Facilities Master Plan Implementation Update and Parking Garage Scoring

undefined
 
Facilities Master Plan Implementation:
Update to Strategic Council
 
Erik Skinner
Vice President, Administrative Services
February 1, 2019
 
Major Developments
 
Draft EIR
Advisory Groups
Parking Garage
New Instructional Building
 
CEQA PROCESS: DRAFT EIR
 
Public comment has ended
Developing responses
Take to the Board in April for
review and May for action
 
ADVISORY GROUPS
 
FMP Task Force
Programming Teams
Project Teams
Campus Forums
 
Parking Garage Scoring
 
Proposals scored by 8 
District representatives (Facilities,
Finance, FMP Architect, and Program 
staff)
 
Assistance provided by technical advisors (Program
Manager, District procurement team)
 
Using scoring rubric defined in RFP
 
Unanimous agreement on McCarthy as best value proposal
 
 
5
 
Parking Garage Scoring
 
 
6
 
Strengths of McCarthy Proposal
 
Cost
—roughly $4.5M below our estimated cost and
$3.25M below next lowest bid.
 
Technical Evaluation
—impressive experience as a DBE
and parking garage builder; well-developed
management plan for subcontractors and construction
site; self-perform the cast-in-place work.
 
Life-Cycle Cost
—cast-in-place construction allows for
a more open design, less maintenance (caulking,
lighting), and lower energy consumption (lighting).
 
7
 
Next Steps
 
Design begins
           
March 2019
Complete CEQA process (adopt EIR and mitigations)
 
May 2019
Obtain Permits:
Corps of Engineers
         
Summer 2019
Regional Water Agency
        
Summer 2019
Department of Fish and Wildlife
      
Fall 2019
DSA
             
Fall 2019
Construction begins
          
November 2019
Project complete
          
Spring 2021
 
8
 
    
 
Questions?
Slide Note
Embed
Share

Update presented to the Strategic Council by Erik Skinner, Vice President of Administrative Services, on the Facilities Master Plan Implementation progress, including major developments, CEQA process, advisory groups involvement, parking garage scoring, strengths of McCarthy proposal, and next project steps towards completion by Spring 2021.

  • Facilities
  • Master Plan
  • Implementation
  • Update
  • Strategic Council

Uploaded on Sep 14, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Facilities Master Plan Implementation: Update to Strategic Council Erik Skinner Vice President, Administrative Services February 1, 2019

  2. Major Developments Draft EIR Advisory Groups Parking Garage New Instructional Building

  3. CEQA PROCESS: DRAFT EIR Public comment has ended Developing responses Take to the Board in April for review and May for action

  4. ADVISORY GROUPS FMP Task Force Programming Teams Project Teams Campus Forums

  5. Parking Garage Scoring Proposals scored by 8 District representatives (Facilities, Finance, FMP Architect, and Program staff) Assistance provided by technical advisors (Program Manager, District procurement team) Using scoring rubric defined in RFP Unanimous agreement on McCarthy as best value proposal 5

  6. Parking Garage Scoring Total Proposal Price (Final GMP) Design Build Entity Rank Score McCarthy Building Companies, Inc. 1 94.56 / 100 $39,300,083 Clark Pacific 2 89.15 / 100 $42,555,013 Otto Construction 3 80.73 / 100 $52,080.000 6

  7. Strengths of McCarthy Proposal Cost roughly $4.5M below our estimated cost and $3.25M below next lowest bid. Technical Evaluation impressive experience as a DBE and parking garage builder; well-developed management plan for subcontractors and construction site; self-perform the cast-in-place work. Life-Cycle Cost cast-in-place construction allows for a more open design, less maintenance (caulking, lighting), and lower energy consumption (lighting). 7

  8. Next Steps Design begins March 2019 Complete CEQA process (adopt EIR and mitigations) May 2019 Obtain Permits: Corps of Engineers Summer 2019 Regional Water Agency Summer 2019 Department of Fish and Wildlife Fall 2019 DSA Fall 2019 Construction begins November 2019 Project complete Spring 2021 8

  9. Questions?

More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#