Seafield WwTW Strategic Odour Review Summary

Slide Note
Embed
Share

Summary of strategic odour review recommendations for Seafield Wastewater Treatment Works (WwTW) includes short-term, medium-term, and long-term measures such as operational improvements, communications enhancements, and site redevelopment strategies presented by Wood plc.


Uploaded on Sep 17, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Seafield WwTW Strategic Odour Review 28thSeptember 2018 woodplc.com

  2. Check on Progress of Recommended Measures Implementation 2

  3. Summary of March 2018 Report Recommendations 12 short-term measures Seafield & Network; 4 engineering feasibility studies Contingency dosing plan 2 ventilation & air balance flow investigations Intermediate wastewater treatment Wallyford Nutriox dosing H2S Monitoring Further septicity investigations Ropeworks vent chimney 3 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  4. Summary of March 2018 Report Recommendations 4 medium-term measures; Conversion of storm tanks Redevelopment of sludge cake building Additional sludge storage capacity Replace PSTs All dependent upon outcomes of engineering feasibility studies 4 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  5. Summary of March 2018 Report Recommendations 2 long-term measures; Vision & strategy for a re-developed, sustainable Seafield site Relocate wastewater and sludge treatment to a new location Both of the above also dependent upon outcomes of feasibility studies and other, wider Edinburgh-wide and national population growth matters 5 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  6. Summary of March 2018 Report Recommendations 7 operational improvement measures; Additional on-site H2S monitoring and limit values Annual odour emissions surveys Improved weather forecasting system HAZOP-type approach for process change odour risks Tanker driver odour awareness training Internal workshops to enhance OMP 6 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  7. Summary of March 2018 Report Recommendations 3 communications improvement measures; More interactive and meaningful web site Real-time odour dispersion model display Enhanced complaints handling & response system 7 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  8. What is the state of progress on these measures? 8

  9. Summary of Progress Status September 2018 12 short-term recommendations; 1 completed (Wallyford); 8 have been commissioned and are under way, with reporting dates in October/November 2018; 1 assessed in detail and rejected (MEPS ferric dosing) 2 to be started (Ropeworks & further septicity surveys) 9 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  10. Summary of Progress Status September 2018 4 medium-term measures; All dependent upon the outcomes of engineering feasibility studies 10 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  11. Summary of Progress Status September 2018 2 long-term measures; Both in the early stages of pre-feasibility Dependent upon the outcomes of engineering feasibility studies and further consideration of Edinburgh-wide and national population growth and development 11 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  12. Summary of Progress Status September 2018 7 operational improvement measures; 1 completed (Tanker drivers training) 5 under way 1 under review (odour surveys) 12 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  13. Summary of Progress Status September 2018 3 communications improvement measures; All 3 under way 13 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  14. Summary of Progress Status September 2018 5 completed 17 in progress 6 to be commenced (4 dependent upon outcome of feasibility studies) 14 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  15. Additional Items Dosing trials with KMnO4 To be carried out at SWH facility at Bo ness Commencing 1/10/2018 for 4/5 weeks Further investigation of the sewer network around Seafield feeding-into the Siphon House Bow-Tie risk analysis of proposed process changes 15 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  16. Thank you 16 A presentation by Wood.

More Related Content