top70,087 h STQ11 top82,448 h STQ20 top100,023 h STQ21 top100,563 h JT Tuner (Micrometer) 1stStage JT EX (1st) 2ndStage Oil SP Oil SP JT EX (2nd) JT valve JT EX (3rd) GM comp. STQ23 top89,603 h STQ6 top103,855 h Comp Comp Comp Adsorber Re-condensing Exchanger

  13. Summary & Conclusion We have developed STQ with Cryocoolers We improved the maintenance of GM/JT coolers Heater bar maintenance to reduces He loss We operate 22 STQ systems for more than 10 years without warming up magnets. Yearly maintenance is essential to avoid degradation of cooling capacity. Unexpected rise of GM head temperature is under investigation. (impurity of coolant gas He) Hardware failures by aging are becoming noticeable. Preparing spare coolers & compressors are essential. Solid infrastructure (electric power & cooling water) is important for long-term operation.

  14. RIBF Cryogenics 100m-long beam lines formed by Stand-alone Superconducting Quads 22 STQ s IRC Cooled by Cryocoolers Linde TCF200 SRC BigRIPS 1stStage SHI CG308 SAMURAI 5 STQ cooled by Cryogenic Plant Charactorized by Beam Heat load to Cryogenic System 3T 880mm-gap Superconducting Dipole Cooled by Cryocoolers Large Heat Load Fluctuation! Linde TCF50S

  15. He Loss during maintenance STQ14 4K ref. Check valve P Relief =3psi P [kPaG] 24h warm-up for JT flushing LHe Loss Level 82% -> 59% ~60L 1.5day Compressor Stop & Dismount cryocooler Mount & Restart compressor Blow to reduce P of He vessel Stop of compressor longer than 30h 70~100L of LHe transfer / 1 STQ

  16. Improvement of GM/JT Cooler Maintenance II Heater-bar maintenance JT flushing without dismounting cryocooler from cryostat He vessel Pressure during maintenance Warm-up JT circuit by heater-bar in Expander Cylinder Level 87% -> 85% LHe Loss ~ Few L Compressor ~5h P [kPaG] Stop STQ17 Restart 50~70L of LHe transfer / STQ in 2~3 years Save ~ 1000L of LHe / year !

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#