Overview of SiD Workshop Summary and DBD Planning
The SiD Workshop at the University of Oregon in November 2010 focused on the Summary of DBD Planning by Andy White. Key points covered included the timeline from Fall 2007 to End 2012, the Detailed Baseline Design DBD with nine crucial points, guidance for DBD presenters, and the importance of finalizing detector optimization and simulation software for progress in detector R&D. The workshop highlighted the necessary steps and deadlines to achieve successful outcomes in detector research and development.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
SiD Workshop University of Oregon November 2010 Summary of DBD Planning Andy White
Where we are Fall 2007: Call for LOIs was made by ILCSC Mar.2008: IDAG formed & 3 LOI groups known 2007 RDR 2008 2009 Mar.2009: 3 LOIs submitted Summer 2009: IDAG recommendation Oct 2009: Work plan of the validated groups Mar:2009: IDAG began monitoring the groups End 2010: Interim report to be produced 2010 Now 2011 2012 End 2012: Detailed Baseline Design Report 2010/11/15 S.Yamada SiD WS@Eugene 2
The Detailed Baseline Design DBD - The Nine Points 1.Demonstrate proof of principle on critical components. When there are options, at least one option for each subsystem will reach a level of maturity which verifies feasibility. 2.Define a feasible baseline design. While a baseline will be specified, options may also be considered. 3.Complete basic mechanical integration of the baseline design accounting for insensitive zones such as the beam holes, support structure, cables, gaps or inner detector material. 4.Develop a realistic simulation model of the baseline design, including the identified faults and limitations. 5.Develop a push-pull mechanism, working out the movement procedure, time scale, alignment and calibration schemes in cooperation with relevant groups. 6.Develop a realistic concept of integration with the accelerator including the IR design. 7.Simulate and analyze updated benchmark reactions with the realistic detector model. Include the impact of detector dead zones and updated background conditions. 8.Simulate and study some reactions at 1 TeV, including realistic higher-energy backgrounds, demonstrating the detector performance. 9.Develop an improved cost estimate.
Guidance for DBD Presenters A list of critical R&D that remains to be done in time for inclusion in the DBD at the end of 2012. Resources (personnel, financial, material) that you need to achieve completion of the critical R&D and any problems that you see their provision. A best-estimate of the timeline for the critical R&D. A re-statement of the baseline technology and the expected status of options. The status of the conceptual engineering. The status and expected evolution of the subsystem in the SiD simulation.
DBD Planning Thank you! to those who provided the reports, DBD related planning information at this meeting. It is clear that predicting where we will be in detector R&D, simulation, conceptual engineering in 2012 is not so easy this meeting has given us a first view. However, in order to make progress we need to fix certain deadlines: - Finalize detector optimization - Freeze global parameters - Complete final DBD simulation software - Complete testing of simulation, reconstruction - Begin event generation for benchmarks - Begin analyses of benchmarks
Detector Optimization MIT group engaged in systematic study of HCal variants based on simplified SiD geometries using slic + SiD PFA (R. Cowan report at next PFA mtg.). extending studies done for the LOI by Marcel Stanitzki using Mokka + MarlinReco (SiD-ish) primarily studying HCal depth and layout. Should we engage in a similar global exercise? Tracker layouts Detector aspect ratios Ecal design HCal absorber materials, layout, readout technologies. 6
SiD Optimizations ECal resolution could be improved with thicker Si ECal thickness ( cost) could be reduced ECal/Hcal separation is somewhat artificial Excellent high energy , e+/- response with analog HCal Octagonal Barrel geometry reduces number of phi cracks reduces amount of overlap in EM staves Is Tracker layout Optimal? Pixel Tracker option very attractive Proposal: Goal to complete optimizations by SiD Workshop in Summer 2011 7
Reconstruction for the DBD Need to solve tracking problems. Need to implement corrections for additional realism . Run on sample at 1 TeV cm to identify additional problems. Verify algorithm improvements carry over to sidloi3. Goal: Completion of reconstruction software end 2011
Outline of Vertex Detector Work for DBD Sensor R&D Power delivery and distribution R&D Test LHC DC-DC converter: January 2010 September 2010 Test serial power scheme: April 2010 March 2011 Design pulsed power system: January 2011 September 2011 Fabricate and test pulsed power system: June 2011 September 2012 Support R&D Design, fabricate, and measure test support cylinder October 2010 March 2011 Design, fabricate, and measure module support test structures June 2010 December 2011 Thin ladder R&D Fabricate and measure thin ladders January 2010 June 2012 Alignment monitoring system Fabricate and test alignment monitoring system March 2010 September 2012 Bill Cooper Oregon Workshop - 15-17 November 2010 9
Outline of Tracker Mechanical Work for DBD Power delivery and distribution R&D Design pulsed power system: January 2011 August 2011 Determine locations of power conditioners: November 2010 August 2011 Develop air flow paths for cooling the power conditioners: April 2011 August 2011 Fabricate and test an R&D prototype with power sources and air flow: September 2011 December 2011 Mechanical Stability Evaluate impact of power cycling: June 2010 March 2011 Test vibrational stability of cylinders and test pulsed power system: April 2011 August 2011 Alignment with vertex detector Continue development of FSI: January 2010 December 2011 Bill Cooper Oregon Workshop - 15-17 November 2010 10
Tracking LOI demonstrated that an all-silicon tracker with ~10 hit measurements would give excellent performance at the ILC Substantial effort in developing a more realistic detector simulation is bearing fruit Forward tracking efficiency problem appears to have a kludge fix that is working Other issues: Charge asymmetry probably requires the Kalman filter fitter to be completed Large hit error in pixels may be due to noise setting being too large Duplicate tracks appear on occasion no easy solution Some events take a long time to complete no easy solution Misplaced hits too few strip / pixel readout bits?? Some of these issues require focused / concentrated effort difficult to achieve with present manpower situation Richard Partridge 11
Vertex + Tracking DBD Planning Re-instate the regular vertex+tracking meetings. Benefit from work deriving from CDR. Improvements for CDR drive timescale Any residual issues for DBD completion by end 2011.
