Seafield WwTW Strategic Odour Review Summary

Seafield WwTW
Strategic Odour
Review
28
th
 September 2018
2
Check on Progress of Recommended
Measures Implementation
 
12 short-term measures – Seafield & Network;
4 engineering feasibility studies
Contingency dosing plan
2 ventilation & air balance flow investigations
Intermediate wastewater treatment
Wallyford  Nutriox dosing
H2S Monitoring
Further septicity investigations
Ropeworks vent chimney
Summary of March 2018 Report Recommendations
3
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
4 medium-term measures;
Conversion of storm tanks
Redevelopment of sludge cake building
Additional sludge storage capacity
Replace PSTs
All dependent upon outcomes of engineering feasibility
studies
Summary of March 2018 Report Recommendations
4
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
2 long-term measures;
Vision & strategy for a re-developed, sustainable
Seafield site
Relocate wastewater and sludge treatment to a new
location
Both of the above also dependent upon outcomes of
feasibility studies and other, wider Edinburgh-wide and
national population growth matters
Summary of March 2018 Report Recommendations
5
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
7 operational improvement measures;
Additional on-site H
2
S monitoring and limit values
Annual odour emissions surveys
Improved weather forecasting system
HAZOP-type approach for process change odour risks
Tanker driver odour awareness training
Internal workshops to enhance OMP
Summary of March 2018 Report Recommendations
6
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
3 communications improvement measures;
More interactive and meaningful web site
Real-time odour dispersion model display
Enhanced complaints handling & response system
Summary of March 2018 Report Recommendations
7
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
8
What is the state of progress on these measures?
12 short-term recommendations;
1 completed (Wallyford);
8 have been commissioned and are under way, with
reporting dates in October/November 2018;
1 assessed in detail and rejected (MEPS ferric dosing)
2 to be started (Ropeworks & further septicity surveys)
Summary of Progress Status September 2018
9
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
4 medium-term measures;
All dependent upon the outcomes of engineering
feasibility studies
Summary of Progress Status September 2018
10
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
2 long-term measures;
Both in the early stages of pre-feasibility
Dependent upon the outcomes of engineering
feasibility studies and further consideration of
Edinburgh-wide and national population growth and
development
Summary of Progress Status September 2018
11
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
7 operational improvement measures;
1 completed (Tanker drivers’ training)
5 under way
1 under review (odour surveys)
Summary of Progress Status September 2018
12
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
3 communications improvement measures;
All 3 under way
Summary of Progress Status September 2018
13
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
5 completed
17 in progress
6 to be commenced (4 dependent upon outcome of
feasibility studies)
Summary of Progress Status September 2018
14
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
Dosing trials with KMnO4
To be carried out at SWH facility at Bo’ness
Commencing 1/10/2018 for 4/5 weeks
Further investigation of the sewer network around Seafield
feeding-into the Siphon House
“Bow-Tie” risk analysis of proposed process changes
Additional Items
15
A presentation by Wood.
Seafield WwTW Check on Measures Implementation
16
A presentation by Wood.
Thank you
 
Slide Note
Embed
Share

Summary of strategic odour review recommendations for Seafield Wastewater Treatment Works (WwTW) includes short-term, medium-term, and long-term measures such as operational improvements, communications enhancements, and site redevelopment strategies presented by Wood plc.

  • Seafield
  • Odour Review
  • Wastewater Treatment
  • Strategic Measures

Uploaded on Sep 17, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. Seafield WwTW Strategic Odour Review 28thSeptember 2018 woodplc.com

  2. Check on Progress of Recommended Measures Implementation 2

  3. Summary of March 2018 Report Recommendations 12 short-term measures Seafield & Network; 4 engineering feasibility studies Contingency dosing plan 2 ventilation & air balance flow investigations Intermediate wastewater treatment Wallyford Nutriox dosing H2S Monitoring Further septicity investigations Ropeworks vent chimney 3 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  4. Summary of March 2018 Report Recommendations 4 medium-term measures; Conversion of storm tanks Redevelopment of sludge cake building Additional sludge storage capacity Replace PSTs All dependent upon outcomes of engineering feasibility studies 4 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  5. Summary of March 2018 Report Recommendations 2 long-term measures; Vision & strategy for a re-developed, sustainable Seafield site Relocate wastewater and sludge treatment to a new location Both of the above also dependent upon outcomes of feasibility studies and other, wider Edinburgh-wide and national population growth matters 5 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  6. Summary of March 2018 Report Recommendations 7 operational improvement measures; Additional on-site H2S monitoring and limit values Annual odour emissions surveys Improved weather forecasting system HAZOP-type approach for process change odour risks Tanker driver odour awareness training Internal workshops to enhance OMP 6 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  7. Summary of March 2018 Report Recommendations 3 communications improvement measures; More interactive and meaningful web site Real-time odour dispersion model display Enhanced complaints handling & response system 7 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  8. What is the state of progress on these measures? 8

  9. Summary of Progress Status September 2018 12 short-term recommendations; 1 completed (Wallyford); 8 have been commissioned and are under way, with reporting dates in October/November 2018; 1 assessed in detail and rejected (MEPS ferric dosing) 2 to be started (Ropeworks & further septicity surveys) 9 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  10. Summary of Progress Status September 2018 4 medium-term measures; All dependent upon the outcomes of engineering feasibility studies 10 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  11. Summary of Progress Status September 2018 2 long-term measures; Both in the early stages of pre-feasibility Dependent upon the outcomes of engineering feasibility studies and further consideration of Edinburgh-wide and national population growth and development 11 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  12. Summary of Progress Status September 2018 7 operational improvement measures; 1 completed (Tanker drivers training) 5 under way 1 under review (odour surveys) 12 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  13. Summary of Progress Status September 2018 3 communications improvement measures; All 3 under way 13 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  14. Summary of Progress Status September 2018 5 completed 17 in progress 6 to be commenced (4 dependent upon outcome of feasibility studies) 14 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  15. Additional Items Dosing trials with KMnO4 To be carried out at SWH facility at Bo ness Commencing 1/10/2018 for 4/5 weeks Further investigation of the sewer network around Seafield feeding-into the Siphon House Bow-Tie risk analysis of proposed process changes 15 A presentation by Wood. Seafield WwTW Check on Measures Implementation

  16. Thank you 16 A presentation by Wood.