An update on infrastructure projects in the Annual Performance Plan, including community-based tourism projects and maintenance of provincial tourism assets in the Eastern Cape. Details of progress, start dates, and expected end dates are provided for various nature reserves and lodges. Practical Completion (PC) achieved in some projects.


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.



Uploaded on Mar 04, 2024 | 0 Views


Presentation Transcript


  1. ANNEXURE - PROGRAMME 3 PROGRESS ON COMMUNITY AND MAINTENANCE PROJECTS AS REFLECTED IN THE ANNUAL PERFORMANCE PLAN

  2. INTRODUCTION An update on the implementation on progress is provided for various infrastructure projects in the Annual Performance Plan the following categories: Community Based Tourism Projects the bulk of which are the development or upgrading of accommodation facilities Maintenance of Provincial Tourism Assets - this work involves maintenance, beautification rehabilitation of terrain, landscaping, paving, painting, fencing, electrical,etc. and enhancement e.g. 2

  3. EASTERN CAPE (1) Implementing Agent and Projects DBSA Progress Provincial maintenance: state-owned assets 1. Thomas Baines Nature Reserve- Makana LM, Sarah Baartman DM 2. Double Mouth Nature Reserve Great Kei LM,Amathole DM 3. Oviston Nature Reserve Walter Sisulu LM, Joe Gqabi DM 4. Mpofu and Fordyce Nature Reserve Raymond Mhlaba LM, Amathole DM 5. Baviaanskloof Nature Reserve - Dr Beyers Naude LM,Sarah Baartman DM 6. Cwebe & Dwesa Nature Reserves 1. Thomas Baines Nature Reserve Progress is at 99% (Q1 70%). Project start date 2023-02-08 and expected end date 2023-08-08. 2. Double Mouth Nature Reserve PC* achieved. Project start date 2023-01-25 and expected end date 2023-07-06. 3. Oviston Nature Reserve Progress is at 99% (Q1 89%). Project start date 2023-01-25 and expected end date 2023-07-25. 4. Mpofu and Fordyce Nature Reserve Progress is at 28% (Q1 - 3%). Project start date 2023-06-02 and expected end date 2023-12-02. 5. Baviaanskloof Nature Reserve Progress is at 80% (Q1 - 41%). Project start date 2023-01-25 and expected end date 2023-09-30. 6. Cwebe & Dwesa Nature Reserve Progress is at 20% (Q1 3%). Project start date 2023-06-01 and expected end date is 2023-12-01. * PC: Practical Completions: project is completed - it is a short period to deal with snags before final certificates are issued 3

  4. EASTERN CAPE (2) Implementing Agent and Projects Progress DBSA Community-based tourism projects: 1. Maluti Hiking Trail, Matatiele Local Municipality (LM), Alfred Nzo District Municipality (DM) - Construction of 4 lappa s, 3 pedestrian bridges,fencing of accommodation sites. 1. Maluti Hiking Trail PC achieved (Q1 - 98 %). Project start date 2022-07-07 and expected end date 2023-07-07. 2. Mthonsi Lodge, Nkonkobe LM, Amathole DM - Construction of thirteen (13) chalets, 2 lappa s, staff accommodation, guard house, admin/restaurant building,backpackers and internal roads. 2. Mthonsi Lodge Progress is at 73% (Q1 - 40%). Project start date 2022-11-14 and expected end date 2023-11-14. 3. Qatywa Lodge, Mbhashe LM, Amathole DM - Construction of guard house, refuse area, 2 lappa s, laundry room, staff accommodation, fencing,conference building,restaurant,curio shop and parking area. 3. Qatywa Lodge Progress is at 48% (Q1 - 22%). Project start date 2023-01-16 and expected end date 2024-01-16. 4. Nyandeni Chalets , Nyandeni LM, OR Tambo DM - Construction of admin building, 4x 3bedroom construction of a guard house, staff accommodation, refuse room, internal walkways. 4. Nyandeni Chalets Progress is at 99% (Q1 - 75%). Project start date 2022-08-15 and expected end date 2023-08-15. chalets, 2x 2bedroom chalets, 5. Western Tembuland, Emalaheni LM, Chris Hani DM - Construction of conference facility, restaurant, guardhouse, museum, craft center, 14 chalets,parking area,walkways and construction of a swimming pool 5. Western Tembuland PC* achieved (Q1 - 95%). Project start date 2022-07-07 and expected end date 2023-07-07. * PC: Practical Completions: project is completed - it is a short period to deal with snags before final certificates are issued 4

