Review of I-195 Washington Bridge Findings on March 14, 2024

 
I-195 Washington Bridge
 
Findings Review
March 14, 2024
 
McNary Bergeron & Johannesen
Structural engineering firm
Specializing in design and construction engineering
for bridges
 
Providing
Independent peer review
Technical advisor for the Rhode Island Department
of Administration
 
Decision to close the bridge was the right and responsible decision
 
Bridge condition was reviewed
including:
In-depth inspection and testing
Modeling and analysis
 
Identified additional structural
deficiencies
 
Multiple options for repairing and
strengthening were reviewed
Replacing tie-rods
Strengthening piers / girders
 
Determined that several elements of
the bridge cannot be viably repaired
 
 
 
Recommended to replace the bridge superstructure (deck and girders)
 
Replace part or all of the substructure (piers and foundations)
Next Step: Procure contractor / engineering
Demolition of the existing bridge
Design-Build construction of the new bridge
 
$250M to $300M estimated cost
Schedule and cost will be updated with selected Design-Build Team
 
I-195 Washington Bridge
 
Findings Review
March 14, 2024
Slide Note
Embed
Share

Structural engineering firm, McNary Bergeron & Johannesen, reviewed the condition of the I-195 Washington Bridge and recommended replacing the superstructure and part or all of the substructure due to identified deficiencies. The decision to close the bridge was deemed responsible. Multiple repair options were considered, with the next steps involving procuring contractors for demolition and construction at an estimated cost of $250-300 million.

  • Bridge review
  • Structural engineering
  • Bridge replacement
  • Infrastructure
  • Construction

Uploaded on Sep 28, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. I-195 Washington Bridge Findings Review March 14, 2024

  2. McNary Bergeron & Johannesen Structural engineering firm Specializing in design and construction engineering for bridges Providing Independent peer review Technical advisor for the Rhode Island Department of Administration

  3. Decision to close the bridge was the right and responsible decision

  4. Bridge condition was reviewed including: In-depth inspection and testing Modeling and analysis Identified additional structural deficiencies

  5. Multiple options for repairing and strengthening were reviewed Replacing tie-rods Strengthening piers / girders Determined that several elements of the bridge cannot be viably repaired

  6. Recommended to replace the bridge superstructure (deck and girders) Replace part or all of the substructure (piers and foundations)

  7. Next Step: Procure contractor / engineering Demolition of the existing bridge Design-Build construction of the new bridge $250M to $300M estimated cost Schedule and cost will be updated with selected Design-Build Team

  8. I-195 Washington Bridge Findings Review March 14, 2024

More Related Content

giItT1WQy@!-/#