Airport Construction Delivery Methods Comparison

 
Operations/Construction/Planning
 
Duluth International Airport
ATCT Architecture and Engineering RFQ Update
ATCT Construction Delivery Method
2023 Construction Season Update
VMS Software Change Over
 
Duluth Sky Harbor Airport
Airport Terminal Program – Sky Harbor Airport Terminal Design
 
Design - Build
 
A single entity who controls all aspects of design and construction.
 
Pros:
Faster overall timeline to completion
Design -> Construction Autonomy
Efficient Communication
Can see cost savings
Construction can start before final
design is complete
 
Cons:
Longer design time
Cannot have a separate construction
company oversee construction
Greater risk of change orders
Less control once a GMP has been
agreed too
Too many unknowns with the FAA
Overall new to airport industry
 
Construction Manager at Risk (CMAR)
 
A construction manager hired by the owner to complete design and construction
under a Guaranteed Maximum Price (GMP)
 
Pros:
Most of the time accompanied by a
GMP
Can see cost savings
Transfer of risk from owner to CM
 
 
Cons:
Longer design time
Too many unknowns with the FAA
Less control once a GMP has been
agreed too
Potential conflicts as CM is also the
GC.
 
Design - Bid - Build
 
Firm that designs a project, puts it out for bid, and then hires GC/CMA to complete
construction.
 
Pros:
Traditional and familiar to the DAA
Greatest speed during design phase
Greatest flexibility during design
phase
Designer will oversee construction
through completion
 
 
 
Cons:
A longer process overall
No contractor input in design
 
Why Did the DAA Choose
Design-Bid-Build?
 
Too many unknowns at this point
Speed needed during the design phase
Most flexible to respond to guidance changes
Familiar to the DAA/FAA
 
Operations/Construction/Planning
 
Duluth International Airport
ATCT Architecture and Engineering RFQ Update
ATCT Construction Delivery Method
2023 Construction Season Update
VMS Software Change Over
 
Duluth Sky Harbor Airport
Airport Terminal Program – Sky Harbor Airport Terminal Design
 
 
 
Operations/Construction/Planning
 
Duluth International Airport
ATCT Architecture and Engineering RFQ Update
ATCT Construction Delivery Method
2023 Construction Season Update
VMS Software Change Over
 
Duluth Sky Harbor Airport
Airport Terminal Program – Sky Harbor Airport Terminal Design
Slide Note
Embed
Share

Explore different construction delivery methods such as Design-Build, Construction Manager at Risk (CMAR), and Design-Bid-Build for airport projects. Understand the pros and cons of each method to make informed decisions based on factors like timeline, cost savings, risk management, and control over the project.


Uploaded on Aug 15, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Operations/Construction/Planning Duluth International Airport ATCT Architecture and Engineering RFQ Update ATCT Construction Delivery Method 2023 Construction Season Update VMS Software Change Over Duluth Sky Harbor Airport Airport Terminal Program Sky Harbor Airport Terminal Design

  2. Design - Build A single entity who controls all aspects of design and construction. Pros: Cons: Faster overall timeline to completion Design -> Construction Autonomy Efficient Communication Can see cost savings Construction can start before final design is complete Longer design time Cannot have a separate construction company oversee construction Greater risk of change orders Less control once a GMP has been agreed too Too many unknowns with the FAA Overall new to airport industry

  3. Construction Manager at Risk (CMAR) A construction manager hired by the owner to complete design and construction under a Guaranteed Maximum Price (GMP) Pros: Cons: Most of the time accompanied by a GMP Can see cost savings Transfer of risk from owner to CM Longer design time Too many unknowns with the FAA Less control once a GMP has been agreed too Potential conflicts as CM is also the GC.

  4. Design - Bid - Build Firm that designs a project, puts it out for bid, and then hires GC/CMA to complete construction. Pros: Cons: Traditional and familiar to the DAA Greatest speed during design phase Greatest flexibility during design phase Designer will oversee construction through completion A longer process overall No contractor input in design

  5. Why Did the DAA Choose Design-Bid-Build? Too many unknowns at this point Speed needed during the design phase Most flexible to respond to guidance changes Familiar to the DAA/FAA

  6. Operations/Construction/Planning Duluth International Airport ATCT Architecture and Engineering RFQ Update ATCT Construction Delivery Method 2023 Construction Season Update VMS Software Change Over Duluth Sky Harbor Airport Airport Terminal Program Sky Harbor Airport Terminal Design

  7. Operations/Construction/Planning Duluth International Airport ATCT Architecture and Engineering RFQ Update ATCT Construction Delivery Method 2023 Construction Season Update VMS Software Change Over Duluth Sky Harbor Airport Airport Terminal Program Sky Harbor Airport Terminal Design

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#