Challenges Faced During Foster Wheeler Steam Boiler Moving Day

 
20 October 2016
Foster Wheeler 1200 LB Steam Boiler
 
1
 
2
 
3
 
4
 
5
 
6
 
7
 
8
 
9
 
10
 
ALL GONE
 
11
 
Boiler Moving Day
22 October 2016
 
Started at 0630 leaving SWOS and
arrived at pier 1100
 
12
 
Last measurement 22 ft. 3 in.
 
13
 
Over the bridge
 
14
 
First major hurdle
 
15
 
Over 4 in cable
 
16
 
Can’t make it over the 4 in cable
 
17
 
Still can’t make it over the cable
 
18
 
4 in. cable
 
19
 
Back up and try again
 
20
 
Lift 4 in. cable
 
21
 
Three hours later, approaching pier;
Verizon life truck ran out of fuel (can’t make this stuff
up) and could not get under last set of wires.
 
22
 
Approaching pier
 
23
 
Barge and tug waiting
 
24
 
Arrived at pier
 
25
 
Removing Tarp
 
26
 
Ready for lift
 
27
 
95,000 lb lift
 
28
 
29
 
30
 
Over barge 1100
 
31
 
Closing remarks
 
Towed to Quonset Point (Reagan
Construction) awaiting favorable weather.
Barge schedule to depart for MMA on
Wednesday.  Estimate travel time is 12 hours.
 
32
Slide Note
Embed
Share

During the process of moving a 1200 LB steam boiler by Foster Wheeler, several challenges were encountered. The journey started on 22nd October 2016 and faced obstacles such as overcoming a 4-inch cable hindrance. Despite setbacks, the team persevered and eventually succeeded in transporting the boiler to its destination. The experience highlights the complexities involved in industrial equipment relocation.

  • Challenges
  • Steam Boiler
  • Foster Wheeler
  • Moving Day
  • Industrial Equipment

Uploaded on Oct 10, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. 20 October 2016 Foster Wheeler 1200 LB Steam Boiler 1

  2. 2

  3. 3

  4. 4

  5. 5

  6. 6

  7. 7

  8. 8

  9. 9

  10. 10

  11. ALL GONE 11

  12. Boiler Moving Day 22 October 2016 Started at 0630 leaving SWOS and arrived at pier 1100 12

  13. Last measurement 22 ft. 3 in. 13

  14. Over the bridge 14

  15. First major hurdle 15

  16. Over 4 in cable 16

  17. Cant make it over the 4 in cable 17

  18. Still cant make it over the cable 18

  19. 4 in. cable 19

  20. Back up and try again 20

  21. Lift 4 in. cable 21

  22. Three hours later, approaching pier; Verizon life truck ran out of fuel (can t make this stuff up) and could not get under last set of wires. 22

  23. Approaching pier 23

  24. Barge and tug waiting 24

  25. Arrived at pier 25

  26. Removing Tarp 26

  27. Ready for lift 27

  28. 95,000 lb lift 28

  29. 29

  30. 30

  31. Over barge 1100 31

  32. Closing remarks Towed to Quonset Point (Reagan Construction) awaiting favorable weather. Barge schedule to depart for MMA on Wednesday. Estimate travel time is 12 hours. 32

More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#