  5. FREE STATE (1) ImplementingAgent and Project Progress DBSA Provincial state-owned assets: 1. Gariep Dam Resort - Umsobomvu LM, Pixley ka Seme DM 2. Maria Moroka Resort Mangaung Metropolitan Municipality 3. Phillip Saunders Resort - Mangaung Metropolitan Municipality 4. Sterkfontein Dam Nature Reserve - Maluti-a- Phofung LM,Thabo Mofutsanyana DM 1. Gariep Dam Resort Progress is at 90% (Q1 - 25%).Project start date 2023-03-14 and expected end date 2023-09-14. 2. Maria Moroka Resort - Progress is at 70% (Q1 - 39%). Project start date 2023-03-15 and expected end date 2023-09-15. 3. Phillip Saunders Resort Progress is at 70% (Q1 - 40%). Project start date 2023-02-15 and expected end date 2023-10-30 4. Sterkfontein Dam Nature Reserve Progress is at 99% (Q1 - 92%).Project start date 2023-02-14 and expected end date 2023- 09-21. DBSA Community-basedTourism Projects: 1. QwaQwa (Accommodation) - Maluti-a-Phofung LM, Thabo Mofutsanyana DM 2. Vredefort Dome Interpretation Centre, near Parys Ngwathe LM,Fezile Dabi DM 3. Monotsha, Phuthaditjhaba (paved access road)- Maluti-a-Phofung LM,Thabo Mofutsanyana DM Guest House, Phuthaditjhaba 1. QwaQwa Guest House Progress is at 98% (Q1 - 90%). Project start date 2022-09-17 and expected end date 2023-09-29. 2. Vredefort Dome Interpretation Centre Progress is at 37% (Q1 - 35%). Project start date 2022-10-17 and expected end date 2023- 10-17. 3. Monotsha paved access road Progress is at 99% (Q1 - 73%). Project start date 2022-09-17 and expected end date 2023-09-17. 5

  6. KWAZULU-NATAL (1) Implementing Agent and Projects DBSA Progress 1. Muzi Pan - Jozini LM,uMkhanyakude DM - Refurbishment of chalets, entrance gate, admin building/conference center and bulk services. 1. Muzi Pan Project is at procurement stage. Project start date 2023-10-13 and expected end date 2024-06-13. 2. Isibhubhu Project, Nongoma LM, Zululand DM - Refurbishment of a pavilion, change room, entrance gate. Construction of ablution facilities and internal road. 2. Isibhubhu Project Progress is at 80% (Q1 - 42%). Project start date 2023- 01-16 and expected end date 2023-09- 16. 6

  7. LIMPOPO Implementing Agent and Project Progress DBSA Provincial maintenance: state-owned assets - 1. Makapans Valley WHS - Mogalakwena LM, Waterberg DM 1. Makapans Valley WHS PC achieved. Project start date 2023-01-16 and expected end date 2023-07-16. 2. Nwanedi Nature Reserve PC achieved. Project start date 2023-01-16 and expected end date 2023-07-16. 3. Blouberg Nature Reserve PC achieved. Project start date 2023-01-16 and expected end date 2023-07-16. 4. Musina Nature Reserve PC achieved. Project start date 2023-01-16 and expected end date 2023-07-16. 5. Modjadji Nature Reserve PC achieved. Project start date 2023-01-16 and expected end date 2023-07-16. 2. Nwanedi Nature Reserve Thulamela LM, Vhembe DM 3. Blouberg Nature Reserve Blouberg LM, Capricorn DM 4. Musina Nature Reserve Musina LM, Vhembe DM 5. Modjadji Nature Reserve Greater Letaba LM, Mopani DM * PC: Practical Completions: project is completed - it is a short period to deal with snags before final certificates are issued 7

