Massachusetts SMART Program Overview

Slide Note
Embed
Share

The Massachusetts SMART Program provides a comprehensive overview covering agenda, safety measures, timelines, party responsibilities, key resources, and more. Learn about BTM vs. stand-alone systems, safety tips, program timelines, national grid numbers, block size, compensation, key resources, and who to contact for various issues. Stay informed on important dates and processes related to the program to ensure smooth operations and maximize incentives.


Uploaded on Aug 04, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Agenda Safety Message Timelines Responsibilities of the parties Overview Program Key Resources BTM vs Stand Alone Diagram Review 1

  2. Safety Message Extension Cord https://vividlearningsystems.com/extension-cord-safety- supervisor-safety-tip-series > 90 day solution in the workplace is prohibited but we can bring that home as well. Inspect Christmas lights and cords for Knicks cuts frays that could create a shock hazard. Fuses do not protect you from shock hazards; the fuse element does not open fast enough to prevent shock. Do not hide cords under rugs they could become frayed. 7 Children per day seek medical help for electrocution. 2

  3. TIMELINES Sept 26, 2018 DPU Smart Order released. Oct 26, EDC s Filed a go live date of Nov 26 Nov 1st, EDC s filed Individual Tariffs. Nov 7, 2018 End to End Review Nov 9, 2018 nCAP portal changes go live. Nov 12-21, 2018 Individual group trainings. Nov 26 Refresher if needed Nov 26-Dec 1st SPA portal opens accepts applications for Preliminary SOQ s 1-3 week review by DOER for approvals. Jan 2019 first incentive checks could be issued. No more than 3 billing cycles. 3

  4. TIMELINES 4

  5. National Grid Numbers 1368 Total Applications 69 BTM systems with ATI issued. 3 Stand Alone systems with ATI issued. Behind the Meter Complex 1104 43 1061 254 250 4 10 17.2 MW 9.2 MW 8.0 MW 443 MW 443 MW 12 KW 0 Simple Stand Alone Systems Complex Simple Blank 5

  6. Who You Gonna call? Issue type Primary point of contact General MA SMART Program questions Program / adder eligibility questions Incentive application status / process questions Interconnection application status / process questions Incentive rate calculation questions Incentive payment questions 6

  7. Block Size 7

  8. Block Compensation 8

  9. Key Resources National Grid Smart Solar Website http://www9.nationalgridus.com/masselectric/home/energyeff /4_smart.asp Clear Results Website http://masmartsolar.com/ DOER Overview Website https://www.mass.gov/solar-massachusetts-renewable- target-smart 9

  10. Key Distinction Behind-the-Meter Standalone System that serves on-site load other than parasitic or station load utilized to operate the unit System that serves no associated on-site load other than parasitic or station load utilized to operate the unit Behind the meter systems will be compensated differently than standalone systems 10

  11. Metering Views Metering Views < 60 kW = Watthr Meter > 60 kW = Interval Meters 11

  12. Metering Views 12

  13. BTM < 60 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 13

  14. BTM < 60 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 14

  15. BTM < 60 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 15

  16. BTM < 60 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 16

  17. BTM >60 kW to 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 17

  18. BTM >60 kW to 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 18

  19. BTM >60 kW to 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 19

  20. BTM >60 kW to 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 20

  21. BTM > 500 KW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 21

  22. BTM > 500 KW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 22

  23. BTM > 500 KW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 23

  24. Stand Alone < 60 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 24

  25. Stand Alone < 60 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 25

  26. Stand Alone < 60 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 26

  27. Stand Alone > 60 kW to < 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 27

  28. Stand Alone > 60 kW to < 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 28

  29. Stand Alone > 60 kW to < 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 29

  30. Stand Alone > 60 kW to < 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. In this particular project there will be two separate work orders (Case # s). One for the PV array and Battery. The other PV array by itself. 30

  31. Stand Alone > 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 31

  32. Stand Alone > 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 32

  33. Stand Alone > 500 kW Inspectors please note; you will be calling in one municipal inspection for all meter sockets. Do not call in one clear but think you are holding the other. 33

  34. What does this mean to me??? New Projects will be specified under the Impact study costs as a line item. In Flight projects will return under a new construction WR# returned to the same DPAM engineer to review and approve a cost. 34

  35. Contact Info Gerald (Jed) Ferris Smart Solar Program Manager National Grid 401 784-7364 Work 401 450-9416 Cell Gerald.Ferris@nationalgrid.com 245 South Main Street, Hopedale, MA. 35