Serco Business Illahee Tire Reef Cleanup Phase 2 Project Overview

Slide Note
Embed
Share

Serco Business, in collaboration with Port of Illahee, is undertaking a tire reef cleanup project as mandated by regulatory requirements. The project involves removing clumps of tires near Illahee pier, evaluating water quality impacts, and establishing best practices for removal. The methodology includes divers securing and removing tire clumps using rigging equipment, with detailed logistics and stakeholder involvement outlined. Water quality monitoring will also be conducted to assess turbidity levels throughout the project.


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.



Uploaded on Apr 05, 2024 | 0 Views


Presentation Transcript


  1. Serco Business Illahee Tire Reef Cleanup (Phase 2) 10 January 2024 PORT OF ILLAHEE Safer, Smarter, Better | Reimagining Government Together 1

  2. Serco Business History Port of Illahee has been mandated to remove tire reef structure by November 2028 as a condition of their DNR Lease. 25 October 2023- Serco conducted detailed Sonar Survey and ROV (visual) inspection of tire reef structure near Illahee pier. 138 clumps located Clumps secured by yellow poly line 12-20 tires per clump 60,000-100,000 lbs of tires for removal 2

  3. Serco Business Project Goals Conduct a test removal of 1-3 tire clumps (324-1620lbs) Assess the impact of removal to water quality (turbidity) Evaluate removal best practices Determine overall removal project timeline and cost Meeting Goals Establish the Statutory and Regulatory requirements for completion of this project Determine Stakeholder Roles & Responsibilities Define Realistic project timeline and milestones 3

  4. Serco Business Removal Methodology Divers from Kitsap Underwater Search and Rescue Volunteer will secure an individual clump using hard rigging (chain) and disconnect the clump from the neighboring reef structure Floatation will be attached to the chain and inflated to break bottom suction Tire clump will be brought to the surface and tied off to cleats at the Illahee pier Lines will be used to pull the clump to the boat launch area at the pier Rigging and inflation will be removed and tires will be transported to an on site dumpster for removal Time Frame 8 hrs Roles and Responsibilities On site supervision Serco Diver Support USRV Kitsap Disposal Serco Pier access Port of Illahee Labor Port of Illahee 4

  5. Serco Business Removal Logistics USRV Kitsap has all appropriate lifting and rigging gear Disposal will be coordinated through Kitsap public works Assistance from Port volunteers to move tires from waterline to dumpster is needed Media presence is at the discretion of the onsite supervisor (SAFETY) 5

  6. Serco Business Water Quality Monitoring o Insitu turbidity monitoring to be installed by SERCO prior to removal operations and left in place to monitor through two tidal exchanges. This will allow us to show the rate of dissipation that can be expected following a removal from this site. o Four monitoring buoys are proposed Each bouy will be configured with turbidity sensors at 1 ft, 10ft and 20ft below the water line to capture turbidity at depth. 6

  7. Serco Business Post Monitoring 2-4 weeks following removal side imaging sonar survey and ROV inspection will be completed to assess the impact of removal activities. 7

  8. Serco Business Regulatory Stake holders o Washington Department of Fish Wildlife o Washington Department of Natural Resources o Washington Department of Ecology o Kitsap County Department of Community Development o Army Corps of Engineers 8

  9. Serco Business Non Regulatory Stake Holders o Washington Autonomous Vehicle Cluster (WAV-C) o Port of Illahee o Suquamish Tribe PORT OF ILLAHEE 9

  10. Serco Business Permitting & notifications Hydraulic Project Approval (WDFW) Section 401 Water Quality Certification (Ecology) Shoreline Substantial Development Permit (Kitsap County) Army Corps Nation-wide permit 27 (Army Corps) Notice to Mariners (US Coast guard) Property owner notifications (Port of Illahee) Local Media Outlets (WAV-C) 10

  11. Serco Business Project Time Line Removal slated for Summer 2024 to minimize impacts to forage fish spawning windows. Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 Jul 2024 Jun 2024 Aug 2024 Budgeting Pre-Removal Activities -Public Outreach -Turbidity baseline measurements -SERCO to weigh Requirements, Consumables, and Labor to accomplish removal. -Quote to be provided through WAV-C Post-Removal Activities -Site Survey -ROV Inspection -Final Report -Cost analysis for full removal Initial Stakeholder meeting -Establish Program Requirements -Identify Knowledge Gaps Go/ No Go Removal -Permit Applications to meet removal timeline 11

  12. Serco Business Questions 12