TXDOT - HOUSTON DISTRICT

 
 
TXDOT – HOUSTON
DISTRICT
MONTGOMERY AREA OFFICE
Suggested uses: Presentations on policy issues.
 
SL 494 – Project Overview
Widen and reconstruct
Roadway
Upgrade Intersection
at Kingwood Dr.
Improve Drainage and
add sidewalks
Project began July
2019
Estimated Completion
Date:
   3rd Quarter 2021
Project Begin
Project End
 
SL 494 – Construction Phasing
Phase 1
Construct Temporary
Pavement Widening
east side of SL 494
Construct Temporary
Pavement Overlay of
Kingwood Intersection
 
SL 494 – Construction Phasing
Phase 2
Move traffic utilizing
existing pavement and
Phase 1 temporary
pavement widening.
Regrade west ditch and
install proposed storm
sewer trunk line.
Construct embankment,
lime subgrade, stabilized
base, bond breaker, and
concrete pavement.
 
SL 494 – Construction Phasing
Phase 3
Move traffic to Phase 2
new pavement.
Regrade west ditch and
install proposed storm
sewer trunk line.
Construct embankment,
lime subgrade,
stabilized base, bond
breaker, and concrete
pavement.
Move traffic to final
location
 
SL 494
Widen Roadway
starting at
Northpark Plaza
Improve Drainage
 
SL 494
Widen Roadway
Improve Drainage
Replace Driveways
Add Center Median
 
SL 494 – Contact Information
 
 Adam C. Galland, PE
TxDOT Montgomery Area Office
901 North FM 3083
Conroe, Tx. 77303
(936)-538-3300
Kelly Kirby  Cell: 928-254-0019
Consultant PM
Eric Bednarsky Cell: 713-412-3941
TxDOT PM
Slide Note
Embed
Share

This project involves widening and reconstructing SL 494, starting at Northpark Plaza in Montgomery area. It includes upgrading the intersection at Kingwood Dr., improving drainage, adding sidewalks, and enhancing roadway infrastructure. The construction is divided into phases aimed at enhancing traffic flow and stormwater management for a safer and more efficient transportation system. Contact information for project managers and consultants is provided for inquiries and updates on the progress.

  • Roadway Project
  • Montgomery Area
  • Construction Phases
  • Drainage Improvement
  • Traffic Management

Uploaded on Feb 17, 2025 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. TXDOT TXDOT HOUSTON HOUSTON DISTRICT DISTRICT MONTGOMERY AREA OFFICE

  2. SL 494 Project Overview Widen and reconstruct Roadway Project Begin Upgrade Intersection at Kingwood Dr. Improve Drainage and add sidewalks Project began July 2019 Estimated Completion Date: 3rd Quarter 2021 Project End

  3. SL 494 Construction Phasing Phase 1 Construct Temporary Pavement Widening east side of SL 494 Construct Temporary Pavement Overlay of Kingwood Intersection

  4. SL 494 Construction Phasing Phase 2 Move traffic utilizing existing pavement and Phase 1 temporary pavement widening. Regrade west ditch and install proposed storm sewer trunk line. Construct embankment, lime subgrade, stabilized base, bond breaker, and concrete pavement.

  5. SL 494 Construction Phasing Phase 3 Move traffic to Phase 2 new pavement. Regrade west ditch and install proposed storm sewer trunk line. Construct embankment, lime subgrade, stabilized base, bond breaker, and concrete pavement. Move traffic to final location

  6. SL 494 Widen Roadway starting at Northpark Plaza Improve Drainage

  7. SL 494 Widen Roadway Improve Drainage Replace Driveways Add Center Median

  8. SL 494 Contact Information Adam C. Galland, PE TxDOT Montgomery Area Office 901 North FM 3083 Conroe, Tx. 77303 (936)-538-3300 Kelly Kirby Cell: 928-254-0019 Consultant PM Eric Bednarsky Cell: 713-412-3941 TxDOT PM

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#