Project Completion Guidelines and Records Management

PROJECT DEATH
Stephanie Rich
Corrective Work
Punch List
Work Complete Date
Request Final(s)
Comprehensive Final Inspection Report
All work complete, Request Formal
Acceptance
Various Final Inspections
Contact Central Office Construction
Liaison
If you had a submittal, you need a
Final Inspection.
Comprehensive Final
Compile All Final Inspections
Issue Comprehensive Final Inspection
Report
Start the Clock
Demobilization
25% Upon Formal Acceptance
 
50% When the Final is Submitted to the
D.O.
 
25% on the Final Estimate
  
* Keep each funding line balance of
at least $1,000 until the Final Estimate.
As Builts
Send them in with or soon after the
Final is submitted to Central Office.
We are currently accepting mylar or
electronic micro station copies
Formal Acceptance
Ditches should drain
All Corrective Work is complete
Corrective Work Complete Date in
SiteManager
Request Formal from the Central
Office Construction Liaison
FHWA Full Oversight
IM, NH, APD, ARRA in the Project number –
usually interstates, parkways, Appalachian
Development Projects or ARRA projects.
 
Records must be maintained 3 Years from FHWA
Reimbursement to KYTC - If in doubt call me!
 
Looking at a way to inform the construction
crew offices when projects are closed out.
FEMA PROJECTS
Records must be maintained until they
are audited by FEMA (Usually
performed when they are in town for a
subsequent disaster)
Resurfacing Projects
Records can be destroyed as soon as
the final estimate is paid to the
contractor.
  
- Indicated by physical Work
Complete
  
  Date in the Critical Dates of
  
  Sitemanager
Grade & Drain Projects that are
not Direct FHWA Oversight
Records must be maintained for three
years after the contractor is paid the
final estimste
Indicted by the physical work complete
date in the Critical Dates of Sitemanager
Contract End
Open to Traffic Date is needed even
when the contract has always been
open to traffic.
After time charges have stopped, Final
Inspections take place.
After Formal Acceptance, final checking
begins.
Purpose of Final checking---to make it
easy for someone with no experience in
construction to verify the quantities paid.
Checking Final Quantities
Make sure there are last load tickets for
every weighed quantity paid.
Make sure all other quantities are justified
by drawings, measurements, or other
means to verify the quantity paid.
Make sure all DWRs are approved on
Diaries.
Material certification then takes place.
The files are sent to the District Office.
To the District and Beyond
The District Office Final Processor checks the quantities in the
same manner as the Section Office.
Starting with verifying weigh tickets, through all the
documentation of all other quantities.
Verifying if LDs are applicable and all material certification are
completed.
District Office sends a copy of the final quantities to the
Contractor for 14 day review.
Central Office Estimate Section is notified and completes the
verification of quantities.
Final Release is sent to the contractor for signature.
Final Release is returned to Central Office and Contractor is
paid.
Contract is closed in SiteManager when Final payment is
made and the Physical Work Complete Date is entered.
Maintenance
Design Meetings
Ditches should drain
It’s yours bed to lay in
Post Construction Reviews
Slide Note
Embed
Share

This document outlines the steps and requirements for completing construction projects, including inspections, final documentation, demobilization, and recordkeeping guidelines. It covers aspects such as formal acceptance, final inspections, demobilization procedures, submission of as-builts, and specific record retention requirements for various types of projects like FHWA and FEMA projects.

  • Construction Projects
  • Completion Guidelines
  • Recordkeeping
  • Final Inspections
  • Project Management

Uploaded on Oct 06, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. PROJECT DEATH Stephanie Rich

  2. Corrective Work Punch List Work Complete Date Request Final(s) Comprehensive Final Inspection Report All work complete, Request Formal Acceptance

  3. Various Final Inspections Contact Central Office Construction Liaison If you had a submittal, you need a Final Inspection.

  4. Comprehensive Final Compile All Final Inspections Issue Comprehensive Final Inspection Report Start the Clock

  5. Demobilization 25% Upon Formal Acceptance 50% When the Final is Submitted to the D.O. 25% on the Final Estimate * Keep each funding line balance of at least $1,000 until the Final Estimate.

  6. As Builts Send them in with or soon after the Final is submitted to Central Office. We are currently accepting mylar or electronic micro station copies

  7. Formal Acceptance Ditches should drain All Corrective Work is complete Corrective Work Complete Date in SiteManager Request Formal from the Central Office Construction Liaison

  8. FHWA Full Oversight IM, NH, APD, ARRA in the Project number usually interstates, parkways, Appalachian Development Projects or ARRA projects. Records must be maintained 3 Years from FHWA Reimbursement to KYTC - If in doubt call me! Looking at a way to inform the construction crew offices when projects are closed out.

  9. FEMA PROJECTS Records must be maintained until they are audited by FEMA (Usually performed when they are in town for a subsequent disaster)

  10. Resurfacing Projects Records can be destroyed as soon as the final estimate is paid to the contractor. - Indicated by physical Work Complete Date in the Critical Dates of Sitemanager

  11. Grade & Drain Projects that are not Direct FHWA Oversight Records must be maintained for three years after the contractor is paid the final estimste Indicted by the physical work complete date in the Critical Dates of Sitemanager

  12. Contract End Open to Traffic Date is needed even when the contract has always been open to traffic. After time charges have stopped, Final Inspections take place. After Formal Acceptance, final checking begins. Purpose of Final checking---to make it easy for someone with no experience in construction to verify the quantities paid.

  13. Checking Final Quantities Make sure there are last load tickets for every weighed quantity paid. Make sure all other quantities are justified by drawings, measurements, or other means to verify the quantity paid. Make sure all DWRs are approved on Diaries. Material certification then takes place. The files are sent to the District Office.

  14. To the District and Beyond The District Office Final Processor checks the quantities in the same manner as the Section Office. Starting with verifying weigh tickets, through all the documentation of all other quantities. Verifying if LDs are applicable and all material certification are completed. District Office sends a copy of the final quantities to the Contractor for 14 day review. Central Office Estimate Section is notified and completes the verification of quantities. Final Release is sent to the contractor for signature. Final Release is returned to Central Office and Contractor is paid. Contract is closed in SiteManager when Final payment is made and the Physical Work Complete Date is entered.

  15. Maintenance Design Meetings Ditches should drain It s yours bed to lay in Post Construction Reviews