  8. LIMPOPO (2) Implementing Agent and Project Progress DBSA Community-based (accommodation upgrading) 1. Phiphidi Thulamela LMVhembe DM 2. The Oaks Lodge, Maruleng LM, Mopani DM 3. Matsila Lodge, Collins Vhembe DM 4. VhaTsonga,Makhado LM,Vhembe DM 5. Ngove, 4km from Giyani, Greater Giyani LM,Mopani DM 6. Tisane, near Jane Furse, Makhuduthamaga LM,Sekhukune DM 7. Nandoni Dam, Collins Vhembe DM tourism Projects: development/ 1. Phiphidi Waterfall Concurrence to appoint contractor being processed. Project start date 2023-05-16 and expected end date 2024-03-16. 2. The Oaks Lodge Progress is at 36% (Q1 - 5%).Project start date 2023- 03-07 and expected end date 2024-02-07. 3. Matsila Lodge Progress is at 55% (Q1 - 25%). Project start date 2023- 01-25 and expected end date 2023-12-14. 4. VhaTsonga Project at tender stage. Project start date 2023-10-23 and expected end date 2024-04-23. 5. Ngove Progress is at 20% (Q1 - 5%) Project start date 2023-06-19 and expected end date 2024-05-19. 6. Tisane Progress is at 53% (Q1 - 22%). Project start date 2023-01-25 and expected end date 2023-12-24. 7. Nandoni Dam Concurrence to appoint contractor being processed. Project start date 2023-05-16 and expected end date 2024-05-16. 8. Tshathogwe Game Farm Progress is at 56% (Q1 - 32%.) Project start date 2022-09-09 and expected end date 2023-09-09. 9. Mapate Recreational Social Tourism Facility Progress is at 72% (Q1 - 47%).Project start date 2022-06-09 and expected end date 2023-06-16. 10. Mtititi Game Farm Progress is at 89% (Q1 - 75%). Project start date 2022-06-10 and expected end date 2023-06-10. 11.Royal Khalanga Project Progress is at 26% (Q1 - 5%).Project start date 2023-04-25 and expected end date 2024-03-25. Waterfall, near Thohoyandou, Chabane LM, Chabane LM, 8. Tshathogwe Game Farm, Makhado LM, Vhembe DM Mapate Recreational Social Tourism Facility Thulamele LM,Vhembe DM 10. Mtititi Game Farm (Collins Chabane LM, Vhembe DM) 11. Royal Khalanga Project (Greater Tzaneen LM,Mopani DM 9. 8

  9. MPUMALANGA Implementing Agent and Project Progress DBSA Provincial state-owned assets maintenance 1. Manyeleti Enhlanzeni DM 2. Andover Enhlanzeni DM 3. Songimvelo Nature Reserve Chief Albert Luthuli LM, Gert Sibande DM 4. SS Skosana Nature Reserve Thembisile Hani LM, Nkangala DM Nature Reserve Bushbuckridge LM, 1. Manyeleti Nature Reserve PC* achieved. Project start date 2023-01-16 and expected end date 2023-07-16. 2. Andover Nature Reserve PC achieved. Project start date 2023-01-16 and expected end date 2023-07-16. 3. Songimvelo Nature Reserve PC achieved. Project start date 2023-01-16 and expected end date 2023-07-16. 4. SS Skosana Nature Reserve PC achieved. Project start date 2023-01-16 and expected end date 2023-07-16. Nature Reserve - Bushbuckridge LM, * PC: Practical Completions: project is completed - it is a short period to deal with snags before final certificates are issued DBSA Community-based tourism Project 1. Numbi Gate - Nkambeni Safari Lodge - Construction of a new Community Centre outdoor tourism activities. 1. Numbi Gate (Nkambeni Safari Lodge) Progress is at 8% (Q1 - 5%). Project start date 2023-04-26 and expected end date 2024-03-26. 2. Numbi Gate (Mdlhuli Safari Lodge) Progress is at 12% (Q1 - 5%). Project start date 2023-04-26 and expected end date 2024-03-26. 2. Numbi Gate - Mdlhuli Safari Lodge Construction of a new Cultural Centre 9

