Michigan Interconnection Rules & Procedures Overview
Explore Michigan's interconnection rules, procedures, and standards for utility documents, covering aspects such as rulemaking, stakeholder involvement, application processes, timelines, and technical requirements.
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
Michigan Interconnection Rules Rules vs. Procedures Julie Baldwin June 20, 2019
Hierarchy of Interconnection Documents Laws Rules Procedures Utility Specific Documents (Business Practice Documents)
Rules Rules may also be referred to as standards. Generally, requirements that are applicable to all utilities must go through the rulemaking process. Incorporating a stakeholder process to develop a draft ruleset and formal rulemaking can take 24 months. Rules may include a waiver however, any waiver must not violate the law. Current MPSC Electric Interconnection and Net Metering Standards Definitions Laws Rules Procedures Utility Documents
Procedures The Generator Interconnection Procedures, Applications and Interconnection Agreements for Category 1 and 2 Projects (up to 150 kW) were approved by Commission Order. Commission approval process could take 6 12 months. Laws Rules Procedures Utility Documents
Consider Addressing in Rules Requirement that Interconnection Procedures be filed within 90 days for MPSC approval List of application Standards Pre-Application Report Fast Track Process Steps & Timelines Study Process Steps & Timelines Alternative Dispute Resolution Process Waiver Process
Consider Addressing in Procedures Fast Track Application List of documents required for completeness Study Process Application List of documents required for completeness System Impact Study Agreement Facilities Study Agreement Construction Agreement Interconnection Operating Agreement Fast Track and Study Process Application Fees System Impact Study Fees (phase I and II) Facilities Study Fees
Technical Matters for Procedures Energy Storage Voltage and Frequency Ride Through Settings (if not handled in utility documents) More items TBD
Matters for Utility Documents Voltage and Frequency Ride-through Settings (if not handled in procedures) Voltage and Reactive Power Control
Thank you! Questions?