HCal DBD Planning global issues - Depth inner radius fixed, outer radius? - N , number of layers optimization? By Summer 2011 - Cracks/stringers more studies - Projective/non-projective boundaries? - Module design (barrel, endcap) how many modules along barrel length? Module shape(s) in endcap? - Engineering layer design/deflections, module design integrity, support from coil - Services allowing space, dead material - Electronics - Power Several items affect completion of simulation end 2011
RPC DHCAL January/February 2011 at FNAL 4 weeks Configuration: Si-W ECAL + DHCAL with 38 layers + RPC TCMT ~April 2011 at FNAL 4 weeks Configuration: DHCAL with 38 layers + RPC TCMT Beyond Spring 2011 Need for TCMT at CERN (OK with us) Initiated discussions with W-HCAL for measurements with RPCs in 2012/3 (probably easier to move Tungsten than RPCs) Possibility for test beams at FNAL in 2012 (depends on continued running of the Tevatron) Ongoing data analyses, publication of papers 16
RPC DHCAL Expectations (very preliminary!) by end of 2012: - testing of a gas recycling system (in cooperation with CERN) - testing of a high voltage generation and distribution system, - possible tests of new approaches to low voltage distribution *depends on continued funding - development of 1-glass RPCs viability - DCAL IV chip development; power reduction; new technology; package thickness reduction. - development of gas distribution strategy different modules/orientations
RPC DHCAL Expectations (very preliminary!) by end of 2012: - Development of RPC assembly techniques appropriate to mass production - need significant mechanical engineering and prototyping schedule?? - Design of a wedge shape module: based on the above developments - produce a first concept of an integrated wedge-shaped module. -
Draft layout of HCal DBD section - Overview of HCal - PFA, Physics performance requirements - Front-end gas calorimeter signal simulation - HCal design: barrel, endcaps - Results of HCal optimization studies: depth, number of layers - Absorber choice(s). - Results of projective/non-projective crack studies - Statement of baseline, options - Description of baseline; design; prototype construction and test results; technical prototype design; engineering issues; - For each option: design; prototype results; technical implementation; - Continuing R&D beyond 2012. -
SiD SOLENOID MAJOR DESIGN TASKS (in order) 3D MAGNET FIELD CALCULATIONS FOR SOLENOID & DID COMBINED FIELDS AND FORCES (Nearly completed) DESIGN OF THE DID COIL AND INTEGRATION WITH THE SOLENOID STRUCTURAL ANALYSIS OF COIL PACKAGE, SUPPORTS AND VACUUM SHELL ASSEMBLY AND INSTALLATION PROCEDURES OVERALL TOLERANCES AND FINAL SIZE SPECIFICATIONS ENGINEERING DRAWINGS CRYOGENIC INTEGRATION OF THE SiD SOLENOID WITH QD0 CONDUCTOR R&D SiD Solenoid Status Update Wes Craddock / SLAC
Muon - RPC Goals for DBD Summarize RPC experience in BaBar - establishing RPC aging properties as adequate for expected background rates Study BESIII or variant RPCs as possible alternatives to traditional linseed oil design No identified manpower to extend detector/flux return designs No identified manpower to extend KPiX/ RPC designs Baseline choice?? 3/28/10 H. Band LCWS 10 21
Muons/Scintillator R&D Schedule FY11 FY12 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Muon detector drawings Procure and bench test PPDs Develop trigger counters WLS to new strips Assemble strips into plane Additional TB4 Bds assembled Bench tests of New TB4 boards Bench tests of new strips Beam tests of new strips/plane Travelers for strips & planes* Reports
FCal - DBD LumiCal No critical R&D for the DBD Alignment issue needs to be addressed in MDI Push-pull. BeamCal Radiation hard Silicon sensor R&D will be carried out by UC-Santa Cruz/SLAC. First prototype of FCAL chip has been fabricated and tested successfully. Need manpower to make progress. BeamCal simulation study will continue. 23
Event generation: Early 2012 Analysis starts: Spring 2012 24
SiD Benchmark Group Tasks 1) ILC Event Generation for DBD in Coordination with ILC Common Data Sample Group 2) Contribute to CLIC Physics Analysis of CDR Benchmark #5, Gaugino Production at 3 TeV (degree of participation still under consideration) 3) Perform 1 TeV Benchmark Analysis of 120 GeV Higgs Decay to gluon-gluon and WW* with Several SiD Detector Configurations for SiD Detector Optimization 4) Analyze DBD Benchmark Reactions 26
DBD Considerations Proposed timeline from now to March 2011: This meeting initial understanding of goals/timeline for next two years. By December 3 finalize list of DBD editors and agree on schedule for draft outline. By January 17 draft outline for each section of DBD Then use Advisory Board + Editors meetings to iterate. End of February 2011 Draft DBD Outline complete period of review/comment etc. by whole of SiD. March 2011 present DBD Outline at ALCPG11.