  10. NORTHERN CAPE ImplementingAgent and Project Progress DBSA Community-basedTourism Projects: 1. Platfontein Lodge, 17km from Kimberley, Sol Plaatje LM,Frances Baard DM - Construction/refurbishment of accommodation facilities. 1. Platfontein Lodge Specialist studies have been commissioned in order to inform the final concept report. Project start date to and end date to be determined. 2. Kamiesburg This is a heritage site and detailed specialist studies are required, therefore the Design Development report is expected in December 2023. Project to commence on the 2023-12-19 and end date to be determined. 2. Kamiesburg, Kamiesburg LM, Roodebergskloof Farm - Construction of chalets, kitchen, restaurant and pool. 10

  11. NORTH WEST Implementing Agent and Project Progress DBSA Community-based tourism Projects: 1. Manyane Mahikeng LM, Ngaka Modiri Molema DM - Refurbishment of chalets, admin block, hall and swimming pool. Lodge, Mafikeng Game Reserve 1. Manyane completed but the project needed to be retendered. Project start date 2023-10-30 and expected end date 2024-04-30. Lodge Tender evaluation had been 2. Lotlamoreng Dam, Mahikeng LM, Ngaka Modiri Molema DM - Construction of day visitor facility. 2. Lotlamoreng Dam The project to be retendered. Project start date 2023-11-05 and expected end date 2024-05-05. 3. NW-Lehurutshe Bird and Trophy Hunting - Ramotshere Moiloa LM, Ngaka Modiri Molema DM - Refurbishment construction of meat processing area, bulk services 3. Lehurutshe evaluation stage. Project start date 2023-09-22 and expected end date 2024-03-22. Bird and Trophy Hunting Tender of tented chalets, 11

  12. WESTERN CAPE (1) Implementing Agent and Project Progress DBSA Provincial state-owned assets - maintenance: 1. Lookout Hill - Khayelitsha, City of Cape Town Metropolitan Council 1. Lookout Hill PC* achieved. Project start date 2022-12-14 and expected end date 2023-06-14. De Hoop Nature Reserve PC achieved. Project start date 2022-12-14 and expected end date 2023-06-14. Cederberg Wilderness Area PC achieved. Project start date 2022-12-14 and expected end date 2023-06-14. Goukamma Nature Reserve PC achieved. Project start date 2022-12-14 and expected end date 2023-06-14. Kogelberg Nature Reserve PC achieved. Project start date 2022-12-14 and expected end date 2023-06-14. Wolwekloof Nature Reserve PC achieved. Project start date 2022-12-14 and expected end date 2023-06-14. 2. De Hoop Nature Reserve Cape Agulhas LM, Overberg DM 2. 3. Cederberg Wilderness Area Cedarberg LM, West Coast District 3. 4. Goukamma Nature Reserve - George LM, Garden Route DM 4. 5. Kogelberg Nature Reserve Overstrand LM, Overberg DM 5. 6. Wolwekloof Nature Reserve City of Cape Town Metropolitan Council * PC: Practical Completions: project is completed - it is a short period to deal with snags before final certificates are issued 6. 12